Ready to move projects in Kothrud, Pune
Updated 19 Nov 2026 · from MahaRERA's records
As of 24 Nov 2026, 30 projects in Kothrud have passed the completion date filed with MahaRERA in the last three years and still have 10 or more homes not booked, the newest Janhavi (18 Nov 2026). Ask the builder for the occupancy certificate (OC) before you book.
33 projects, first 30
- Rank 1Due Nov 2026 · ask for OCJanhavi
completion filed for 18 Nov 2026, now passed, 31 of 79 homes not booked
- Registered
- Mar 2021
- Possession filed
- Nov 2026moved from Sep 2025
- Homes
- 79
- Booked
- 48 (61%)
MahaRERA P52100028769
- Rank 2Due Nov 2026 · ask for OCElitas by Eka Buildcon LLP
completion filed for 11 Nov 2026, now passed, 122 of 233 homes not booked
- Registered
- Aug 2021
- Possession filed
- Nov 2026moved from Jul 2026
- Homes
- 233
- Booked
- 111 (48%)
MahaRERA P52100030185
- Rank 3Due Oct 2026 · ask for OCAyodhyanagar by Gokhale Constructions
completion filed for 31 Oct 2026, now passed, 28 of 46 homes not booked
- Registered
- Dec 2021
- Possession filed
- Oct 2026moved from Aug 2025
- Homes
- 46
- Booked
- 18 (39%)
MahaRERA P52100032277
- Rank 4Due Oct 2026 · ask for OCDwarkakunj by JOSHI BUILDCON LANDMARKS
completion filed for 31 Oct 2026, now passed, 12 of 18 homes not booked
- Registered
- Jan 2024
- Possession filed
- Oct 2026
- Homes
- 18
- Booked
- 6 (33%)
MahaRERA P52100054204
- Rank 5Due Oct 2026 · ask for OCShri Laxmi Chhaya Sahakari Grahrachana Sanstha Marayadit by ARCHWAY PROPERTIES LLP
completion filed for 30 Oct 2026, now passed, 28 of 45 homes not booked
- Registered
- Jan 2023
- Possession filed
- Oct 2026moved from Dec 2025
- Homes
- 45
- Booked
- 17 (38%)
MahaRERA P52100049116
- Rank 6Due Sep 2026 · ask for OCArunali by Badhekar Properties
completion filed for 30 Sep 2026, now passed, 31 of 52 homes not booked
- Registered
- Aug 2021
- Possession filed
- Sep 2026moved from Jun 2025
- Homes
- 52
- Booked
- 21 (40%)
MahaRERA P52100030309
- Rank 7Due Sep 2026 · ask for OCGuruvaibhav Co-Op.Housing Society Limited by SHREEPAD ASSOCIATES
completion filed for 30 Sep 2026, now passed, 20 of 30 homes not booked
- Registered
- Jan 2023
- Possession filed
- Sep 2026moved from Mar 2025
- Homes
- 30
- Booked
- 10 (33%)
MahaRERA P52100049050
- Rank 8Due Jun 2026 · ask for OCDodke Palazzo by DODKE LANDMARKS
completion filed for 30 Jun 2026, now passed, 30 of 134 homes not booked
- Registered
- Oct 2021
- Possession filed
- Jun 2026moved from Dec 2024
- Homes
- 134
- Booked
- 104 (78%)
MahaRERA P52100031044
- Rank 9Due Jun 2026 · ask for OCLaxmikrupa
completion filed for 30 Jun 2026, now passed, 45 of 93 homes not booked
- Registered
- May 2022
- Possession filed
- Jun 2026moved from Dec 2025
- Homes
- 93
- Booked
- 48 (52%)
MahaRERA P52100045252
- Rank 10Due Jun 2026 · ask for OCNavkshitij CHS LTD by Vishwam Realtors & Developers LLP
completion filed for 30 Jun 2026, now passed, 16 of 27 homes not booked
- Registered
- Jan 2021
- Possession filed
- Jun 2026
- Homes
- 27
- Booked
- 11 (41%)
MahaRERA P52100028051
- Rank 11Due Jun 2026 · ask for OCVidula Apartments by HINDUSTAN BUILDERS
completion filed for 30 Jun 2026, now passed, 15 of 30 homes not booked
