Sadguru Empire, Ravet
by Sadguru Developers And Builders · Ravet, Haveli, Pune district · 412101
- Possession
- Jun 2027
- completion filed with MahaRERA
- Booked
- 97 of 126
What stands out
As of 20 Nov 2026, from MahaRERA and the sources below.
- The project was originally registered to finish by 30 Jun 2023, but the filed completion date with MahaRERA is now 30 Jun 2027.
- 77% of homes booked: Buyers have committed to 97 of the 126 homes in this single 15-floor tower.
- With 126 homes, this development is larger by unit count than 114 of 192 ongoing projects in Ravet.
Updated 22 Nov 2026
Our team is still collecting details on Sadguru Empire.
We do not have prices, the builder's pictures and floor plans yet. What you see here is what we have now: MahaRERA's record, read on the date shown. Ask us and we send you what we find first.
Price
No price for Sadguru Empire is published yet.
What new homes in Ravet usually ask
- 2 BHK about ₹60 – 85 L (47 projects)
- 2.5 BHK about ₹90 L – ₹1.1 Cr (3 projects)
- 3 BHK about ₹85 L – ₹1.2 Cr (51 projects)
- 4 BHK about ₹1.6 – 2 Cr (8 projects)
Our own guide: the middle half of the starting prices we have read for projects being sold in Ravet, rounded. Use it to judge an offer, not as a price.
Ravet average ₹9,812/sq ft across 30 projectsThe middle asking price per sq ft of other projects in Ravet.
Ask about this project
Outside our main East Pune areas: the Avasetu team finds out what it can.
Floor plans
Location
Position checkedThe project's pin on Google Maps, checked against its MahaRERA name and pincode. Open the map (opens in a new tab)
Sadguru Empire, year by year, up close
Sharp satellite pictures taken in Nov 2022, Jan 2024, Feb 2025 and Apr 2026, centred on the project's map pin, about 580 m across at about 0.3 m a pixel.
Nov 2022 Jan 2024 Feb 2025 Apr 2026 · latest
Each picture is dated by when it was taken; the ring is 100 m around the pin. Map image is the intellectual property of Esri and is used herein under license. Copyright © 2026 Esri and its licensors (imagery: Maxar, Vantor). All rights reserved. Compare every release ↗
Work hubs
- Hinjawadi Phase 1 (Rajiv Gandhi Infotech Park)7.6 km
- Baner-Balewadi High Street11.1 km
- Pune Airport (Lohegaon)21.1 km
- Pune Railway Station21.3 km
Nearby
- SchoolS.B. Patil Public School (SBPPS) Ravet, Pune2.1 km
- Railway stationDehu Road2.5 km
- TempleISKCON (Shree Govinda Dham) Ravet3 km
- ShoppingD Mart Ravet3.4 km
- CollegeD. Y. Patil International University3.7 km
Straight-line distances; the drive is longer. Places: Google Maps.
Amenities
- Rain water harvesting system.
- Open and closed parking spaces.
Last checked 21 Nov 2026.
MahaRERA record
From MahaRERA, read 20 Nov 2026Possession date
30 Jun 2027
Completion date filed with MahaRERA. At registration: 30 Jun 2023. Moved 44 months later, 4 of them by MahaRERA's August 2026 order for most projects.
Ask for the possession date in writing in your agreement for sale.
Beside other Ravet projects
Worked out by Avasetu- Completion date
- Moved 44 months later
- 55 of 205 Ravet projects being built moved theirs 3 months or more.
From MahaRERA records read 20 Nov 2026. Dates net of MahaRERA's August 2026 order.
The record
- Homes booked
- 97 of 126
- Towers
- 1 in this registration
- The tallest has 15 floors.
- Registered on
- 1 Jul 2020
- MahaRERA registration
- P52100025665
- Listed or updated on MahaRERA 21 Aug 2026.
- Promoter (builder)
- Sadguru Developers And Builders
- Project type
- Residential / Group Housing
- Pincode
- 412101
Check before you book
From MahaRERA- The builder has moved the completion date 44 months later since registration, from Jun 2023 to Jun 2027 (MahaRERA's 2026 blanket extension for all projects left out). Ask why, and which date goes in your agreement for sale.
Tower by tower
1 building
Buildings
From MahaRERA| Building | Floors | Homes | Other |
|---|---|---|---|
| C WING | 15 | 126 | 0 |
As filed with MahaRERA (sanctioned floors).
Sadguru Developers And Builders: track record
From MahaRERA recordsSadguru Developers And Builders has 2 projects in our MahaRERA register for Pune.
- Sadguru Empire - A and B Wingcompletion filed 30 Jun 2028, moved 14 months later
Planning to buy here?
Ask about prices, floor plans, offers or a site visit.
Other projects in Ravet
More by Sadguru Developers And Builders
FAQ
What is the price of Sadguru Empire?
No price for Sadguru Empire is published yet. Ask through the enquiry form on this page for the current price.
What is the possession date of Sadguru Empire?
The completion date filed with MahaRERA is 30 Jun 2027. At registration it was 30 Jun 2023. MahaRERA added 4 months to most projects' dates in August 2026 (Order 66/2026). Ask the builder for the possession date in your agreement, in writing.
What is the MahaRERA number of Sadguru Empire?
Sadguru Empire is registered with MahaRERA as P52100025665.
How many towers and floors does Sadguru Empire have?
MahaRERA lists 1 building, the tallest with 15 floors.
How many flats are there in Sadguru Empire?
MahaRERA lists 126 units.
How many homes in Sadguru Empire are booked?
97 of 126 homes were booked as per MahaRERA on 20 Nov 2026.
Who is the builder of Sadguru Empire?
The promoter registered with MahaRERA is Sadguru Developers And Builders. Our register has 2 Pune projects by Sadguru Developers And Builders.
Where is Sadguru Empire?
Sadguru Empire is in Haveli, Pune district (pincode 412101).
Which school is nearest to Sadguru Empire?
S.B. Patil Public School (SBPPS) Ravet, Pune, about 2.1 km away in a straight line from the map position; the drive is longer.
Which railway station is nearest to Sadguru Empire?
Dehu Road, about 2.5 km away in a straight line from the map position; the drive is longer.
How far is Sadguru Empire from Pune Airport?
About 21.1 km in a straight line from the map position; the drive is longer.
How far is Sadguru Empire from Hinjawadi Phase 1 (Rajiv Gandhi Infotech Park)?
About 7.6 km in a straight line from the map position; the drive is longer. It is the nearest of Pune's main work hubs to Sadguru Empire.
Sources
- Registration, promoter, pincodeFrom MahaRERA
MahaRERA listing, updated 21 Aug 2026
- Dates and homes bookedFrom MahaRERA
Checked 21 Nov 2026
- Buildings and wingsFrom MahaRERA
Checked 21 Nov 2026
- Location and nearbyGathered and checked
Checked 21 Nov 2026
- DescriptionGathered and checked
Checked 21 Nov 2026
- Project facts and amenitiesGathered and checked
The builder's site and property sites, which can be wrong: where they differ from MahaRERA, MahaRERA counts (21 Nov 2026)
Get the price sheet and floor plans for SADGURU EMPIRE
The Avasetu team calls or WhatsApps you back; we never share your number without your OK.