The builder's picture
MahaRERA registered P52100001891Verify on MahaRERA (opens in a new tab)Near completion

Adhya Radha Krishna, Moshi

by Adhya Properties · Moshi, Haveli, Pune district · 412105

Possession
Jul 2027
completion filed with MahaRERA
Booked
302 of 359

What stands out

As of 14 Nov 2026, from MahaRERA and the sources below.

  • 84% of the 359 units are already booked, while the median booking rate for the eight Moshi projects is about 52%.
  • With 359 homes in this registration, it has more units than 243 of the 269 comparable Moshi projects.
  • The completion date filed with MahaRERA is 31 Jul 2027, which adds several months to the original registration date of 30 Dec 2022.

Updated 23 Nov 2026

Pictures

Adhya Radha Krishna, from the builder's website
Adhya Radha Krishna, from the builder's website
Adhya Radha Krishna, from the builder's website
111live-1 (2)
111live-2 (2)
111live-3 (2)

From the builder's website. Renders are the builder's artist's impressions and plans are indicative: check the sanctioned plans before you book.

Price

No price for Adhya Radha Krishna is published yet.

What new homes in Moshi usually ask

  • 1 BHK about ₹30 – 45 L (11 projects)
  • 2 BHK about ₹45 – 65 L (54 projects)
  • 2.5 BHK about ₹65 – 80 L (4 projects)
  • 3 BHK about ₹65 – 90 L (41 projects)
  • 4 BHK about ₹1.1 – 1.9 Cr (6 projects)

Our own guide: the middle half of the starting prices we have read for projects being sold in Moshi, rounded. Use it to judge an offer, not as a price.

Moshi average ₹7,638/sq ft across 18 projectsThe middle asking price per sq ft of other projects in Moshi.

Ask about this project

Outside our main East Pune areas: the Avasetu team finds out what it can.

Send your question

Floor plans

See the 3 floor plans

Location

A map search by name. Open the map (opens in a new tab)

Project facts

Amenities

Last checked 22 Nov 2026.

MahaRERA record

From MahaRERA, read 14 Nov 2026

Possession date

31 Jul 2027

Completion date filed with MahaRERA. At registration: 30 Dec 2022. Moved 51 months later, 4 of them by MahaRERA's August 2026 order for most projects.

Ask for the possession date in writing in your agreement for sale.

Beside other Moshi projects

Worked out by Avasetu
Homes booked
84%
The middle of 8 Moshi projects registered within a year of it: 52%.
Completion date
Moved 51 months later
61 of 290 Moshi projects being built moved theirs 3 months or more.

From MahaRERA records read 14 Nov 2026. Homes booked are the builders' own quarterly counts. Dates net of MahaRERA's August 2026 order.

The record

Homes booked
302 of 359
Towers
5 in this registration
The tallest has 15 floors.
Units
359
335 homes, 24 shops or offices. 466 in the whole project (builder's site).
Registered on
29 Jul 2017
MahaRERA registration
P52100001891
Listed or updated on MahaRERA 1 Feb 2025.
Promoter (builder)
Adhya Properties
Project type
Residential / Group Housing
Pincode
412105

Open the MahaRERA record (opens in a new tab)

Check before you book

From MahaRERA
  • The builder has moved the completion date 51 months later since registration, from Dec 2022 to Jul 2027 (MahaRERA's 2026 blanket extension for all projects left out). Ask why, and which date goes in your agreement for sale.
  • 24 shops or offices are part of the project. Ask where they open and whether their visitors use the residents' gate.

Tower by tower

5 buildings

Buildings

From MahaRERA
BuildingFloorsHomesOther
A12700
B13900
Building 3000
D15770
E159824

As filed with MahaRERA (sanctioned floors).

What the builder's and property sites say

Gathered and checked
Land
2.8 acres
From the builder's site
Architect
Brainmine
From the builder's site

Last checked 22 Nov 2026. MahaRERA counts where they differ.

Adhya Properties: track record

From MahaRERA records

Adhya Properties has 2 projects in our MahaRERA register for Pune.

All 2 projects by Adhya Properties in Pune

Planning to buy here?

Ask about prices, floor plans, offers or a site visit.

Other projects in Moshi

More by Adhya Properties

FAQ

What is the price of Adhya Radha Krishna?

No price for Adhya Radha Krishna is published yet. Ask through the enquiry form on this page for the current price.

What is the possession date of Adhya Radha Krishna?

The completion date filed with MahaRERA is 31 Jul 2027. At registration it was 30 Dec 2022. MahaRERA added 4 months to most projects' dates in August 2026 (Order 66/2026). Ask the builder for the possession date in your agreement, in writing.

What is the MahaRERA number of Adhya Radha Krishna?

Adhya Radha Krishna is registered with MahaRERA as P52100001891.

How many towers and floors does Adhya Radha Krishna have?

MahaRERA lists 5 buildings, the tallest with 15 floors.

How many flats are there in Adhya Radha Krishna?

MahaRERA lists 359 units (335 residential, 24 other).

How many homes in Adhya Radha Krishna are booked?

302 of 359 homes were booked as per MahaRERA on 14 Nov 2026.

Who is the builder of Adhya Radha Krishna?

The promoter registered with MahaRERA is Adhya Properties. Our register has 2 Pune projects by Adhya Properties.

Where is Adhya Radha Krishna?

Adhya Radha Krishna is in Haveli, Pune district (pincode 412105).

Sources
  • Registration, promoter, pincodeFrom MahaRERA

    MahaRERA listing, updated 1 Feb 2025

  • Dates and homes bookedFrom MahaRERA

    Checked 22 Nov 2026

  • Buildings and wingsFrom MahaRERA

    Checked 22 Nov 2026

  • Location and nearbyNot checked yet

    Still checking

  • DescriptionGathered and checked

    Checked 22 Nov 2026

  • Project facts and amenitiesGathered and checked

    The builder's site and property sites, which can be wrong: where they differ from MahaRERA, MahaRERA counts (22 Nov 2026)

Get the price sheet and floor plans for Adhya Radha Krishna

The Avasetu team calls or WhatsApps you back; we never share your number without your OK.

What would you like?

BHK

Add budget, move-in or a note (optional)

Skip anything you like. It only helps with better options.

Budget

Move in

Payment