- Registered
- Jun 2024
- Possession filed
- Jun 2026
- Homes
- 30
- Booked
- 15 (50%)
MahaRERA P52100076729
- Rank 12Due Jun 2026 · ask for OCChandrasmit by Metricon Builders Private Limited
completion filed for 29 Jun 2026, now passed, 32 of 53 homes not booked
- Registered
- Oct 2022
- Possession filed
- Jun 2026moved from Jun 2025
- Homes
- 53
- Booked
- 21 (40%)
MahaRERA P52100047222
- Rank 13Due Apr 2026 · ask for OCGangawas by Archway Estates DB Gangawas LLP
completion filed for 30 Apr 2026, now passed, 23 of 42 homes not booked
- Registered
- Mar 2022
- Possession filed
- Apr 2026moved from Dec 2024
- Homes
- 42
- Booked
- 19 (45%)
MahaRERA P52100034138
- Rank 14Due Mar 2026 · ask for OCAdiyogi by KIDPL ADIYOGI PRIVATE LIMITED
completion filed for 31 Mar 2026, now passed, 17 of 33 homes not booked
- Registered
- Jan 2024
- Possession filed
- Mar 2026moved from Jul 2025
- Homes
- 33
- Booked
- 16 (48%)
MahaRERA P52100054560
- Rank 15Due Mar 2026 · ask for OCShri Dattatraya Co. Housing Society LTD by ARCHWAY ESTATES DB LLP
completion filed for 31 Mar 2026, now passed, 15 of 28 homes not booked
- Registered
- Jan 2023
- Possession filed
- Mar 2026moved from Mar 2025
- Homes
- 28
- Booked
- 13 (46%)
MahaRERA P52100048893
- Rank 16Due Feb 2026 · ask for OCRatnaprabha by ASHWAMEDH SPACES PRIVATE LIMITED
completion filed for 28 Feb 2026, now passed, 30 of 52 homes not booked
- Registered
- Jun 2022
- Possession filed
- Feb 2026moved from Jun 2025
- Homes
- 52
- Booked
- 22 (42%)
MahaRERA P52100045880
- Rank 17Due Dec 2025 · ask for OCDwarka
completion filed for 31 Dec 2025, now passed, 34 of 40 homes not booked
- Registered
- Jul 2021
- Possession filed
- Dec 2025moved from Dec 2024
- Homes
- 40
- Booked
- 6 (15%)
MahaRERA P52100029936
- Rank 18Due Dec 2025 · ask for OCManasi by ABHILASHA DEVELOPERS
completion filed for 31 Dec 2025, now passed, 22 of 29 homes not booked
- Registered
- Feb 2023
- Possession filed
- Dec 2025
- Homes
- 29
- Booked
- 7 (24%)
MahaRERA P52100049332
- Rank 19Due Dec 2025 · ask for OCManoj Villa by Dream Forge Infra Private Limited
completion filed for 31 Dec 2025, now passed, 26 of 38 homes not booked
- Registered
- Sep 2021
- Possession filed
- Dec 2025
- Homes
- 38
- Booked
- 12 (32%)
MahaRERA P52100030927
- Rank 20Due Dec 2025 · ask for OCMrudgandha
completion filed for 31 Dec 2025, now passed, 26 of 44 homes not booked
- Registered
- Jun 2021
- Possession filed
- Dec 2025moved from Dec 2024
- Homes
- 44
- Booked
- 18 (41%)
MahaRERA P52100029764
- Rank 21Due Dec 2025 · ask for OCPride Shree by Pride Group
completion filed for 31 Dec 2025, now passed, 22 of 27 homes not booked
- Registered
- Sep 2021
- Possession filed
- Dec 2025moved from Dec 2024
- Homes
- 27
- Booked
- 5 (19%)
MahaRERA P52100031012 · registered as SHREE · filed by PRIDE PROPERTIES & INFRASTRUCTURE
- Rank 22Due Dec 2025 · ask for OCRamkrupa Kothrud
completion filed for 31 Dec 2025, now passed, 20 of 54 homes not booked
- Registered
- Oct 2019
- Possession filed
- Dec 2025moved from Dec 2023
- Homes
- 54
- Booked
- 34 (63%)
MahaRERA P52100022539 · registered as Ramkrupa
- Rank 23Due Dec 2025 · ask for OCReshma Heights Co-Operative Housing Society LTD.
