New projects and flats in Chakan, Pune
Updated 23 Nov 2026
- Projects being built
- 77
- Homes booked
- 52%
- 2 BHK from
- ₹22.24 L
- Past their completion date
- 13
As of 24 Nov 2026, MahaRERA lists 77 housing projects in Chakan, Pune being built or recently finished (2 sold out). 4,531 of their 8,791 homes are booked. The earliest filed completion date is Ghanwat Square (Nov 2025). 2 BHK flats start from ₹22.24 L (Ivory Tathastu).
Every residential project MahaRERA lists in Chakan, the flats and apartments on sale here and the ones already handed over: 77 being built or recently finished, and 81 older ones. Before you buy a property in Chakan, each page shows the completion date the builder filed with MahaRERA, whether it has moved, and how many homes are booked, with the date we read the record.
Top projects you can still buy
Most homes booked first, with 10 or more open
- Sara Abhiruchi Tower A
Rank 1Picture 1 / 5Under construction41 of 276 homes open · 85% booked · possession Jul 2033
- Dwarka Project 5 2 BHK ₹38 L to ₹43.57 L
Rank 2Possession soonThe project's position on the map34 of 143 homes open · possession Oct 2027
- Rank 3Under constructionThe project's position on the mapTathastu
154 of 224 homes open · 31% booked · possession Apr 2031
- Rank 4Possession soonThe project's position on the mapSiddhivinayak Residency
132 of 212 homes open · 38% booked · possession Jul 2027
- See all 26 →
Flat prices in Chakan
Starting prices of new flats in Chakan by size, from the builder's own site or two property sites that agree, read in the last 45 days. Parking, stamp duty, registration and GST are usually extra.
| Size | Starting price | Lowest at | Projects |
|---|---|---|---|
| 2 BHK | ₹22.24 L to ₹38 L | Ivory Tathastu | 2 with 2 BHK flats |
What new homes in Chakan usually ask
- 2 BHK about ₹15 – 40 L (4 projects)
Our own guide: the middle half of the starting prices we have read for projects being sold in Chakan, rounded. Use it to judge an offer, not as a price.
Chakan: the good and what to check
What's going for it
- Buyers are booking here: 52% of the homes in projects being built are already booked.
- 19 projects have possession filed within the next 12 months.
Check before you book
- 29 of 77 projects have moved their possession date by 3 months or more, usually by 51 months (not counting MahaRERA's 2026 extension for all projects). See the date history on a project's page before you book.
- 13 projects are past the completion date filed with MahaRERA: ask for the occupancy certificate (OC) before you pay.
- Starting prices are for the smallest home of each size and usually leave out parking, stamp duty, registration and GST: ask for the full cost sheet.
Counted from MahaRERA records of the projects on this page.
Most active projects in Chakan
- Sara Abhiruchi Tower A 114 homes booked (41% of its 276 homes) between 2026-10-13 and 2026-11-12 (MahaRERA)
- Pradnyesh Prime 9 homes booked (7% of its 125 homes) between 2026-10-13 and 2026-11-12 (MahaRERA)
- Dwarka Project 5 28 homes booked (20% of its 143 homes) between 2026-10-14 and 2026-11-13 (MahaRERA)
- Menlo Bougainvillea 6 homes booked (21% of its 28 homes) between 2026-10-14 and 2026-11-13 (MahaRERA)
- Tathastu 21 homes booked (9% of its 224 homes) between 2026-10-14 and 2026-11-13 (MahaRERA)
- Dwarka Business Square 9 homes booked (5% of its 190 homes) between 2026-10-13 and 2026-11-07 (MahaRERA)
- Siddhivinayak Residency 13 homes booked (6% of its 212 homes) between 2026-10-15 and 2026-11-14 (MahaRERA)
