Ready to move projects in Hinjawadi, Pune
As of 15 Oct 2026, 30 projects in Hinjawadi have passed the completion date filed with MahaRERA in the last three years, the newest GAURAV ICON TOWER (31 Jul 2026). Ask the builder for the occupancy certificate (OC) before you book.
48 projects, first 30
- GAURAV ICON TOWER by GAURAV ICON INFRATECH PRIVATE LIMITED
completion filed for 31 Jul 2026, now passed, 4 of 14 homes not booked (MahaRERA)
- Registered
- Dec 2021
- Possession filed
- Jul 2026moved from Mar 2026
- Homes
- 14
- Booked
- 10 (71%)
MahaRERA P52100032040
- 172W Inclusive Housing by Vilas Javdekar Lifestyle Developers Pvt. Ltd.
completion filed for 30 Jun 2026, now passed, 1 of 21 homes not booked (MahaRERA)
- Registered
- Feb 2023
- Possession filed
- Jun 2026
- Homes
- 21
- Booked
- 20 (95%)
MahaRERA P52100049412
- Blueridge-The Groves by NOVA DEVELOPERS PVT LTD
completion filed for 30 Jun 2026, now passed (MahaRERA)
- Registered
- Dec 2020
- Possession filed
- Jun 2026
- Homes
- 0
MahaRERA P52100027419
- YashONE Eternitee by Vilas Javdekar Infinitee Developers Pvt. Ltd.
completion filed for 30 Apr 2026, now passed (MahaRERA)
- Registered
- Jun 2022
- Possession filed
- Apr 2026
- Homes
- 382
- Booked
- 382 (100%)
MahaRERA P52100046122 · registered as YashONE Eternitee Phase 1
- GAIKWAD NIRVANAS by GAIKWAD DEVELOPERS
completion filed for 31 Mar 2026, now passed, 40 of 156 homes not booked (MahaRERA)
- Registered
- Oct 2022
- Possession filed
- Mar 2026
- Homes
- 156
- Booked
- 116 (74%)
MahaRERA P52100047315
- ROYAL ACE by Five Star Construction Company
completion filed for 31 Mar 2026, now passed, 7 of 40 homes not booked (MahaRERA)
- Registered
- Jul 2024
- Possession filed
- Mar 2026
- Homes
- 40
- Booked
- 33 (83%)
MahaRERA P52100077036
- Saarrthi Savvy Homes II by Siddharth Properties
completion filed for 31 Mar 2026, now passed, 47 of 196 homes not booked (MahaRERA)
- Registered
- Apr 2018
- Possession filed
- Mar 2026moved from Dec 2022
- Homes
- 196
- Booked
- 149 (76%)
MahaRERA P52100016105
- Yashwin SuperNova by Vilas Javdekar Eco Shelters Private Limited
completion filed for 30 Mar 2026, now passed, 213 of 710 homes not booked (MahaRERA)
- Registered
- Mar 2021
- Possession filed
- Mar 2026
- Homes
- 710
- Booked
- 497 (70%)
MahaRERA P52100028652
- KUBER ANTONIA
completion filed for 23 Feb 2026, now passed, 3 of 60 homes not booked (MahaRERA)
- Registered
- May 2022
- Possession filed
- Feb 2026moved from Feb 2025
- Homes
- 60
- Booked
- 57 (95%)
MahaRERA P52100035197
- Apostrophe Hinjawadi by HINJAWADI INFRADEVELOPMENT PVT LTD
completion filed for 31 Dec 2025, now passed (MahaRERA)
- Registered
- Oct 2021
- Possession filed
- Dec 2025
- Homes
- 0
MahaRERA P52100031595 · registered as Apostrophe Hinjawadi Tower C
- Athashree by SHREE HOUSING
completion filed for 31 Dec 2025, now passed, 9 of 10 homes not booked (MahaRERA)
- Registered
- Dec 2021
- Possession filed
- Dec 2025moved from Dec 2022
- Homes
- 10
- Booked
- 1 (10%)
MahaRERA P52100032023
- PRAGATI by Sigma Realty
completion filed for 31 Dec 2025, now passed (MahaRERA)
- Registered
- Jun 2024
- Possession filed
- Dec 2025
- Homes
- 0
MahaRERA P52100076817
- RIOLAND B WING by WAMAN KALATE INFRASTRUCTURES
completion filed for 31 Dec 2025, now passed (MahaRERA)
- Registered
- Dec 2023
- Possession filed
- Dec 2025moved from Sep 2024
- Homes
- 0
MahaRERA P52100053851
- Suyog Space by SUYOG BUILDERS
completion filed for 31 Dec 2025, now passed, 12 of 182 homes not booked (MahaRERA)
- Registered
- Dec 2021
- Possession filed
- Dec 2025
- Homes
- 182
- Booked
- 170 (93%)
MahaRERA P52100032138 · registered as SUYOG SPACE - PHASE II
- TALREJA BUSINESS HUB
completion filed for 31 Dec 2025, now passed (MahaRERA)
- Registered
- Dec 2024
- Possession filed
- Dec 2025moved from Dec 2024
- Homes
- 17
MahaRERA P52100078593
- TRIDENT C, D by PARANJAPE SCHEMES (CONSTRUCTION) LTD
completion filed for 31 Dec 2025, now passed, 24 of 308 homes not booked (MahaRERA)
- Registered
- Mar 2018
- Possession filed
- Dec 2025moved from Dec 2023
- Homes
- 308
- Booked
- 284 (92%)
MahaRERA P52100015697
- TRINITY GRACE by Jethani Landmark LLP
completion filed for 31 Dec 2025, now passed, 7 of 50 homes not booked (MahaRERA)
- Registered
- Sep 2023
