Sai Shivam, Talegaon
by S.r. Developers · Talegaon, Mawal, Pune district · 410507
- Possession
- Oct 2021
- completion filed with MahaRERA
As of 17 Oct 2026, Sai Shivam by S.r. Developers in Talegaon, Pune district is registered with MahaRERA as P52100012266. The completion date filed with MahaRERA is 30 Oct 2021, moved from 30 Apr 2019 at registration. The filed completion date has passed: ask for the occupancy certificate (OC).
Updated 17 Oct 2026
Still being built in Talegaon
Sai Shivam is finished (completion filed for Oct 2021), so we do not take enquiries for it. These projects nearby still have homes to book, the soonest possession first.
- City Plazapossession Dec 2026
- Indraprasthpossession Dec 2026
- One Lonvalapossession Dec 2026
- Paloma Azurepossession Dec 2026
- Sai Ganeshpossession Dec 2026
- Siddhivinayak Rigelpossession Dec 2026
- VTP Urban Life Phase 1possession Dec 2026
- Arunoday Classic A Wingpossession Jan 2027
- Green Meadows Phase -2 Annexpossession Feb 2027
- Hillcrestpossession Feb 2027
Location
A map search by name. Open the map (opens in a new tab)
MahaRERA record
From MahaRERA, read 17 Oct 2026Possession date
30 Oct 2021
Completion date filed with MahaRERA. At registration: 30 Apr 2019. Moved 30 months later.
The filed completion date has passed. Ask for the occupancy certificate (OC) before you book.
Ask for the possession date in writing in your agreement for sale.
Beside other Talegaon projects
Worked out by Avasetu- Completion date
- Moved 30 months later
- 29 of 104 Talegaon projects being built moved theirs 3 months or more.
From MahaRERA records read 17 Oct 2026. Dates net of MahaRERA's August 2026 order.
The record
- Registered on
- 1 Sep 2017
- MahaRERA registration
- P52100012266
- Listed or updated on MahaRERA 9 Sep 2021.
- Promoter (builder)
- S.r. Developers
- Pincode
- 410507
Check before you book
From MahaRERA- The completion date filed with MahaRERA (Oct 2021) has passed. Ask for the occupancy certificate (OC) before you pay anything more.
- The builder has moved the completion date 30 months later since registration, from Apr 2019 to Oct 2021. Ask why, and which date goes in your agreement for sale.
S.r. Developers: track record
From MahaRERA recordsS.r. Developers has 2 projects in our MahaRERA register for Pune.
- Shree Apartmentcompletion filed 31 Dec 2025
More by S.r. Developers
FAQ
What is the price of Sai Shivam?
No price for Sai Shivam is published yet. Ask through the enquiry form on this page for the current price.
What is the possession date of Sai Shivam?
The completion date filed with MahaRERA is 30 Oct 2021. At registration it was 30 Apr 2019. Ask the builder for the possession date in your agreement, in writing.
What is the MahaRERA number of Sai Shivam?
Sai Shivam is registered with MahaRERA as P52100012266.
Who is the builder of Sai Shivam?
The promoter registered with MahaRERA is S.r. Developers. Our register has 2 Pune projects by S.r. Developers.
Where is Sai Shivam?
Sai Shivam is in Mawal, Pune district (pincode 410507).
Has the completion date of Sai Shivam passed?
Yes. Ask the builder for the occupancy certificate (OC) before you book.
Sources
- Registration, promoter, pincodeFrom MahaRERA
MahaRERA listing, updated 9 Sep 2021
- Dates and homes bookedNot checked yet
Still checking
- Buildings and wingsNot checked yet
Still checking
- Location and nearbyNot checked yet
Still checking
- DescriptionNot checked yet
Still checking