- Opal Field completion filed for 31 Dec 2034 (MahaRERA)
Being built (75)
New launch (6)
- Gurukrupa Heights MahaRERA onlyby Shivam Developers Private Limited · possession Apr 2028 · 0/7 booked
- Opal Field Checkedby P And N Mutke Builders And Developers · possession Dec 2034 · 0/124 booked
- Pradnyesh Shree Checkedby Ssh Buildcon LLP · possession Dec 2028 · 0/58 booked
- Raj Kunj MahaRERA onlypossession Apr 2030 · 0/46 booked
- Sara Prima MahaRERA onlyby Jagrutsara Structures LLP · possession Dec 2033 · 0/170 booked
- Vighnaharta Checked 3/4by Sharayu Developers · possession Apr 2028 · 0/11 booked
Early stage (15)
- Aetheria - A wing MahaRERA onlyby Shree Sai Associates · possession Dec 2029 · 0/56 booked
- Empire Business Hub Chakan MahaRERA onlyby Gajraj Developers · possession Jul 2029 · 7/229 booked
- Gold Nest MahaRERA onlyby Sudarshan Properties · possession Apr 2043
- Gulmohar City MahaRERA onlyby Gurudatta Builders And Developers Chakan · possession Apr 2031
- Harmony MahaRERA onlyby M/s Padma Constructions · possession Oct 2028 · 0/28 booked
- Imperial Plaza MahaRERA onlyby Keystone Group · possession Oct 2029 · 2/46 booked
- Menlo Bougainvillea Checkedby Sai Asha Infra-Edge City · possession Apr 2030 · 13/28 booked
- Pradnyesh Prime Checkedpossession Apr 2030 · 37/125 booked · from ₹25.96 L
- Sara Abhiruchi Tower A Checkedby Sara Landmarks India LLP · possession Jul 2033 · 235/276 booked
- Sara Ekadant MahaRERA onlypossession Apr 2029 · 3/30 booked
- Sara Kasturi Building D and E MahaRERA onlyby Jagrutsara Structures LLP · possession Apr 2031
- Sara Nilaay Checkedby Jagrutsara Structures LLP · possession Apr 2031 · 407/430 booked
- Sara Nilaay C & D Checked 3/4by Jagrutsara Structures LLP · possession Jul 2031 · 0/292 booked
- Skyline MahaRERA onlyby Roofone Jk Kad Buildcon LLP · possession Jul 2029
- Tathastu Checkedby Sai Asha Infra-Edge City · possession Apr 2031 · 70/224 booked · from ₹24.5 L
Mid stage (12)
- Bajrang Complex Wing A MahaRERA onlypossession Oct 2027 · 2/14 booked
- Chakreshwar Vihar Checked 3/4possession Apr 2029 · 2/141 booked
- Dwarka Business Square Checkedby Naiknavare Housing Developments Pvt. Ltd. · possession Jul 2028 · 82/190 booked
- Dwarka Project 5 Checkedby Naiknavare Housing Developments Pvt Ltd · possession Oct 2027 · 109/143 booked · from ₹38 L
- Dwarkadhish Park Building D MahaRERA onlyby Sai Datta Enterprises · possession Apr 2029 · 8/40 booked
- Ghanwat Icon MahaRERA onlyby Shivam Developers Pvt Ltd · possession Dec 2027 · 1/39 booked
- Phase I - Buildings A, A1, P and S,T,U Combined wing Checked 3/4by Shree Sai Associates · possession Apr 2031 · 113/245 booked
- Siddhivinayak Dream Homes C,D Wing MahaRERA onlypossession Aug 2028 · 30/84 booked
- Swami Samarth Buildcon - Kalpavruksh Heights MahaRERA onlypossession Apr 2028 · 34/56 booked
- Tathastu Homes MahaRERA onlyby Shri Bhagyalaxmi Infracon · possession Oct 2029 · 36/80 booked
- The Urbana-N1 and N2 MahaRERA onlyby Intercontinental Infrastructure Limited · possession Apr 2029
- The Urbana-N5A and N5B Checkedby Intercontinental Infrastructure Limited · possession Apr 2029 · 0/140 booked
Near completion (25)
- Aapla Ghar Chakan Talegaon Phase I Checked 3/4possession Apr 2028 · 259/272 booked
- Aapla Ghar Moshi Annex Phase I Checkedby Maple Shelters Pvt. Ltd. · possession Apr 2028 · 280/296 booked
- Amrutvel Checkedby Shivmudra Enterprises · possession Mar 2027 · 58/125 booked
