City Corporation Limited projects in Pune
Our MahaRERA register holds 10 Pune projects by City Corporation Limited; 2 still being built or recently finished.
- Projects
- 10
- Homes listed
- 1,287
- Homes booked
- 1,211
- Completion date moved 3+ months
- 1 of 10
- by 24 months on average
City Corporation Limited's date record
1 of City Corporation Limited's 10 Pune projects with both dates on MahaRERA moved the completion date 3 months or more later, by 24 months on average.
- Amanora Gateway Towers 2moved 24 months later, now Apr 2022
How we count: the completion date the builder files with MahaRERA today against the one filed at registration. Moves under 3 months and MahaRERA's blanket extensions for all projects (4 months in 2026) are left out. MahaRERA does not publish handover dates, so a date that did not move is not proof of an on-time handover.
Projects being built
Finished more than a year ago
- Amanora Sweet Water Villa PlotsMagarpatta · possession filed Sep 2018 · 72/88 bookedMahaRERA P52100004890
- Amanora Gateway Towers 98 and 99Magarpatta · possession filed Dec 2018MahaRERA P52100000321
- Amanora Adreno TowersMagarpatta · possession filed Mar 2022MahaRERA P52100001822
- Amanora Gateway Towers 2Magarpatta · possession filed Apr 2022 · moved 24 months laterMahaRERA P52100000380
- Amanora Gold Towers 42 and 43Magarpatta · possession filed Dec 2023MahaRERA P52100017612
- Amanora Gold Towers 44, 45 and 46Magarpatta · possession filed May 2024MahaRERA P52100017962
- Amanora Ascent AvenueMagarpatta · possession filed Sep 2025 · 91/131 booked · moved 2 months laterMahaRERA P52100047453
- Amanora Ascent Towers 48 and 49Magarpatta · possession filed Sep 2025MahaRERA P52100030032
Questions buyers ask
How many projects does City Corporation Limited have in Pune?
MahaRERA lists 10 Pune projects by City Corporation Limited in our register (towers and phases counted once); 2 are being built or recently finished.
Does City Corporation Limited deliver on time in Pune?
1 of City Corporation Limited's 10 Pune projects with both dates on MahaRERA moved the completion date 3 months or more later, by 24 months on average. That compares the completion date filed today with the one filed at registration, leaving out MahaRERA's blanket extensions for all projects. MahaRERA does not publish handover dates, so check the occupancy certificate for a finished project.
Which City Corporation Limited projects are being built in Pune?
Amanora Elevate Tower 47 (completion filed Dec 2025); Amanora Arbano Towers in Hadapsar (completion filed Sep 2028).
Source: MahaRERA public records. Towers and phases of one project are counted once. Check each project's MahaRERA record and your agreement before you book.