- Possession filed
- Dec 2025
- Homes
- 50
- Booked
- 43 (86%)
MahaRERA P52100052541
- Unnati by Sigma Realty
completion filed for 31 Dec 2025, now passed (MahaRERA)
- Registered
- Jun 2024
- Possession filed
- Dec 2025
- Homes
- 0
MahaRERA P52100066546 · registered as UNNATI PHASE III
- 32 Pinewood Drive -Phase2 by S S Properties
completion filed for 30 Dec 2025, now passed, 1 of 169 homes not booked (MahaRERA)
- Registered
- Feb 2022
- Possession filed
- Dec 2025moved from Dec 2024
- Homes
- 169
- Booked
- 168 (99%)
MahaRERA P52100033337
- The Water Edge by Vision Developers
completion filed for 30 Aug 2025, now passed (MahaRERA)
- Registered
- Aug 2023
- Possession filed
- Aug 2025moved from Aug 2024
- Homes
- 60
MahaRERA P52100052250
- Kratos Tower by APUS REALTIES PRIVATE LIMITED
completion filed for 28 Aug 2025, now passed, 36 of 55 homes not booked (MahaRERA)
- Registered
- Jun 2018
- Possession filed
- Aug 2025moved from Feb 2024
- Homes
- 55
- Booked
- 19 (35%)
MahaRERA P52100016937
- NARMADA BLUE SAPPHIRE
completion filed for 31 Jul 2025, now passed, 15 of 20 homes not booked (MahaRERA)
- Registered
- Jun 2018
- Possession filed
- Jul 2025moved from Dec 2023
- Homes
- 20
- Booked
- 5 (25%)
MahaRERA P52100016661
- ELYSIA TOWERS by BHAKTI BUILDERS
completion filed for 30 Jun 2025, now passed, 55 of 117 homes not booked (MahaRERA)
- Registered
- Dec 2020
- Possession filed
- Jun 2025moved from Dec 2024
- Homes
- 117
- Booked
- 62 (53%)
MahaRERA P52100027702
- YASHWIN HINJAWADI by Vilas Javdekar Eco Shelters Private Limited
completion filed for 30 Jun 2025, now passed (MahaRERA)
- Registered
- Jun 2017
- Possession filed
- Jun 2025
- Homes
- 0
MahaRERA P52100000037
- Ivana Residency by Siddhidata Infra
completion filed for 31 May 2025, now passed, 3 of 10 homes not booked (MahaRERA)
- Registered
- Oct 2023
- Possession filed
- May 2025
- Homes
- 10
- Booked
- 7 (70%)
MahaRERA P52100053060
- Rahul Aston by Rahul Construction
completion filed for 30 Apr 2025, now passed (MahaRERA)
- Registered
- Nov 2020
- Possession filed
- Apr 2025moved from Mar 2025
- Homes
- 0
MahaRERA P52100026878 · registered as Rahul Aston - I
- FUTURE ELITE
completion filed for 31 Mar 2025, now passed (MahaRERA)
- Registered
- Jun 2023
- Possession filed
- Mar 2025moved from Aug 2023
- Homes
- 0
MahaRERA P52100051491
- Sky Bhumi
completion filed for 31 Mar 2025, now passed (MahaRERA)
- Registered
- Jul 2024
- Possession filed
- Mar 2025
- Homes
- 14
MahaRERA P52100076990
- YOU57 AMENITY BUILDING by SANAS DEVELOPERS PRIVATE LIMITED
completion filed for 31 Mar 2025, now passed, 21 of 28 homes not booked (MahaRERA)
- Registered
- Feb 2023
- Possession filed
- Mar 2025moved from Mar 2024
- Homes
- 28
- Booked
- 7 (25%)
MahaRERA P52100049285
- Stellar Homes - Phase I
completion filed for 30 Mar 2025, now passed (MahaRERA)
- Registered
- Jun 2021
- Possession filed
- Mar 2025moved from Mar 2024
- Homes
- 0
MahaRERA P52100029687
Questions buyers ask
- Which projects in Hinjawadi, Pune are ready to move?
- As of 15 Oct 2026, 30 projects in Hinjawadi have passed the completion date filed with MahaRERA in the last three years, the newest GAURAV ICON TOWER (31 Jul 2026). Ask the builder for the occupancy certificate (OC) before you book. The newest: GAURAV ICON TOWER, 172W Inclusive Housing, Blueridge-The Groves, YashONE Eternitee, GAIKWAD NIRVANAS.
- Does a passed completion date mean I can move in?
- Not on its own. The completion date is what the builder filed with MahaRERA. The occupancy certificate (OC) from the local authority is what says the building can be lived in: ask for it.
- Where do these numbers come from?
- MahaRERA's public records, read by Avasetu; this list was worked out on 2026-10-15. Each project's page shows the date we read its record.
The same list near Hinjawadi
How this list is made
Projects whose completion date filed with MahaRERA passed in the last three years, newest first. MahaRERA does not show the occupancy certificate, so ask the builder for it. Towers and phases of one project count once. From MahaRERA public records, worked out on 15 Oct 2026; each project's page shows the date we read its record. No builder pays to be on this list. This is general information, not investment or legal advice.