River Nest Building A, Moshi
Filed on MahaRERA as River Nest Building A Wing B
See the site from above todayby Amarnath Group of Companies · Moshi, Haveli, Pune district · 412105
- Possession
- from Oct 2027
- its parts filed Oct 2027 to Dec 2029
- Booked
- 358 of 592
- across all 3 of its MahaRERA registrations
As of 19 Nov 2026, River Nest Building A by Amarnath Group of Companies in Moshi, Pune district is registered with MahaRERA in 3 parts, the main one P52100047001. Its parts have filed completion dates from 30 Oct 2027 to 31 Dec 2029. For P52100047001: The completion date filed with MahaRERA is 30 Oct 2027, moved from 31 Dec 2025 at registration (MahaRERA's August 2026 order added 4 months to most projects). MahaRERA shows 358 of 592 homes booked, across all 3 of its MahaRERA registrations.
Updated 21 Nov 2026
Our team is still collecting details on River Nest Building A.
We do not have prices, the builder's pictures and floor plans yet. What you see here is what we have now: MahaRERA's record, read on the date shown. Ask us and we send you what we find first.
Price
No price for River Nest Building A is published yet.
What new homes in Moshi usually ask
- 1 BHK about ₹30 – 45 L (11 projects)
- 2 BHK about ₹45 – 65 L (54 projects)
- 2.5 BHK about ₹65 – 80 L (4 projects)
- 3 BHK about ₹65 – 90 L (41 projects)
- 4 BHK about ₹1.1 – 1.9 Cr (6 projects)
Our own guide: the middle half of the starting prices we have read for projects being sold in Moshi, rounded. Use it to judge an offer, not as a price.
Moshi average ₹7,638/sq ft across 18 projectsThe middle asking price per sq ft of other projects in Moshi.
Ask about this project
Outside our main East Pune areas: the Avasetu team finds out what it can.
River Nest Building A from above, today
River Nest Building A, year by year, up close
Sharp satellite pictures taken in Nov 2022, Jan 2024, Jan 2025 and Apr 2026, centred on the project's map pin, about 580 m across at about 0.5 m a pixel.
Nov 2022 Jan 2024 Jan 2025 Apr 2026 · latest
Each picture is dated by when it was taken; the ring is 100 m around the pin. Map image is the intellectual property of Esri and is used herein under license. Copyright © 2026 Esri and its licensors (imagery: Maxar, Vantor). All rights reserved. Compare every release ↗
Latest reading from space, Oct–Dec 2026 (looked Nov 2026)
Work shows after the Oct 2026 registration with expanded footprints.
possession filed for from Oct 2027
The site shows gradual clearing and construction activity across multiple MahaRERA registrations from 2022 to 2026, transitioning from vegetated plots to built structures and cleared grounds.
The seasons before
- Jan–Mar 2024Sparse vegetation remains inside the ring.
- Jan–Mar 2023Plant cover drops further as clearing continues.
- Oct–Dec 2022Work shows after the Sep 2022 registration with new structures.
Construction proof from space: Jan 2021 to Nov 2026, Copernicus Sentinel-2 (2 earlier seasons)
- Jan–Mar 2022Plant cover decreases slightly inside the ring.
- Jan–Mar 2021Ring shows green patches, paths, and scattered structures.
The yellow ring marks the project's map pin. Each picture is 600 m across at 10 m a pixel: it takes in neighbouring plots, and shows ground, not floors. The satellite sees 10 m a pixel, so this shows that the ground changed, not the towers themselves. Pictures are the middle of every clear pass, sharpened and colour-corrected by code; nothing is drawn in. The timeline starts a year before the project registered. The lines are written from the pictures and the MahaRERA filings, and say only what can be seen. Contains modified Copernicus Sentinel data 2021-2026.
Floor plans
Location
Position checkedThe project's pin on Google Maps, checked against its MahaRERA name and pincode. Open the map (opens in a new tab)
Work hubs
- Pune Airport (Lohegaon)8.9 km
- EON IT Park, Kharadi12.8 km
- World Trade Center, Kharadi12.9 km
- Pune Railway Station14.9 km
Nearby
- TempleWagheshwar Maharaj Temple0.7 km
- BankAxis Bank1.6 km
- TempleShree Sant Dnyaneshwar Maharaj Samadhi Mandir, Alandi2 km
- TempleJalaram temple - Alandi Pune2 km
- CollegeMIT Alandi Campus2.1 km
Straight-line distances; the drive is longer. Places: Google Maps and © OpenStreetMap contributors.
MahaRERA record
From MahaRERA, read 19 Nov 2026Possession date
30 Oct 2027 to 31 Dec 2029
The completion dates filed with MahaRERA for its 3 registrations; each is in the table of towers and phases below.
