Up to 3 projects side by side. Dates and bookings from MahaRERA's public record; prices as the builder or two property sites publish them. A dash means we do not have that fact yet.

FactOmicron Tech ParkWagholiMahaRERA PC1260002601259Tech TowerKharadiMahaRERA P52100054776One SuitesKharadiMahaRERA PC1260002502329
Possession filedApr 2032filed with MahaRERAApr 2029filed with MahaRERADec 2028filed with MahaRERA
Date moved by the builderNot moved by the builderMahaRERA's 2026 order added 4 monthsMoved 16 months laterfirst filed for Dec 2027Moved laterfirst filed for Oct 2027
Homes booked0% booked0 of 8 homes18% booked3 of 17 homes82% booked148 of 180 homes
Homes left8 homesnot yet booked on MahaRERA14 homesnot yet booked on MahaRERA32 homesnot yet booked on MahaRERA
Towers1 tower, up to 3 floors1 tower, up to 21 floors1 tower, up to 10 floors
StageNew launchby dates, registration to filed completionMid stageby dates, registration to filed completionEarly stageby dates, registration to filed completion
Builder's date record1 project on MahaRERAtoo few with both dates to judge1 project on MahaRERAtoo few with both dates to judge—
Pick

The all-in cost adds GST, stamp duty (7%) and registration to the lowest published price; parking, club house and other charges come from the builder's cost sheet. A per sq ft figure is the site's own: some quote carpet, some saleable area.