- Chakan High Street MahaRERA onlyby Chakan Business Hub LLP · possession Apr 2027 · 141/191 booked
- Chakan Nagarparishad Pmay Ahp MahaRERA onlypossession Apr 2027
- Creative Ventures Chakan MahaRERA onlypossession Apr 2028
- Crown World MahaRERA onlyby Manjare And Mutake Associates · possession Dec 2026
- Dnyanada City and Dnyanada Commercial Center MahaRERA onlypossession Apr 2028
- Dwarka PROJECT2 Checked 3/4possession Dec 2027 · 143/192 booked
- Ivory Tathastu Checkedby Ivory Lifespace LLP · possession Apr 2027 · 123/127 booked · from ₹22.24 L
- Kumar Paksha-B Checked 2/4by Kumar Properties Lifespaces Private Limited · possession Oct 2027 · 62/262 booked
- Laxmi Vishwa MahaRERA onlypossession Dec 2026
- Mungase Towers Checkedpossession Apr 2027 · 76/144 booked
- Nakoda Height MahaRERA onlyby Ambika Developers · possession Dec 2028 · 3/42 booked
- Raj Apoorvam Checked 3/4possession Apr 2028 · 28/131 booked
- Richmond MahaRERA onlyby Coral Shubh Builders · possession Feb 2027 · 78/80 booked
- Sara Business Hub MahaRERA onlyby Sara Towers Pvt Ltd · possession Jul 2027 · 113/114 booked
- Sara City C4 MahaRERA onlyby Jagrutsara Structures LLP · possession Apr 2028
- Sarangi Paradise MahaRERA onlypossession Jun 2027 · 39/84 booked
- Shree Samarth Shrushti MahaRERA onlyby Jagdamba Developers · possession Jan 2027 · 16/70 booked
- Shri Sai Park MahaRERA onlypossession Apr 2028 · 34/63 booked
- Siddhivinayak Residency Checkedby Kate Builders · possession Jul 2027 · 80/212 booked · from ₹20.99 L
- Urban County A & B Wing MahaRERA onlyby Padmalaya Properties · possession Apr 2027
- Urja Cornerstone Building 2 MahaRERA onlypossession Dec 2026 · 34/98 booked
- Vallabh Heights MahaRERA onlyby G R Developers · possession Jan 2027 · 1/27 booked
Completion date passed (13)
- Avasa Parkland MahaRERA onlyby Naiknavare Housing Development Pvt.ltd · possession Dec 2025 · 34 homes
- Avasa Woodland MahaRERA onlyby Naiknavare Housing Development Pvt.ltd · possession Dec 2025 · 56 homes
- AVONVISTAPROJECT4 MahaRERA onlypossession Dec 2025 · 245/246 booked
- Casa Feliz MahaRERA onlyby Aujaswi Associates · possession Dec 2025 · 23/48 booked
- City Plaza MahaRERA onlyby Bharat Builders and Developers · possession Jun 2026
- Dwarka PROJECT3 MahaRERA onlypossession Jun 2026 · 188/480 booked
- Ghanwat Square MahaRERA onlyby Shivam Developers Pvt. Ltd. · possession Nov 2025
- Gulmohar Apartment MahaRERA onlyby Sai Builders And Developers · possession Jun 2026
- Krushna Kunj MahaRERA onlyby MNM Developers · possession Dec 2025 · 16 homes
- Pearl Unicon MahaRERA onlyby Shree Vijayalaxmi Developers · possession Dec 2025 · 7/22 booked
- Sai Plaza MahaRERA onlyby Sainath Enterprises · possession Dec 2025
- Sara Abhiman MahaRERA onlyby Jagrutsara Structures LLP · possession Mar 2026 · 67/68 booked
- Sara Swapnavihar MahaRERA onlyby Jagrutsara Structures LLP · possession Oct 2026
Dates not read yet (4)
- Pradnyesh Shriniwas MahaRERA onlyby Jj Mauli Developers LLP · possession Apr 2028 · 32/81 booked
- Sara City Plot E 1 Checked 3/4by Jagrutsara Structures LLP · possession Dec 2029 · 145/859 booked
- Sara Kasturi MahaRERA onlyby Jagrutsara Structures LLP · possession Mar 2027 · 361/388 booked
- The Urbana MahaRERA onlyby Intercontinental Infrastructure Limited · possession Mar 2026 · 185/198 booked
Stage by dates: how much of the time between MahaRERA registration and the completion date the builder filed has gone. Not a site check: MahaRERA’s construction progress reports are behind its login.
