Aarav Elite Row Villas, Wagholi
by Aarav Constructions · Wagholi, Pune · 412207
- Possession
- Apr 2028
- completion filed with MahaRERA
- Booked
- 1 of 15
What stands out
As of 7 Nov 2026, from MahaRERA and the sources below.
- This registration has more homes than 7 of 79 projects still being built in Wagholi. It plans 15 homes across 2 buildings of up to 4 floors.
- Buyers have booked 1 of 15 homes, which is 7%. For comparison, similar projects are at about 0% in Wagholi.
- The original completion date was 31 Dec 2027. A MahaRERA order added 4 months to the schedule, taking the completion date to 30 Apr 2028.
Updated 21 Nov 2026
Price
No price for Aarav Elite Row Villas is published yet.
What new homes in Wagholi usually ask
- 1 BHK about ₹25 – 40 L (6 projects)
- 2 BHK about ₹50 – 75 L (33 projects)
- 3 BHK about ₹90 L – ₹1.3 Cr (21 projects)
- 4 BHK about ₹1.2 – 2.6 Cr (6 projects)
Our own guide: the middle half of the starting prices we have read for projects being sold in Wagholi, rounded. Use it to judge an offer, not as a price.
Wagholi average ₹8,168/sq ft across 13 projectsThe middle asking price per sq ft of other projects in Wagholi.
Get the exact price for your home
The Avasetu team gets you the current price sheet for the size you want, with parking and all other charges.
Floor plans
Location
A map search by name. Open the map (opens in a new tab)
Project facts
- The project consists of two buildings or towers.
Last checked 21 Nov 2026.
MahaRERA record
From MahaRERA, read 7 Nov 2026Possession date
30 Apr 2028
The completion date filed with MahaRERA is 30 Apr 2028; MahaRERA's August 2026 order added 4 months to it (the builder has not moved it). At registration: 31 Dec 2027.
Beside other Wagholi projects
Worked out by Avasetu- Homes booked
- 7%
- The middle of 37 Wagholi projects registered within a year of it: 0%.
- Completion date
- Not moved by the builder
- 26 of 95 Wagholi projects being built moved theirs 3 months or more.
From MahaRERA records read 7 Nov 2026. Homes booked are the builders' own quarterly counts. Dates net of MahaRERA's August 2026 order.
The record
- Homes booked
- 1 of 15
- Towers
- 2 in this registration
- The tallest has 4 floors.
- Registered on
- 17 Feb 2026
- MahaRERA registration
- PR1260002502385
- Listed or updated on MahaRERA 17 Feb 2026.
- Promoter (builder)
- Aarav Constructions
- Project type
- Residential / Group Housing
- Pincode
- 412207
Tower by tower
2 buildings
Buildings
From MahaRERA| Building | Floors | Homes | Other |
|---|---|---|---|
| AARAV ELITE ROW VILLAS, BUILDING A | 4 | 5 | 0 |
| AARAV ELITE ROW VILLAS, BUILDING B | 4 | 10 | 0 |
As filed with MahaRERA (sanctioned floors).
Aarav Constructions: track record
From MahaRERA recordsAarav Constructions has 1 project in our MahaRERA register for Pune.
Planning to buy here?
Ask about prices, floor plans, offers or a site visit.
Other projects in Wagholi
FAQ
What is the price of Aarav Elite Row Villas?
No price for Aarav Elite Row Villas is published yet. Ask through the enquiry form on this page for the current price.
What is the possession date of Aarav Elite Row Villas?
The completion date filed with MahaRERA is 30 Apr 2028; MahaRERA's August 2026 order added 4 months to it (the builder has not moved it).
What is the MahaRERA number of Aarav Elite Row Villas?
Aarav Elite Row Villas is registered with MahaRERA as PR1260002502385.
How many towers and floors does Aarav Elite Row Villas have?
MahaRERA lists 2 buildings, the tallest with 4 floors.
How many flats are there in Aarav Elite Row Villas?
MahaRERA lists 15 units.
How many homes in Aarav Elite Row Villas are booked?
1 of 15 homes were booked as per MahaRERA on 7 Nov 2026.
Who is the builder of Aarav Elite Row Villas?
The promoter registered with MahaRERA is Aarav Constructions.
Where is Aarav Elite Row Villas?
Aarav Elite Row Villas is in Wagholi, Pune (pincode 412207).
Sources
- Registration, promoter, pincodeFrom MahaRERA
MahaRERA listing, updated 17 Feb 2026
- Dates and homes bookedFrom MahaRERA
Checked 21 Nov 2026
- Buildings and wingsFrom MahaRERA
Checked 7 Nov 2026
- Location and nearbyGathered and checked
Checked 21 Nov 2026
- DescriptionGathered and checked
Checked 21 Nov 2026
- Project facts and amenitiesGathered and checked
The builder's site and property sites, which can be wrong: where they differ from MahaRERA, MahaRERA counts (21 Nov 2026)
Get the price sheet and floor plans for AARAV ELITE ROW VILLAS
The Avasetu team calls or WhatsApps you back; we never share your number without your OK.