Mahindra Citadel Phase 1, Pimpri
See the site from above todayby Mahindra Lifespaces · Pimpri, Haveli, Pune district · 411018
- Possession
- from Oct 2028
- its parts filed Oct 2028 to Dec 2031
- Booked
- 732 of 1,329
- 14 booked in the last 30 days
Avasetu's read (from MahaRERA data, 20 Oct 2026)
446 of 448 homes are booked, which is 100 percent compared to about 74 percent for 14 similar Pimpri projects. The completion date filed with MahaRERA is 30 Oct 2028. Out of 22 Mahindra Lifespaces projects in Pune, 2 moved the completion date 3 months or more later.
What stands out
As of 19 Nov 2026, from MahaRERA and the sources below.
- Homes booked: All 448 homes in this registration are booked, similar projects are at about 55%
- Completion date changed: MahaRERA's order added 4 months to the completion date, which is now 30 Oct 2028
Updated 21 Nov 2026
Pictures
From the builder's website. Renders are the builder's artist's impressions and plans are indicative: check the sanctioned plans before you book.
Price
No price for Mahindra Citadel Phase 1 is published yet.
What new homes in Pimpri usually ask
- 2 BHK about ₹70 L – ₹1.1 Cr (4 projects)
- 3 BHK about ₹1.2 – 2.1 Cr (5 projects)
- 4 BHK about ₹2 – 2.8 Cr (6 projects)
Our own guide: the middle half of the starting prices we have read for projects being sold in Pimpri, rounded. Use it to judge an offer, not as a price.
Pimpri average ₹12,820/sq ft across 4 projectsThe middle asking price per sq ft of other projects in Pimpri.
Ask about this project
Outside our main East Pune areas: the Avasetu team finds out what it can.
Mahindra Citadel Phase 1 from above, today
Mahindra Citadel Phase 1, year by year, up close
Sharp satellite pictures taken in Nov 2022, Jan 2024, Feb 2025 and Apr 2026, centred on the project's map pin, about 580 m across at about 0.3 m a pixel.
Nov 2022 Jan 2024 Feb 2025 Apr 2026 · latest
Each picture is dated by when it was taken; the ring is 100 m around the pin. Map image is the intellectual property of Esri and is used herein under license. Copyright © 2026 Esri and its licensors (imagery: Maxar, Vantor). All rights reserved. Compare every release ↗
Latest reading from space, Oct–Dec 2026 (looked Nov 2026)
Ground cleared
Registered with MahaRERA Nov 2022 · possession filed for from Oct 2028
Satellite imagery shows the transition of open land into active construction following the initial November 2022 registration. Over subsequent years, ground clearing leads to deep shadows from tall structures, aligning with the registered phases.
The seasons before
- Apr–May 2026Established building footprints and shadows visible within the ring.
- Jan–Mar 2026Multiple tall building shadows and active construction visible inside the ring.
- Oct–Dec 2025New structures and shadows expand within and near the ring area.
Construction proof from space: Jan 2021 to Oct 2026, Copernicus Sentinel-2 (13 earlier seasons)
- Apr–May 2025Construction footprints and shadows persist inside the ring.
- Jan–Mar 2025Tall building shadows and active construction footprints visible inside the ring.
- Oct–Dec 2024Dark shadows from emerging tall structures indicate building growth within the ring.
- Apr–May 2024Bright structures and active construction footprints visible inside the ring.
- Jan–Mar 2024Foundations and early building structures appear inside the ring.
- Oct–Dec 2023Initial structural footprints and earthwork visible within the ring.
- Apr–May 2023Bare soil and construction activity signs visible inside the ring.
- Jan–Mar 2023Cleared land and excavation marks visible inside the ring.
- Oct–Dec 2022Ground clearing and early site preparation visible after the November 2022 registration.
- Jan–Mar 2022Sparse vegetation and open ground remain visible within the ring.
- Oct–Dec 2021Green vegetation increases slightly inside the ring following monsoon rains.
- Apr–May 2021Dry ground and sparse vegetation visible inside the ring; little change observed.
- Jan–Mar 2021Vegetation and open land visible inside the ring; little change from previous periods.
The yellow ring marks the project's map pin. Each picture is 600 m across at 10 m a pixel: it takes in neighbouring plots, and shows ground, not floors. The satellite sees 10 m a pixel, so this shows that the ground changed, not the towers themselves. Pictures are the middle of every clear pass, sharpened and colour-corrected by code; nothing is drawn in. The timeline starts a year before the project registered. The lines are written from the pictures and the MahaRERA filings, and say only what can be seen. Contains modified Copernicus Sentinel data 2021-2026.
