Studio06, Karve Nagar
by Karvenagar Studio LLP · Karve Nagar, Haveli, Pune district · 411052
- Possession
- Sep 2027
- completion filed with MahaRERA
- Booked
- 119 of 199
What stands out
As of 13 Nov 2026, from MahaRERA and the sources below.
- This registration contains 199 homes, giving it more units than 24 of 25 ongoing projects in Karve Nagar.
- The project packs 199 units into 0.17 acres, resulting in an intense density of about 1171 homes per acre across a single 10-floor building.
- The completion date filed at initial registration was 31 May 2026, but the date currently filed with MahaRERA is 30 Sep 2027.
- 60% of homes booked: Buyers have secured 119 of the 199 homes available in this building.
Updated 22 Nov 2026
Floor plans
Location
Position checkedThe project's pin on Google Maps, checked against its MahaRERA name and pincode. Open the map (opens in a new tab)
Studio06, year by year, up close
Sharp satellite pictures taken in Nov 2022, Jan 2024, Mar 2025 and Apr 2026, centred on the project's map pin, about 580 m across at about 0.5 m a pixel.
Nov 2022 Jan 2024 Mar 2025 Apr 2026 · latest
Each picture is dated by when it was taken; the ring is 100 m around the pin. Map image is the intellectual property of Esri and is used herein under license. Copyright © 2026 Esri and its licensors (imagery: Maxar, Vantor). All rights reserved. Compare every release ↗
Work hubs
- Pune Railway Station7 km
- Baner-Balewadi High Street10.2 km
- Magarpatta City11.6 km
- Pune Airport (Lohegaon)13.5 km
Nearby
- Bus standKothrud1.4 km
- HospitalDeenanath Mangeshkar Hospital and Research Center1.7 km
- BankHDFC Bank1.7 km
- ShoppingAbhiruchi Mall & Multiplex3.1 km
- CollegeMIT World Peace University (MIT-WPU)3.2 km
Straight-line distances; the drive is longer. Places: Google Maps and © OpenStreetMap contributors.
Project facts
- The project is built on a total area of 0.17 acres.
Last checked 21 Nov 2026.
MahaRERA record
From MahaRERA, read 13 Nov 2026Possession date
30 Sep 2027
Completion date filed with MahaRERA. At registration: 31 May 2026. Moved 12 months later, 4 of them by MahaRERA's August 2026 order for most projects.
Ask for the possession date in writing in your agreement for sale.
Studio06: what changed, as we read it
Completion date filed with MahaRERA
- 31 May 2026 → 30 Sep 2027, filed by the builder; we saw it on 13 Nov 2026
Read by Avasetu from MahaRERA on each date shown. MahaRERA shows only the latest figures, so earlier ones are our own readings.
Beside other Karve Nagar projects
Worked out by Avasetu- Completion date
- Moved 12 months later
- 5 of 27 Karve Nagar projects being built moved theirs 3 months or more.
From MahaRERA records read 13 Nov 2026. Dates net of MahaRERA's August 2026 order.
The record
- Homes booked
- 119 of 199
- Towers
- 1 in this registration
- The tallest has 10 floors.
- Units
- 199
- 171 homes, 28 shops or offices.
- Registered on
- 11 Mar 2024
- MahaRERA registration
- P52100055193
- Listed or updated on MahaRERA 9 Nov 2026.
- Promoter (builder)
- Karvenagar Studio LLP
- Project type
- Others
- Pincode
- 411052
Check before you book
From MahaRERA and checked sites- The builder has moved the completion date 12 months later since registration, from May 2026 to Sep 2027 (MahaRERA's 2026 blanket extension for all projects left out). Ask why, and which date goes in your agreement for sale.
- About 1,171 homes per acre (199 homes on 0.17 acres, from two property sites that agree). Towers stand close: ask how far your tower is from the next and which flats face another tower.
- 28 shops or offices are part of the project. Ask where they open and whether their visitors use the residents' gate.
Tower by tower
1 building
Buildings
From MahaRERA| Building | Floors | Homes | Other |
|---|---|---|---|
| Studio06 | 10 | 171 | 28 |
As filed with MahaRERA (sanctioned floors).
What the builder's and property sites say
Gathered and checked- Land
- 0.17 acres
Last checked 21 Nov 2026. MahaRERA counts where they differ.
Karvenagar Studio LLP: track record
From MahaRERA recordsKarvenagar Studio LLP has 1 project in our MahaRERA register for Pune.
Planning to buy here?
Ask about prices, floor plans, offers or a site visit.
Other projects in Karve Nagar
FAQ
What is the price of Studio06?
No price for Studio06 is published yet. Ask through the enquiry form on this page for the current price.
What is the possession date of Studio06?
The completion date filed with MahaRERA is 30 Sep 2027. At registration it was 31 May 2026. MahaRERA added 4 months to most projects' dates in August 2026 (Order 66/2026). Ask the builder for the possession date in your agreement, in writing.
What is the MahaRERA number of Studio06?
Studio06 is registered with MahaRERA as P52100055193.
How many towers and floors does Studio06 have?
MahaRERA lists 1 building, the tallest with 10 floors.
How many flats are there in Studio06?
MahaRERA lists 199 units (171 residential, 28 other).
How many homes in Studio06 are booked?
119 of 199 homes were booked as per MahaRERA on 13 Nov 2026.
Who is the builder of Studio06?
The promoter registered with MahaRERA is Karvenagar Studio LLP.
Where is Studio06?
Studio06 is in 411052, Haveli, Pune district (pincode 411052).
Which hospital is nearest to Studio06?
Deenanath Mangeshkar Hospital and Research Center, about 1.7 km away in a straight line from the map position; the drive is longer.
How far is Studio06 from Pune Airport?
About 13.5 km in a straight line from the map position; the drive is longer.
How far is Studio06 from Baner-Balewadi High Street?
About 10.2 km in a straight line from the map position; the drive is longer. It is the nearest of Pune's main work hubs to Studio06.
Sources
- Registration, promoter, pincodeFrom MahaRERA
MahaRERA listing, updated 9 Nov 2026
- Dates and homes bookedFrom MahaRERA
Checked 21 Nov 2026
- Buildings and wingsFrom MahaRERA
Checked 19 Nov 2026
- Location and nearbyGathered and checked
Checked 21 Nov 2026
- DescriptionGathered and checked
Checked 21 Nov 2026
- Project facts and amenitiesGathered and checked
The builder's site and property sites, which can be wrong: where they differ from MahaRERA, MahaRERA counts (21 Nov 2026)