MahaRERA registered P52100031375Verify on MahaRERA (opens in a new tab)Completion date passed

Sai Apartments, Maval taluka

by Kevinn Construction · Maval taluka, Mawal, Pune district · 412106

Possession
Jun 2025
completion filed with MahaRERA

As of 14 Oct 2026, Sai Apartments by Kevinn Construction in Maval taluka, Pune district is registered with MahaRERA as P52100031375. The completion date filed with MahaRERA is 30 Jun 2025, moved from 15 Dec 2022 at registration. The filed completion date has passed: ask for the occupancy certificate (OC).

Updated 14 Oct 2026

Location

A map search by name. Open the map (opens in a new tab)

MahaRERA record

From MahaRERA, read 14 Oct 2026

Possession date

30 Jun 2025

Completion date filed with MahaRERA. At registration: 15 Dec 2022. Moved 30 months later.

The filed completion date has passed. Ask for the occupancy certificate (OC) before you book.

Ask for the possession date in writing in your agreement for sale.

Beside other Maval taluka projects

Worked out by Avasetu
Completion date
Moved 30 months later
10 of 46 Maval taluka projects being built moved theirs 3 months or more.

From MahaRERA records read 14 Oct 2026. Dates net of MahaRERA's August 2026 order.

The record

Registered on
23 Oct 2021
MahaRERA registration
P52100031375
Listed or updated on MahaRERA 31 Jan 2024.
Promoter (builder)
Kevinn Construction
Pincode
412106

Open the MahaRERA record (opens in a new tab)

Check before you book

From MahaRERA
  • The completion date filed with MahaRERA (Jun 2025) has passed. Ask for the occupancy certificate (OC) before you pay anything more.
  • The builder has moved the completion date 30 months later since registration, from Dec 2022 to Jun 2025. Ask why, and which date goes in your agreement for sale.

Kevinn Construction: track record

From MahaRERA records

Kevinn Construction has 1 project in our MahaRERA register for Pune.

FAQ

What is the price of Sai Apartments?

No price for Sai Apartments is published yet. Ask through the enquiry form on this page for the current price.

What is the possession date of Sai Apartments?

The completion date filed with MahaRERA is 30 Jun 2025. At registration it was 15 Dec 2022. Ask the builder for the possession date in your agreement, in writing.

What is the MahaRERA number of Sai Apartments?

Sai Apartments is registered with MahaRERA as P52100031375.

Who is the builder of Sai Apartments?

The promoter registered with MahaRERA is Kevinn Construction.

Where is Sai Apartments?

Sai Apartments is in Mawal, Pune district (pincode 412106).

Has the completion date of Sai Apartments passed?

Yes. Ask the builder for the occupancy certificate (OC) before you book.

Sources
  • Registration, promoter, pincodeFrom MahaRERA

    MahaRERA listing, updated 31 Jan 2024

  • Dates and homes bookedNot checked yet

    Still checking

  • Buildings and wingsNot checked yet

    Still checking

  • Location and nearbyNot checked yet

    Still checking

  • DescriptionNot checked yet

    Still checking