Up to 3 projects side by side. Dates and bookings from MahaRERA's public record; prices as the builder or two property sites publish them. A dash means we do not have that fact yet.

FactIndraprasthaWagholiMahaRERA P52100077450Sai HemantKharadiMahaRERA PR1260002600119Purple Park Eden Phase IKharadiMahaRERA PR1260002502005
Starting priceFrom ₹66.5 Lread Nov 2026From ₹45.7 Lread Oct 2026From ₹1.99 Crread Nov 2026
All-in cost, lowest priceAbout ₹74.78 LGST, stamp duty, registration; before the builder's chargesAbout ₹51.48 LGST, stamp duty, registration; before the builder's chargesAbout ₹2.23 CrGST, stamp duty, registration; before the builder's charges
Per sq ft, as published—Wagholi middle ₹8,125 (12 projects)—Kharadi middle ₹12,294 (9 projects)—Kharadi middle ₹12,294 (9 projects)
Possession filedApr 2029filed with MahaRERAApr 2028filed with MahaRERAFeb 2031filed with MahaRERA
Date moved by the builderNot moved by the builderMahaRERA's 2026 order added 4 monthsNot moved by the builderMahaRERA's 2026 order added 4 monthsNot moved by the builderMahaRERA's 2026 order added 4 months
Homes booked43% booked33 of 77 homes0% booked0 of 24 homes11% booked27 of 249 homes
Homes left44 homesnot yet booked on MahaRERA24 homesnot yet booked on MahaRERA222 homesnot yet booked on MahaRERA
Towers2 towers, up to 9 floors1 tower, up to 7 floors2 towers, up to 32 floors
StageMid stageby dates, registration to filed completionEarly stageby dates, registration to filed completionEarly stageby dates, registration to filed completion
Builder's date record2 projects on MahaRERAtoo few with both dates to judge0 of 5 moved their dateSai Associates, 5 projects1 project on MahaRERAtoo few with both dates to judge
Pick

The all-in cost adds GST, stamp duty (7%) and registration to the lowest published price; parking, club house and other charges come from the builder's cost sheet. A per sq ft figure is the site's own: some quote carpet, some saleable area.