Floor plans
Location
Position checkedThe project's pin on Google Maps, checked against its MahaRERA name and pincode. Open the map (opens in a new tab)
Work hubs
- Baner-Balewadi High Street6.6 km
- Hinjawadi Phase 1 (Rajiv Gandhi Infotech Park)8.4 km
- Pune Airport (Lohegaon)10.9 km
- Pune Railway Station11.7 km
Nearby
- Industrial areaICC Devi Gaurav Technology Park0.2 km
- CollegeDr. D. Y. Patil Institute of Technology0.8 km
- HospitalPCMC PGI Yashwantrao Chavan Memorial Hospital1 km
- HospitalD Y Patil Hospital In Pune1.2 km
- Railway stationKasarwadi1.3 km
Straight-line distances; the drive is longer. Places: Google Maps.
Project facts
- Spread across 9.66 acres of development. (the builder's site)
- Offers 1, 2, 3 and 4 BHK homes. (the builder's site)
Amenities
- Includes two clubhouses spanning 21,000 sq ft. (the builder's site)
Last checked 13 Nov 2026.
MahaRERA record
From MahaRERA, read 19 Nov 2026Possession date
30 Oct 2028 to 31 Dec 2031
The completion dates filed with MahaRERA for its 3 registrations; each is in the table of towers and phases below.
For P52100047656: 30 Oct 2028. The completion date filed with MahaRERA is 30 Oct 2028; MahaRERA's August 2026 order added 4 months to it (the builder has not moved it). At registration: 30 Jun 2028.
The record
- Homes booked
- 732 of 1,329
- Across all 3 of its MahaRERA registrations. P52100047656 alone: 446 of 448.
- Towers
- 4 in this registration
- The tallest has 30 floors.
- Registered on
- 17 Nov 2022
- Main MahaRERA registration
- P52100047656
- Listed or updated on MahaRERA 17 Nov 2022.
- Promoter (builder)
- Mahindra Lifespace Developers limited
- Project type
- Residential / Group Housing
- Pincode
- 411018
Check before you book
From MahaRERA- Towers go up to 30 floors. Ask how many lifts serve your tower and how many homes share them.
Tower by tower
3 registrations, 4 buildings
Towers and phases (3 registrations)
From MahaRERAMahaRERA holds Mahindra Citadel Phase 1 as 3 registrations. Together they list 1,329 homes, 732 booked.
| Registration | Completion filed | Booked |
|---|---|---|
| Mahindra Citadel Phase 1P52100047656 (opens in a new tab) | 30 Oct 2028at registration 30 Jun 2028 | 446 of 448 |
| Mahindra Citadel - Tower LPR1260002500154 (opens in a new tab) | 30 Apr 2031at registration 31 Dec 2030 | 146 of 211 |
| Mahindra Citadel - Phase 5PM1264042600425 (opens in a new tab) | 31 Dec 2031at registration 31 Aug 2031 | 140 of 670 |
Each row is its own MahaRERA registration, as filed.
Buildings
From MahaRERA| Building | Floors | Homes | Other |
|---|---|---|---|
| Tower A | 30 | 137 | 0 |
| Tower B | 30 | 88 | 0 |
| Tower C | 30 | 88 | 0 |
| Tower D | 30 | 135 | 0 |
As filed with MahaRERA (sanctioned floors).
What the builder's and property sites say
Gathered and checkedLast checked 13 Nov 2026. MahaRERA counts where they differ.
Mahindra Lifespaces: track record
From MahaRERA recordsMahindra Lifespaces has 21 projects in our MahaRERA register for Pune. 1 of 21 with both dates moved the completion date 3 months or more later, by 3 months on average.