Sold out on MahaRERA (2)
- Phase IV - K1 and L1 Buildings MahaRERA onlyby Shree Sai Associates · possession Dec 2025 · 176/176 booked
- Sara Swapnoday MahaRERA onlyby Jagrutsara Structures LLP · possession Jun 2026 · 343/343 booked
Finished more than a year ago (81)
- Aabhas Phase I MahaRERA onlypossession Feb 2021
- Aabhas Phase II MahaRERA onlypossession Oct 2024
- Aapla Ghar Chakan Phase I Amentiy A Bldg MahaRERA onlypossession Dec 2022 · 24/30 booked
- Aapla Ghar Chakan Phase II MahaRERA onlypossession Dec 2022
- Aapla Ghar Chakan Phase II Amenity Bldg A MahaRERA onlypossession Dec 2022
- Abc Palladium MahaRERA onlyby Krish Realtors Private Limited · possession Sep 2023
- Amrutvel MahaRERA onlyby R K Developers · possession May 2025
- Anand Residency MahaRERA onlyby Medankar Shevkari Associates · possession Dec 2018
- Atharva Patson Phinix PH II MahaRERA onlyby M/S Samrat Atharva Patson Builders And Developers · possession Jul 2023
- Avasa Groveland MahaRERA onlyby Naiknavare Housing Developments Pvt Ltd · possession Dec 2024 · 37 homes
- Avasagrassland MahaRERA onlyby Naiknavare Housing Developments Pvt. Ltd. · possession Dec 2024 · 76 homes
- Avon Vista Project -1 MahaRERA onlyby Naiknavare Profile Constructions Pvt Ltd · possession Jun 2022
- Avon Vista Project 2 MahaRERA onlypossession Jun 2022
- Avon Vista Project 3 MahaRERA onlyby Naiknavare Profile Constructions Pvt Ltd · possession Jun 2023
- Balaji Paradise MahaRERA onlypossession Mar 2023
- Capital City MahaRERA onlyby GDS Buildcon Private Limited · possession Dec 2018
- Chakan Annex MahaRERA onlyby Sangam Realty · possession Jun 2023 · 91/124 booked
- Construction of 648 Nos Ews TS, 620 Lig TS Under PH2 at Mahalunge Tal Khed Dist Pune MahaRERA onlyby Pune Housing & Area Development Board · possession Dec 2020
- Crown Field Wing B MahaRERA onlyby Manjare And Mutke Associates · possession Dec 2024
- Dnyanai Residency MahaRERA onlypossession Dec 2020
- Dwarka Project 1 MahaRERA onlypossession Dec 2018
- Dwarka Project 4 MahaRERA onlypossession Dec 2019
- Ekaakshara Heights MahaRERA onlyby Shiv Construction And Developers · possession Sep 2020
- Excel Celestia Residency MahaRERA onlyby Excel Housing · possession Dec 2023 · 40/44 booked
- Gulmohar Park MahaRERA onlyby G G Builders And Developers · possession Dec 2021
- Kalp Homes MahaRERA onlyby Dwarkamai Enterprises · possession Dec 2018
- Kalp Residency C Wing MahaRERA onlypossession Dec 2019
- Kalp Residency D Wing MahaRERA onlypossession Dec 2023
- Kalpataru MahaRERA onlypossession Dec 2020
- Kohinoor Blisspark MahaRERA onlyby Kohinoor Properties · possession Dec 2018
- Kulswamini Kasturi MahaRERA onlypossession Sep 2018
- Kushal Swarnali C1 MahaRERA onlyby Kushal Adiraj Associates · possession Dec 2021
- Kushal Swarnali C4 MahaRERA onlyby Kushal Adiraj Associates · possession Jun 2022
- Mantra Magic MahaRERA onlyby Mantra Island Homes Chimbli Private Limited · possession Nov 2018
- Mantra Magic II MahaRERA onlyby Mantra Infrahome LLP · possession Jul 2022
- Mantra Residency MahaRERA onlyby Mantra Residencies LLP · possession Dec 2018
- Mohan Petals MahaRERA onlypossession Apr 2021
- Narayan Octave MahaRERA onlypossession Dec 2018
- Narayan Octave Commercial MahaRERA onlypossession Dec 2019
- Nisarg MahaRERA onlyby Kulswamini Associates Promotoers And Builders · possession Dec 2022
- Phase II - C1, D1 and E1 Buildings MahaRERA onlyby Shree Sai Associates · possession Dec 2019
- Pradnyesh Residency MahaRERA onlyby M\S Pradnyesh Builders And Developers · possession Dec 2022
- Prasanna I Square MahaRERA onlyby Prasanna Developers · possession Sep 2021
- Rhythm Park MahaRERA onlypossession Jun 2019
- Roshan One Wing B MahaRERA onlypossession Aug 2018
- Roshan One Wing C MahaRERA onlypossession Mar 2019
- Saidatta Paradise MahaRERA onlyby Sai Datta Enterprises · possession May 2019 · 24/56 booked
- Sanvi Majesty A-D-C MahaRERA onlyby Milestone Developers · possession Oct 2020
- Sara Abhiman Plots MahaRERA onlyby Jagrutsara Structures LLP · possession Mar 2023 · 8 homes
