What is changing in Pune
Every road, bridge, metro line, airport, rule and rate we follow, with where it stands today and the dated reports behind it. Newest change first.
Tracker · RuleAll Pune buyers
PMC building rules (FSI and TDR)
Premium FSI and TDR along roads earmarked for widening are withheld until the whole stretch is widened on the ground, under a Pune Municipal Corporation circular for building proposals submitted from 27 November 2026.
Status as of
Tracker · ProjectHinjawadiWakadBaner
Metro Line 3 (Hinjawadi to Shivajinagar)
Stage 3 of 3: Open
Open: passenger trains run between Hinjawadi and District Court at 17 of the 23 stations, after the inauguration on 3 November. The other six, including Baner's and Shivajinagar, are to open in stages by January 2027.
Status as of · 81 reportsNew report
Tracker · ProjectKharadiWagholi
Pune Metro phase 2 (four new corridors)
Stage 2 of 4: Foundation stone and tenders
Tenders have begun: Maha Metro invited bids for the 6.5 km SNDT-Warje stretch, with two flyovers planned at Karve Putala Chowk and Ambedkar Chowk. The Ramwadi-Wagholi stretch is likely to be built as a double-decker.
Status as of · 1 report
Tracker · ProjectPune
Parking at Pune metro stations
The Pune Municipal Corporation has built two pay-and-park lots near metro stations, has tenders out for two more, and expects two further sites ready by March. It plans parking across the network of about 81 stations; PMRDA is seeking land for eight more lots.
Status as of · 1 report
Tracker · ProjectPune
MHADA Pune housing lottery
Stage 2 of 3: Applications closed, draw due
Applications are closed with a record response, about 61 applicants for every home; the draw for the 4,462 homes is set for December 1.
Status as of · 1 report
Tracker · RuleAll Pune buyers
PMC property tax
New property tax registrations have fallen well behind this year because the department is short of staff; the corporation also adds a penalty tax on developers of illegal constructions.
Status as of · 1 reportNew report
Tracker · ProjectKeshav NagarKharadi
Keshavnagar-Kharadi bridge
Stage 2 of 3: Built, not formally open
Built, but residents say it is unclear whether the bridge is officially open: barricades near it keep being taken down by locals, and traffic still crowds the Chanchala Kodre bridge and Mundhwa Chowk.
Status as of
Tracker · RateAll Pune buyers
Ready reckoner rates and stamp duty
There was no ready reckoner rate rise this year. The state plans to set ready reckoner rates by micro-zone on a map, first as a pilot in Mumbai, with Pune later.
Status as of · 7 reportsNew report
Tracker · RateAll Pune buyers
Home loan rates (RBI repo rate)
The RBI raised the repo rate by 0.25 percentage point to 5.50%. Several banks, among them PNB and Bank of Baroda, raised their home loan rates after it.
Status as of · 29 reportsNew report
Tracker · ProjectLohegaon
Vishrantwadi flyover
Stage 1 of 2: Being built
Being built, with grade separator work expected to finish by December end
Status as of · 1 report
Tracker · ProjectPune
Suncity-Karvenagar flyover
Stage 1 of 2: Being built
Being built and due to be finished in December 2026, with the opening expected in early 2027. Land for the approach roads on both sides is still being acquired, and residents asked Maha Metro to hold its Khadakwasla-Kharadi work on Sinhagad Road until the flyover opens.
Status as of
Tracker · ProjectPune
HCMTR
Stage 2 of 5: Land survey
Land survey: the Pune Collector has set 30 October as the deadline for the HCMTR and inner ring road land surveys. Earlier this month the survey on Nagar Road stopped over notice and compensation.
Status as of · 10 reportsNew report
Tracker · ProjectBaner
PMC bridges and flyovers due in 2027
The Pune Municipal Corporation expects four to five bridges and flyovers to be finished by the end of December 2026 and opened in early 2027, among them the Sadhu Vaswani bridge (likely January 2027) and the Ghorpadi flyover, about 90% built. Another bridge is due in March 2027.
Status as of
Tracker · ProjectPune
Patal Lok underground road (Bhosari to Undri)
Stage 2 of 5: Project report (DPR)
Plan reworked: the 23 km Bhosari-Undri tunnel through Khadi Machine Chowk is now the priority, and the civic body approved hiring a consultant for its detailed project report. A project report for an 8 km Bhugaon-Erandwane tunnel was approved, and a Swargate-Shaniwarwada tunnel is being studied.
Status as of
Tracker · ProjectPune
Pune Ring Road
Survey for Pune Ring Road halted due to compensation dispute
Status as of · 23 reports
Tracker · ProjectPune
Purandar airport
Stage 3 of 5: Feasibility and design
Land acquisition is nearly done, tender to be floated soon
Status as of · 44 reports
Tracker · RuleLohegaon
Development plan for merged villages
The revised development plan for nine merged villages makes 143 changes, the most in Lohegaon, and narrows about 50 planned roads, among them the highway at Undri.
Status as of
Tracker · ProjectPune
Swargate-Katraj metro extension
Stage 2 of 3: Construction
Construction: the first tunnel boring machine has arrived and tunnelling is to begin in January. The two machines that will tunnel towards Katraj are expected in six to eight months, and the corporation is handing over land for the Padmavati station.
Status as of
Tracker · RuleWagholi
Water in merged villages
Builders must supply water in the 32 merged villages for three years or until PMC water supply begins, and PMRDA requires assured water supply before approving a building.
Status as of · 5 reports
Tracker · ProjectLohegaon
Lohegaon hospital
Stage 2 of 3: Built, waiting to open
Built and staffed, with ambulances ready, but not open: it is still waiting for permission to be inaugurated.
Status as of · 6 reportsNew report