Skip to main contentSkip to navigation

Compare projects

Up to 3 projects side by side. Dates and bookings from MahaRERA's public record; prices as the builder or two property sites publish them. A dash means we do not have that fact yet.

FactTech TowerKharadiMahaRERA P52100054776Oxy BastionKharadiMahaRERA PC1260002501826343 CrestUpper KharadiMahaRERA P52100022737
Possession filedApr 2029filed with MahaRERAOct 2028filed with MahaRERADec 2027filed with MahaRERA
Date moved by the builderMoved 16 months laterfirst filed for Dec 2027Not moved by the builderMahaRERA's 2026 order added 4 monthsMoved 12 months laterfirst filed for Dec 2026
Homes booked18% booked3 of 17 homes0% booked0 of 27 homes—
Homes left14 homesnot yet booked on MahaRERA27 homesnot yet booked on MahaRERA—
Towers1 tower, up to 21 floors1 tower, up to 18 floors1 tower, up to 4 floors
StageMid stageby dates, registration to filed completionEarly stageby dates, registration to filed completionNear completionby dates, registration to filed completion
Builder's date record1 project on MahaRERAtoo few with both dates to judge1 project on MahaRERAtoo few with both dates to judge4 of 22 moved their dateGera Developments, 22 projects
Pick

The all-in cost adds GST, stamp duty (7%) and registration to the lowest published price; parking, club house and other charges come from the builder's cost sheet. A per sq ft figure is the site's own: some quote carpet, some saleable area.