- Antheia C1completion filed 31 Mar 2018
- Antheia A4completion filed 30 Jun 2018
- Antheia B4completion filed 30 Jun 2018
- Antheia D4completion filed 30 Jun 2018
- Antheia C2completion filed 31 Dec 2018
- MSPACEcompletion filed 31 Dec 2019
- Antheia B3completion filed 30 Sep 2020
- Antheia A3completion filed 30 Dec 2020
- Centro MHADAcompletion filed 28 Feb 2023
- Antheia C3completion filed 30 Mar 2023
- Centralis Tower 4completion filed 30 Mar 2023
- Happinest Tathawade Phase-1completion filed 31 May 2027
- Nest EWScompletion filed 31 May 2027
- Mahindra Happinest Tathawade Phase 2completion filed 30 Sep 2027
- MAHINDRA NESTALGIAcompletion filed 31 Dec 2027
- Mahindra Citadel - Bastion J , Kcompletion filed 30 Oct 2029
- Mahindra Citadel - Bastion Icompletion filed 30 Jul 2030
- Mahindra Codename Crown Tower A and Tower Bcompletion filed 31 Jul 2030, moved 3 months later
- Mahindra IvyLush Tower C and Tower Dcompletion filed 31 Dec 2030
- Mahindra Rivenza Phase 2completion filed 30 Dec 2031
Planning to buy here?
Ask about prices, floor plans, offers or a site visit.
Other projects in Pimpri
More by Mahindra Lifespace Developers limited
- Mahindra Happinest Tathawade Phase-1possession May 2027
- Mahindra Citadelpossession Jul 2030
- Mahindra Citadel - Bastion J , Kpossession Oct 2029
- Mahindra Codename Crown in Wagholi3 BHK · from ₹1.38 Cr · possession Jul 2030
- Mahindra Happinest Tathawadepossession Sep 2027
- Mahindra IvyLush Tower C and Tower D2 BHK · from ₹95 L · possession Dec 2030
- Mahindra Rivenza2, 3, 4 BHK · from ₹90 L · possession Dec 2031
- Mahindra Nest EWSpossession May 2027
FAQ
What is the price of Mahindra Citadel Phase 1?
No price for Mahindra Citadel Phase 1 is published yet. Ask through the enquiry form on this page for the current price.
What is the possession date of Mahindra Citadel Phase 1?
The 3 MahaRERA registrations of Mahindra Citadel Phase 1 have filed completion dates from 30 Oct 2028 to 31 Dec 2031. For P52100047656: The completion date filed with MahaRERA is 30 Oct 2028; MahaRERA's August 2026 order added 4 months to it (the builder has not moved it).
What is the MahaRERA number of Mahindra Citadel Phase 1?
Mahindra Citadel Phase 1 is registered with MahaRERA in 3 parts (towers or phases): P52100047656, PR1260002500154, PM1264042600425.
How many towers and floors does Mahindra Citadel Phase 1 have?
MahaRERA lists 4 buildings in registration P52100047656, one of the project's 3, the tallest with 30 floors.
How many flats are there in Mahindra Citadel Phase 1?
MahaRERA lists 1329 units across all 3 of its MahaRERA registrations; P52100047656 has 448.
How many homes in Mahindra Citadel Phase 1 are booked?
732 of 1329 homes were booked as per MahaRERA on 19 Nov 2026, across all 3 of its MahaRERA registrations.
Who is the builder of Mahindra Citadel Phase 1?
The promoter registered with MahaRERA is Mahindra Lifespace Developers limited. Our register has 21 Pune projects by Mahindra Lifespaces; 1 of 21 with both dates moved their completion date 3 months or more later.
Where is Mahindra Citadel Phase 1?
Mahindra Citadel Phase 1 is in 411018, Haveli, Pune district (pincode 411018).
Which hospital is nearest to Mahindra Citadel Phase 1?
PCMC PGI Yashwantrao Chavan Memorial Hospital, about 1 km away in a straight line from the map position; the drive is longer.
Which railway station is nearest to Mahindra Citadel Phase 1?
Kasarwadi, about 1.3 km away in a straight line from the map position; the drive is longer.
How far is Mahindra Citadel Phase 1 from Pune Airport?
About 10.9 km in a straight line from the map position; the drive is longer.
How far is Mahindra Citadel Phase 1 from Baner-Balewadi High Street?
About 6.6 km in a straight line from the map position; the drive is longer. It is the nearest of Pune's main work hubs to Mahindra Citadel Phase 1.
Sources
- Registration, promoter, pincodeFrom MahaRERA
MahaRERA listing, updated 17 Nov 2022
- Dates and homes bookedFrom MahaRERA
Checked 13 Nov 2026
- Buildings and wingsFrom MahaRERA
Checked 5 Nov 2026
- Location and nearbyGathered and checked
Checked 13 Nov 2026
- DescriptionGathered and checked
Checked 13 Nov 2026
- Project facts and amenitiesGathered and checked
The builder's site and property sites, which can be wrong: where they differ from MahaRERA, MahaRERA counts (13 Nov 2026)