completion filed for 31 Dec 2025, now passed, 12 of 21 homes not booked
- Registered
- Jun 2023
- Possession filed
- Dec 2025
- Homes
- 21
- Booked
- 9 (43%)
MahaRERA P52100051614
- Rank 24Due Dec 2025 · ask for OCSangeetdhara by Vishva Gangotree Buildcon
completion filed for 31 Dec 2025, now passed, 12 of 21 homes not booked
- Registered
- Jan 2023
- Possession filed
- Dec 2025
- Homes
- 21
- Booked
- 9 (43%)
MahaRERA P52100048529
- Rank 25Due Dec 2025 · ask for OCSuparn by Badhekar Properties
completion filed for 31 Dec 2025, now passed, 21 of 26 homes not booked
- Registered
- Mar 2023
- Possession filed
- Dec 2025
- Homes
- 26
- Booked
- 5 (19%)
MahaRERA P52100050130
- Rank 26Due Dec 2025 · ask for OCVarun Enclave CHS by KIRIK ENTERPRISES
completion filed for 31 Dec 2025, now passed, 19 of 24 homes not booked
- Registered
- Feb 2023
- Possession filed
- Dec 2025
- Homes
- 24
- Booked
- 5 (21%)
MahaRERA P52100049179
- Rank 27Due Dec 2025 · ask for OCYoganand Park 2 by BELVALKAR HOUSING LLP
completion filed for 31 Dec 2025, now passed, 19 of 21 homes not booked
- Registered
- Jun 2023
- Possession filed
- Dec 2025
- Homes
- 21
- Booked
- 2 (10%)
MahaRERA P52100051502
- Rank 28Due Dec 2025 · ask for OCAnand by ARCHWAY PROPERTIES
completion filed for 30 Dec 2025, now passed, 17 of 24 homes not booked
- Registered
- Mar 2023
- Possession filed
- Dec 2025moved from Oct 2024
- Homes
- 24
- Booked
- 7 (29%)
MahaRERA P52100050190
- Rank 29Due Oct 2025 · ask for OCKalakunj CD by VG Empires LLP
completion filed for 31 Oct 2025, now passed, 26 of 41 homes not booked
- Registered
- May 2021
- Possession filed
- Oct 2025moved from Feb 2025
- Homes
- 41
- Booked
- 15 (37%)
MahaRERA P52100029413
- Rank 30Due Oct 2025 · ask for OCRatnankur by Ranjekar Realty LLP
completion filed for 31 Oct 2025, now passed, 18 of 39 homes not booked
- Registered
- Apr 2022
- Possession filed
- Oct 2025
- Homes
- 39
- Booked
- 21 (54%)
MahaRERA P52100035032
Questions buyers ask
- Which projects in Kothrud, Pune are ready to move?
- As of 24 Nov 2026, 30 projects in Kothrud have passed the completion date filed with MahaRERA in the last three years and still have 10 or more homes not booked, the newest Janhavi (18 Nov 2026). Ask the builder for the occupancy certificate (OC) before you book. The newest: Janhavi, Elitas, Ayodhyanagar, Dwarkakunj, Shri Laxmi Chhaya Sahakari Grahrachana Sanstha Marayadit.
- Does a passed completion date mean I can move in?
- Not on its own. The completion date is what the builder filed with MahaRERA. The occupancy certificate (OC) from the local authority is what says the building can be lived in: ask for it.
- Where do these numbers come from?
- MahaRERA's public records, read by Avasetu; this list was worked out on 2026-11-24. Each project's page shows the date we read its record.
How this list is made
Projects whose completion date filed with MahaRERA passed in the last three years and that still have 10 or more homes not booked, newest first. Offices and shops are left out. MahaRERA does not show the occupancy certificate, so ask the builder for it. Towers and phases of one project count once. From MahaRERA public records, worked out on 24 Nov 2026; each project's page shows the date we read its record. No builder pays to be on this list. This is general information, not investment or legal advice.