Kalpataru projects in Pune
Our MahaRERA register holds 12 Pune projects by Kalpataru; 6 still being built or recently finished.
- Projects
- 12
- Homes listed
- 961
- Homes booked
- 484
- Completion date moved 3+ months
- 3 of 12
- by 22 months on average
Kalpataru's date record
3 of Kalpataru's 12 Pune projects with both dates on MahaRERA moved the completion date 3 months or more later, by 22 months on average.
- Kalpataru Estate Building 8moved 30 months later, now Jun 2025
- Kalpataru Amoda Reservemoved 24 months later, now Apr 2027
- Kalpataru Aakash Heightsmoved 12 months later, now Sep 2023
How we count: the completion date the builder files with MahaRERA today against the one filed at registration. Moves under 3 months and MahaRERA's blanket extensions for all projects (4 months in 2026) are left out. MahaRERA does not publish handover dates, so a date that did not move is not proof of an on-time handover.
Projects being built
- Kalpataru Serenity - Bldg. 3Manjari · possession filed Dec 2025MahaRERA P52100034075
- Kalpataru Jade SkylineBaner · possession filed Dec 2026 · 327/465 bookedMahaRERA P52100033791
- Kalpataru Amoda ReserveLonavala and Khandala · possession filed Apr 2027 · 95/114 booked · moved 24 months laterMahaRERA P52100003084
- Kalpataru Blossoms - Inclusive HousingDhayari · possession filed Jul 2029 · 0/60 bookedMahaRERA P52100077715
- Kalpataru BlossomsDhayari · possession filed Jul 2029 · 62/213 bookedMahaRERA P52100077649
- Kalpataru Aurevia Tower 5Dhayari · possession filed Sep 2032 · 0/109 bookedMahaRERA PR1260002602690
Finished more than a year ago
- Kalpataru Serenity - Bldg. 5Manjari · possession filed Dec 2022MahaRERA P52100001267
- Kalpataru Aakash HeightsPimpri · possession filed Sep 2023 · moved 12 months laterMahaRERA P52100028823
- Kalpataru Serenity - Bldg. 2Manjari · possession filed Oct 2024MahaRERA P52100015855
- Kalpataru ExquisiteHinjawadi · possession filed Dec 2024MahaRERA P52100000298
- Kalpataru Jade ResidencesAundh · possession filed Dec 2024MahaRERA P52100000676
- Kalpataru Estate Building 8Pimple Saudagar · possession filed Jun 2025 · moved 30 months laterMahaRERA P52100017535
Companies on MahaRERA
Builders often register each project under its own company. We count a project as Kalpataru's when the company's name says so, or the project is sold under the Kalpataru name.
- Kalpataru Gardens Pvt. Ltd. (3 projects)
- Kalpataru Limited (3 projects)
- Astrum Developments Private Limited (2 projects)
- Kalpataru Construction (Pune) (1 project)
- Kalpataru Properties (Thane) Private Limited (1 project)
- Kalpataru Retail Ventures Private Limited (1 project)
- M/S KALPATARU PROMOTERS DEVELOPERS PVT LTD (1 project)
Questions buyers ask
How many projects does Kalpataru have in Pune?
MahaRERA lists 12 Pune projects by Kalpataru in our register (towers and phases counted once); 6 are being built or recently finished.
Does Kalpataru deliver on time in Pune?
3 of Kalpataru's 12 Pune projects with both dates on MahaRERA moved the completion date 3 months or more later, by 22 months on average. That compares the completion date filed today with the one filed at registration, leaving out MahaRERA's blanket extensions for all projects. MahaRERA does not publish handover dates, so check the occupancy certificate for a finished project.
Which Kalpataru projects are being built in Pune?
Kalpataru Serenity - Bldg. 3 (completion filed Dec 2025); Kalpataru Jade Skyline (completion filed Dec 2026); Kalpataru Amoda Reserve (completion filed Apr 2027); Kalpataru Blossoms - Inclusive Housing (completion filed Jul 2029); Kalpataru Blossoms (completion filed Jul 2029); Kalpataru Aurevia Tower 5 (completion filed Sep 2032).
Which companies does Kalpataru register its Pune projects under?
On MahaRERA, Kalpataru's Pune projects are filed by 7 companies, including Kalpataru Gardens Pvt. Ltd., Kalpataru Limited, Astrum Developments Private Limited, Kalpataru Construction (Pune).
Source: MahaRERA public records. Towers and phases of one project are counted once. Check each project's MahaRERA record and your agreement before you book.