- Sara Business Center MahaRERA onlyby Jagrutsara Structures LLP · possession Dec 2022
- Sara City C10 MahaRERA onlyby Jagrutsara Structures LLP · possession Mar 2024
- Sara City C11 MahaRERA onlyby Jagrutsara Structures LLP · possession Mar 2024
- Sara City C5 MahaRERA onlyby Jagrutsara Structures LLP · possession Dec 2023
- Sara City C8 MahaRERA onlyby Jagrutsara Structures LLP · possession Mar 2024
- Sara City C9 MahaRERA onlyby Jagrutsara Structures LLP · possession Mar 2024
- Sara Sanskruti MahaRERA onlyby Jagrutsara Structures LLP · possession Sep 2022
- Shivam Greencourt MahaRERA onlyby Shivam Developers Pvt. Ltd. · possession Oct 2021
- Shivdeep Associates MahaRERA onlyby Shivdeep Associates · possession Jan 2018
- Shivshakti MahaRERA onlypossession Dec 2023
- shree hari Residency MahaRERA onlyby Archie Nova Associates · possession Dec 2024
- Shreeram Tradecon MahaRERA onlypossession Oct 2025
- Shreeram Tradecon MahaRERA onlypossession Dec 2018
- Shriram Reality MahaRERA onlypossession Sep 2020
- Siddhi Homes MahaRERA onlyby Shree Ganesh Developers · possession May 2022
- Siddhivinayak Dream Homes MahaRERA onlypossession Dec 2020
- Signature 28 MahaRERA onlyby Jagrutsara Structures LLP · possession Dec 2020
- Solitaire Park MahaRERA onlypossession Dec 2019 · 5/11 booked
- Spine City Residency Building C MahaRERA onlyby Spine Developers · possession Aug 2022
- Springfield MahaRERA onlyby Swami Samarth Associates · possession Dec 2018
- sudarshan heights MahaRERA onlyby sudarshan properties · possession Aug 2019
- Sunshine Residency MahaRERA onlyby Sunshine Builders · possession Jun 2022
- Surabhi Iconica MahaRERA onlypossession Dec 2023
- The Grand Central MahaRERA onlypossession Dec 2024
- Tiara Meadow Phase I MahaRERA onlyby Tiara Housing · possession Jul 2018
- Unicon Bliss MahaRERA onlyby Shree Vijayalaxmi Developers · possession Oct 2020
- Urbangram Chakan Phase III MahaRERA onlyby S2 Realty · possession Jul 2019
- Urja Cornerstone MahaRERA onlypossession Jun 2025 · 81/98 booked
- Vastu Forest Nest MahaRERA onlyby Vastushilpbuilders & Developers · possession Mar 2018
- Vastu Vintage Phase 1 MahaRERA onlyby Vastushilpbuilders & Developers · possession Mar 2018
- Xrbia Eiffel City Chakan PH1 MahaRERA onlyby Xrbia Chakan Developers Private Limited · possession Mar 2022
- Xrbia Eiffel City Chakan PH2 MahaRERA onlyby Xrbia Chakan Developers Private Limited · possession Mar 2022
Questions buyers ask about Chakan
- How many new projects are there in Chakan, Pune?
- 77 projects registered with MahaRERA are being built or recently finished in Chakan as of 24 Nov 2026, out of 176 projects MahaRERA has listed there.
- What is the price of a 2 BHK flat in Chakan?
- Among 2 projects with a published 2 BHK price, starting prices run from ₹22.24 L to ₹38 L; the lowest is Ivory Tathastu. Prices are from the builder's own site or two property sites that agree; parking, stamp duty, registration and GST are usually extra.
- Which projects in Chakan have the earliest possession?
- By the completion date the builder filed with MahaRERA: Ghanwat Square (Nov 2025), Avasa Parkland (Dec 2025), Avasa Woodland (Dec 2025). A filed date can move; each project's page shows whether it has.
- Do builders in Chakan keep their possession dates?
- 29 of the 77 projects being built in Chakan whose dates we have read have moved their MahaRERA possession date by 3 months or more, usually by 51 months, not counting MahaRERA's 2026 extension for all projects. Each project's page shows its own date history.
- Which builders have the most projects in Chakan?
- Among projects being built or recently finished: JAGRUTSARA STRUCTURES LLP (8), Intercontinental Infrastructure Limited (3), Shree Sai Associates (3).
- Where do these Chakan numbers come from?
- MahaRERA's public register, read by Avasetu; each project's page shows the date we read its record. No builder pays to be listed.
From MahaRERA's public records, read on the date shown on each project's page. A project is listed under the area of the pincode it is filed under. This is general information, not investment or legal advice.