Phase I - Buildings A, A1, P and S,T,U Combined wing, Chakan
by Shree Sai Associates · Chakan, Khed, Pune district · 410501
- Possession
- Apr 2031
- completion filed with MahaRERA
- Booked
- 113 of 245
What stands out
As of 20 Nov 2026, from MahaRERA and the sources below.
- The MahaRERA filing sets completion for 30 Apr 2031, ten years after the registration date of 30 Dec 2021.
- Only 113 of 245 homes are booked (46%), far below the Chakan median of 74% for similar projects.
- The development lists 24-hour backup electricity as an amenity.
Updated 22 Nov 2026
Our team is still collecting details on Phase I - Buildings A, A1, P and S,T,U Combined wing.
We do not have prices, the builder's pictures and floor plans yet. What you see here is what we have now: MahaRERA's record, read on the date shown. Ask us and we send you what we find first.
Price
No price for Phase I - Buildings A, A1, P and S,T,U Combined wing is published yet.
What new homes in Chakan usually ask
- 2 BHK about ₹15 – 40 L (4 projects)
Our own guide: the middle half of the starting prices we have read for projects being sold in Chakan, rounded. Use it to judge an offer, not as a price.
Ask about this project
Outside our main East Pune areas: the Avasetu team finds out what it can.
Flat sizes
- 1 BHK: 625 to 650 sq ft, saleable area
- 2 BHK: 850 sq ft, saleable area
- 3 BHK: 1,195 sq ft, saleable area
Your agreement for sale states the final carpet area.
Floor plans
Location
A map search by name. Open the map (opens in a new tab)
Amenities
- Black Granite Kitchen.
- Rain water harvesting system installed.
Last checked 22 Nov 2026.
MahaRERA record
From MahaRERA, read 20 Nov 2026Possession date
30 Apr 2031
Completion date filed with MahaRERA. At registration: 30 Dec 2021. Moved 108 months later, 4 of them by MahaRERA's August 2026 order for most projects.
Ask for the possession date in writing in your agreement for sale.
Beside other Chakan projects
Worked out by Avasetu- Homes booked
- 46%
- The middle of 9 Chakan projects registered within a year of it: 74%.
- Completion date
- Moved 108 months later
- 17 of 51 Chakan projects being built moved theirs 3 months or more.
From MahaRERA records read 20 Nov 2026. Homes booked are the builders' own quarterly counts. Dates net of MahaRERA's August 2026 order.
The record
- Homes booked
- 113 of 245
- Towers
- 4 in this registration
- The tallest has 8 floors.
- Registered on
- 24 Aug 2017
- MahaRERA registration
- P52100010202
- Listed or updated on MahaRERA 20 Aug 2026.
- Promoter (builder)
- Shree Sai Associates
- Project type
- Residential / Group Housing
- Pincode
- 410501
Check before you book
From MahaRERA- The builder has moved the completion date 108 months later since registration, from Dec 2021 to Apr 2031 (MahaRERA's 2026 blanket extension for all projects left out). Ask why, and which date goes in your agreement for sale.
- Completion is filed for Apr 2031, about 4 years away. Until then you may pay rent and loan interest (pre-EMI) together; ask for a construction-linked payment plan.
Tower by tower
4 buildings
Buildings
From MahaRERA| Building | Floors | Homes | Other |
|---|---|---|---|
| Phase I - A Building | 4 | 35 | 0 |
| Phase I - A1 Building | 8 | 28 | 0 |
| Phase I - P Building | 4 | 56 | 0 |
| Phase I - Buildings S, T and U - Combined | 8 | 126 | 0 |
As filed with MahaRERA (sanctioned floors).
Shree Sai Associates: track record
From MahaRERA recordsShree Sai Associates has 5 projects in our MahaRERA register for Pune. 2 of 5 with both dates moved the completion date 3 months or more later, by 90 months on average.
- Phase II - C1, D1 and E1 Buildingscompletion filed 31 Dec 2019
- SAI VATSALYAcompletion filed 30 Jun 2024
- Phase IV - K1 and L1 Buildingscompletion filed 31 Dec 2025, moved 72 months later
- Aetheria - A wingcompletion filed 31 Dec 2029
Planning to buy here?
Ask about prices, floor plans, offers or a site visit.
Other projects in Chakan
More by Shree Sai Associates
FAQ
What is the price of Phase I - Buildings A, A1, P and S,T,U Combined wing?
No price for Phase I - Buildings A, A1, P and S,T,U Combined wing is published yet. Ask through the enquiry form on this page for the current price.
What is the possession date of Phase I - Buildings A, A1, P and S,T,U Combined wing?
The completion date filed with MahaRERA is 30 Apr 2031. At registration it was 30 Dec 2021. MahaRERA added 4 months to most projects' dates in August 2026 (Order 66/2026). Ask the builder for the possession date in your agreement, in writing.
What is the MahaRERA number of Phase I - Buildings A, A1, P and S,T,U Combined wing?
Phase I - Buildings A, A1, P and S,T,U Combined wing is registered with MahaRERA as P52100010202.
How many towers and floors does Phase I - Buildings A, A1, P and S,T,U Combined wing have?
MahaRERA lists 4 buildings, the tallest with 8 floors.
How many flats are there in Phase I - Buildings A, A1, P and S,T,U Combined wing?
MahaRERA lists 245 units.
How many homes in Phase I - Buildings A, A1, P and S,T,U Combined wing are booked?
113 of 245 homes were booked as per MahaRERA on 20 Nov 2026.
Who is the builder of Phase I - Buildings A, A1, P and S,T,U Combined wing?
The promoter registered with MahaRERA is Shree Sai Associates. Our register has 5 Pune projects by Shree Sai Associates; 2 of 5 with both dates moved their completion date 3 months or more later.
Where is Phase I - Buildings A, A1, P and S,T,U Combined wing?
Phase I - Buildings A, A1, P and S,T,U Combined wing is in Khed, Pune district (pincode 410501).
Sources
- Registration, promoter, pincodeFrom MahaRERA
MahaRERA listing, updated 20 Aug 2026
- Dates and homes bookedFrom MahaRERA
Checked 22 Nov 2026
- Buildings and wingsFrom MahaRERA
Checked 22 Nov 2026
- Location and nearbyNot checked yet
Still checking
- DescriptionGathered and checked
Checked 22 Nov 2026
- Home sizesGathered and checked
The builder's site, or two property sites that agree
- Project facts and amenitiesGathered and checked
The builder's site and property sites, which can be wrong: where they differ from MahaRERA, MahaRERA counts (22 Nov 2026)
Get the price sheet and floor plans for Phase I - Buildings A, A1, P and S,T,U Combined wing
The Avasetu team calls or WhatsApps you back; we never share your number without your OK.