MANTRA ISLAND HOMES TALEGAON LLP: projects in Pune
Our MahaRERA register holds 5 Pune projects by MANTRA ISLAND HOMES TALEGAON LLP; 1 still being built or recently finished.
- Projects
- 5
- Completion date moved later
- 4 of 4
- by 32 months on average
Projects being built
Finished more than a year ago
- MANTRA CITY 360 PHASE01Talegaon · possession filed Oct 2021 · moved 24 months laterMahaRERA P52100001846
- MANTRA CITY 360 PHASE03Talegaon · possession filed Oct 2021 · moved 24 months laterMahaRERA P52100002880
- MANTRA CITY 360 PHASE02Talegaon · possession filed Jan 2022 · moved 24 months laterMahaRERA P52100001834
- MANTRA CITY 360 PHASE04Talegaon · possession filed Jul 2024 · moved 56 months laterMahaRERA P52100001457
Source: MahaRERA public records. Towers and phases of one project are counted once. Check each project's MahaRERA record and your agreement before you book.