Acropolis, Pimpri
by Krrisha Developers · Pimpri, Haveli, Pune district · 411017
- Possession
- Mar 2021
- completion filed with MahaRERA
As of 17 Oct 2026, Acropolis by Krrisha Developers in Pimpri, Pune district is registered with MahaRERA as P52100004298. The completion date filed with MahaRERA is 30 Mar 2021, moved from 31 Dec 2018 at registration. The filed completion date has passed: ask for the occupancy certificate (OC).
Updated 17 Oct 2026
Still being built in Pimpri
Acropolis is finished (completion filed for Mar 2021), so we do not take enquiries for it. These projects nearby still have homes to book, the soonest possession first.
- Adi Amma Insperiapossession Nov 2026
- Rajveer Imperiapossession Nov 2026
- Anantapossession Dec 2026
- Aureliapossession Dec 2026
- Square Onepossession Dec 2026
- Stella Apexpossession Feb 2027
- KK Mangalam Emeraldpossession Feb 2027
- Prajol Aashiyana B Wingpossession Feb 2027
- Legacy Kairos A and B Buildingpossession Mar 2027
- Sant Kanwaram Co-operative Housing Societypossession Apr 2027
Location
A map search by name. Open the map (opens in a new tab)
MahaRERA record
From MahaRERA, read 17 Oct 2026Possession date
30 Mar 2021
Completion date filed with MahaRERA. At registration: 31 Dec 2018. Moved 27 months later.
The filed completion date has passed. Ask for the occupancy certificate (OC) before you book.
Ask for the possession date in writing in your agreement for sale.
Beside other Pimpri projects
Worked out by Avasetu- Completion date
- Moved 27 months later
- 11 of 68 Pimpri projects being built moved theirs 3 months or more.
From MahaRERA records read 17 Oct 2026. Dates net of MahaRERA's August 2026 order.
The record
- Registered on
- 9 Aug 2017
- MahaRERA registration
- P52100004298
- Listed or updated on MahaRERA 17 Jun 2020.
- Promoter (builder)
- Krrisha Developers
- Pincode
- 411017
Check before you book
From MahaRERA- The completion date filed with MahaRERA (Mar 2021) has passed. Ask for the occupancy certificate (OC) before you pay anything more.
- The builder has moved the completion date 27 months later since registration, from Dec 2018 to Mar 2021. Ask why, and which date goes in your agreement for sale.
Krrisha Developers: track record
From MahaRERA recordsKrrisha Developers has 1 project in our MahaRERA register for Pune.
FAQ
What is the price of Acropolis?
No price for Acropolis is published yet. Ask through the enquiry form on this page for the current price.
What is the possession date of Acropolis?
The completion date filed with MahaRERA is 30 Mar 2021. At registration it was 31 Dec 2018. Ask the builder for the possession date in your agreement, in writing.
What is the MahaRERA number of Acropolis?
Acropolis is registered with MahaRERA as P52100004298.
Who is the builder of Acropolis?
The promoter registered with MahaRERA is Krrisha Developers.
Where is Acropolis?
Acropolis is in Haveli, Pune district (pincode 411017).
Has the completion date of Acropolis passed?
Yes. Ask the builder for the occupancy certificate (OC) before you book.
Sources
- Registration, promoter, pincodeFrom MahaRERA
MahaRERA listing, updated 17 Jun 2020
- Dates and homes bookedNot checked yet
Still checking
- Buildings and wingsNot checked yet
Still checking
- Location and nearbyNot checked yet
Still checking
- DescriptionNot checked yet
Still checking