For P52100047001: 30 Oct 2027. Completion date filed with MahaRERA. At registration: 31 Dec 2025. Moved 18 months later, 4 of them by MahaRERA's August 2026 order for most projects.
Ask for the possession date in writing in your agreement for sale.
The record
- Homes booked
- 358 of 592
- Across all 3 of its MahaRERA registrations. P52100047001 alone: 192 of 282.
- Towers
- 1 in this registration
- The tallest has 25 floors.
- Units
- 282
- 256 homes, 26 shops or offices.
- Registered on
- 26 Sep 2022
- Main MahaRERA registration
- P52100047001
- Listed or updated on MahaRERA 16 Sep 2026.
- Promoter (builder)
- Amarnath Group of Companies
- Project type
- Others
- Pincode
- 412105
Check before you book
From MahaRERA- The builder has moved the completion date 18 months later since registration, from Dec 2025 to Oct 2027 (MahaRERA's 2026 blanket extension for all projects left out). Ask why, and which date goes in your agreement for sale.
- 26 shops or offices are part of the project. Ask where they open and whether their visitors use the residents' gate.
Tower by tower
3 registrations, 1 building
Towers and phases (3 registrations)
From MahaRERAMahaRERA holds River Nest Building A as 3 registrations. Together they list 592 homes, 358 booked.
| Registration | Completion filed | Booked |
|---|---|---|
| River Nest Building A Wing BP52100047001 (opens in a new tab) | 30 Oct 2027at registration 31 Dec 2025 | 192 of 282 |
| River Nest Building A Wing CP52100051184 (opens in a new tab) | 30 Oct 2027at registration 30 Jun 2026 | 166 of 215 |
| RIVER NEST BUILDING A WING D AND EPR1260002602451 (opens in a new tab) | 31 Dec 2029 | 0 of 95 |
Each row is its own MahaRERA registration, as filed.
Buildings
From MahaRERA| Building | Floors | Homes | Other |
|---|---|---|---|
| B Wing | 25 | 256 | 26 |
As filed with MahaRERA (sanctioned floors).
Amarnath Group of Companies: track record
From MahaRERA recordsAmarnath Group of Companies has 1 project in our MahaRERA register for Pune.
Planning to buy here?
Ask about prices, floor plans, offers or a site visit.
Other projects in Moshi
FAQ
What is the price of River Nest Building A?
No price for River Nest Building A is published yet. Ask through the enquiry form on this page for the current price.
What is the possession date of River Nest Building A?
The 3 MahaRERA registrations of River Nest Building A have filed completion dates from 30 Oct 2027 to 31 Dec 2029. For P52100047001: The completion date filed with MahaRERA is 30 Oct 2027. At registration it was 31 Dec 2025. MahaRERA added 4 months to most projects' dates in August 2026 (Order 66/2026). Ask the builder for the possession date in your agreement, in writing.
What is the MahaRERA number of River Nest Building A?
River Nest Building A is registered with MahaRERA in 3 parts (towers or phases): P52100047001, P52100051184, PR1260002602451.
How many towers and floors does River Nest Building A have?
MahaRERA lists 1 building in registration P52100047001, one of the project's 3, the tallest with 25 floors.
How many flats are there in River Nest Building A?
MahaRERA lists 592 units across all 3 of its MahaRERA registrations; P52100047001 has 282.
How many homes in River Nest Building A are booked?
358 of 592 homes were booked as per MahaRERA on 19 Nov 2026, across all 3 of its MahaRERA registrations.
Who is the builder of River Nest Building A?
The promoter registered with MahaRERA is Amarnath Group of Companies.
Where is River Nest Building A?
River Nest Building A is in Haveli, Pune district (pincode 412105).
How far is River Nest Building A from Pune Airport?
About 8.9 km in a straight line from the map position; the drive is longer.
How far is River Nest Building A from EON IT Park, Kharadi?
About 12.8 km in a straight line from the map position; the drive is longer. It is the nearest of Pune's main work hubs to River Nest Building A.
Sources
- Registration, promoter, pincodeFrom MahaRERA
MahaRERA listing, updated 16 Sep 2026
- Dates and homes bookedFrom MahaRERA
Checked 19 Nov 2026
- Buildings and wingsFrom MahaRERA
Checked 19 Nov 2026
- Location and nearbyGathered and checked
Checked 19 Nov 2026
- DescriptionNot checked yet
Still checking
Get the price sheet and floor plans for River Nest Building A Wing B
The Avasetu team calls or WhatsApps you back; we never share your number without your OK.