New projects and flats in Pimple Gurav, Pune
Updated 21 Nov 2026
- Projects being built
- 16
- Homes booked
- 46%
- Past their completion date
- 4
As of 24 Nov 2026, MahaRERA lists 16 housing projects in Pimple Gurav, Pune being built or recently finished. 687 of their 1,486 homes are booked. The earliest filed completion date is MK Crest (Dec 2025).
Every residential project MahaRERA lists in Pimple Gurav, the flats and apartments on sale here and the ones already handed over: 16 being built or recently finished, and 24 older ones. Before you buy a property in Pimple Gurav, each page shows the completion date the builder filed with MahaRERA, whether it has moved, and how many homes are booked, with the date we read the record.
Pimple Gurav: the good and what to check
What's going for it
- Room to choose: 799 of 1,486 homes in projects being built are still open.
- 3 projects have possession filed within the next 12 months.
Check before you book
- 5 of 16 projects have moved their possession date by 3 months or more, usually by 23 months (not counting MahaRERA's 2026 extension for all projects). See the date history on a project's page before you book.
- 4 projects are past the completion date filed with MahaRERA: ask for the occupancy certificate (OC) before you pay.
Counted from MahaRERA records of the projects on this page.
Most active projects in Pimple Gurav
- Krishna Prabha Aangan completion filed for 30 Mar 2027, moved 23 months later (MahaRERA)
- Eastern River Residency Wing Ij completion filed for 31 Dec 2035 (MahaRERA)
- 10 Elite Akasa completion filed for 30 Apr 2030 (MahaRERA)
- 7 Avenue Pimple Gurav completion filed for 28 Jun 2028 (MahaRERA)
- Silver Paradise Pimple Gurav completion filed for 31 Mar 2026 (MahaRERA)
- MK Crest completion filed for 31 Dec 2025 (MahaRERA)
- Eastern River Residency Wing B completion filed for 30 Jun 2026, moved 8 months later (MahaRERA)
- Eastern River Residency MHADA Buildings completion filed for 30 Apr 2029 (MahaRERA)
Being built (16)
New launch (1)
- Eastern River Residency Wing Ij Checked 2/4by M/s Vinayak Enterprises · possession Dec 2035 · 0/148 booked
Early stage (2)
- 1 Priority Rathod Business Zone MahaRERA onlyby Shreeji Developers · possession Dec 2029 · 0/23 booked
- 10 Elite Akasa Checkedby Kadam Jagtap Associates · possession Apr 2030 · 39/264 booked
Mid stage (5)
- 7 Avenue Pimple Gurav MahaRERA onlyby Destiny Developers · possession Jun 2028 · 0/24 booked
- B-Capital MahaRERA onlypossession Jul 2028 · 12/37 booked
- ChandraSi Elite MahaRERA onlypossession Jul 2028 · 9/87 booked
- Eastern River Residency MHADA Buildings MahaRERA onlypossession Apr 2029
- Westmark MahaRERA onlyby Aceprime Skyscraper LLP · possession Mar 2029 · 38/66 booked
Near completion (2)
- Akshay Vista MahaRERA onlyby Akshay Skyscrapers Private Limited · possession May 2027 · 30/58 booked
- Dwarkadhish Apartment MahaRERA onlypossession Feb 2027
Completion date passed (4)
- Govind Riverine MahaRERA onlypossession Mar 2026
- Lambodar Residence MahaRERA onlyby Vighnaharta Landmarks · possession Oct 2026
- MK Crest MahaRERA onlyby Mk Buildcon · possession Dec 2025
- Silver Paradise Pimple Gurav MahaRERA onlypossession Mar 2026
Dates not read yet (2)
- Eastern River Residency Wing B MahaRERA onlypossession Jun 2026 · 520/591 booked
- Krishna Prabha Aangan Checked 3/4possession Mar 2027 · 39/188 booked
Stage by dates: how much of the time between MahaRERA registration and the completion date the builder filed has gone. Not a site check: MahaRERA’s construction progress reports are behind its login.
Finished more than a year ago (24)
- Amit Developers and Builder MahaRERA onlyby Amit Developers & Builder · possession Dec 2019
- Avnindra MahaRERA onlypossession Feb 2022
- Basileo Phase 2 MahaRERA onlyby Kate Jagtap Associates · possession Feb 2020
- Chandrarang Floret MahaRERA onlyby Chandrarang Developer and Builders Private Limited · possession Oct 2024
- Engracia MahaRERA onlyby Jagtap Patil Promoters & Builders · possession Dec 2019
- Ganesh Residency MahaRERA onlyby Trimurti Promotors And Developers · possession Mar 2024
- Garve Patil Samrajya Wing GH MahaRERA onlyby Garve Patil Construction Company · possession Jun 2023 · 182/425 booked
- Kate Central MahaRERA onlyby M/S Kate Construction · possession Aug 2018
- Laxmirang Heights MahaRERA onlyby Jawalkar Associates · possession Dec 2017
- Rajyog Royal MahaRERA onlyby Rajyog Builders and Developers · possession Jun 2021
- Ratnadeep MahaRERA onlyby G P Enterprises · possession Dec 2020
- Ravi Karan Heights MahaRERA onlyby Ramkrishna Developers · possession Dec 2019
- S R K Corner MahaRERA onlyby S R K Buildcon · possession Dec 2023
- S R K Corner MahaRERA onlyby S R K Realty · possession Sep 2020
- Sai Avenue MahaRERA onlyby Sai Buildcon · possession Dec 2023
- Sai Nisarg MahaRERA onlypossession Dec 2018
- Saipushp Residency MahaRERA onlyby Rohit Developers · possession Sep 2020
- Saiyog MahaRERA onlyby Kadam Developers · possession Jun 2018
- Salunkhe Heights MahaRERA onlyby Pandurang Developers · possession Sep 2024
- Shree Swami Samarth Apartment MahaRERA onlypossession May 2025
- Siddhi Iris MahaRERA onlyby Jai Ganesh Construction · possession Jun 2024
- Soham Residency MahaRERA onlyby Khushbu Realties Pvt. Ltd · possession Jan 2020
- Vaishnavi Pride Pimple Gurav MahaRERA onlypossession May 2024
- Varad Residency MahaRERA onlypossession Jan 2021
Questions buyers ask about Pimple Gurav
- How many new projects are there in Pimple Gurav, Pune?
- 16 projects registered with MahaRERA are being built or recently finished in Pimple Gurav as of 24 Nov 2026, out of 49 projects MahaRERA has listed there.
- Which projects in Pimple Gurav have the earliest possession?
- By the completion date the builder filed with MahaRERA: MK Crest (Dec 2025), Govind Riverine (Mar 2026), Silver Paradise Pimple Gurav (Mar 2026). A filed date can move; each project's page shows whether it has.
- Do builders in Pimple Gurav keep their possession dates?
- 5 of the 16 projects being built in Pimple Gurav whose dates we have read have moved their MahaRERA possession date by 3 months or more, usually by 23 months, not counting MahaRERA's 2026 extension for all projects. Each project's page shows its own date history.
- Where do these Pimple Gurav numbers come from?
- MahaRERA's public register, read by Avasetu; each project's page shows the date we read its record. No builder pays to be listed.
From MahaRERA's public records, read on the date shown on each project's page. A project is listed under the area of the pincode it is filed under. This is general information, not investment or legal advice.