Parshwa Developers projects in Pune
Our MahaRERA register holds 6 Pune projects by Parshwa Developers in Lohegaon; 1 still being built or recently finished.
- Projects
- 6
- Homes listed
- 155
- Homes booked
- 66
- Completion date moved 3+ months
- 1 of 6
- by 4 months on average
Parshwa Developers's date record
1 of Parshwa Developers's 6 Pune projects with both dates on MahaRERA moved the completion date 3 months or more later, by 4 months on average.
- Vedamoved 4 months later, now Jul 2018
How we count: the completion date the builder files with MahaRERA today against the one filed at registration. Moves under 3 months and MahaRERA's blanket extensions for all projects (4 months in 2026) are left out. MahaRERA does not publish handover dates, so a date that did not move is not proof of an on-time handover.
Projects being built
Finished more than a year ago
- VedaDhanori · possession filed Jul 2018 · moved 4 months laterMahaRERA P52100003939
- SignetDhanori · possession filed Dec 2019MahaRERA P52100017261
- RagaLohegaon · possession filed Sep 2022MahaRERA P52100025758
- TejasLohegaon · possession filed Jul 2024MahaRERA P52100034114
- Sona RupaPeth areas · possession filed Jan 2025 · 71 homesMahaRERA P52100027917
Questions buyers ask
How many projects does Parshwa Developers have in Pune?
MahaRERA lists 6 Pune projects by Parshwa Developers in our register (towers and phases counted once), in Lohegaon; 1 is being built or recently finished.
Does Parshwa Developers deliver on time in Pune?
1 of Parshwa Developers's 6 Pune projects with both dates on MahaRERA moved the completion date 3 months or more later, by 4 months on average. That compares the completion date filed today with the one filed at registration, leaving out MahaRERA's blanket extensions for all projects. MahaRERA does not publish handover dates, so check the occupancy certificate for a finished project.
Which Parshwa Developers projects are being built in Pune?
24 Sunshine Viva (completion filed Apr 2027).
Source: MahaRERA public records. Towers and phases of one project are counted once. Check each project's MahaRERA record and your agreement before you book.