As of 24 Nov 2026, MahaRERA lists 19 housing projects in Kamshet, Pune being built or recently finished (1 sold out). 264 of their 953 homes are booked. The earliest filed completion date is Gagan Nulife (Mar 2018).
Every residential project MahaRERA lists in Kamshet, the flats and apartments on sale here and the ones already handed over: 19 being built or recently finished, and 15 older ones. Before you buy a property in Kamshet, each page shows the completion date the builder filed with MahaRERA, whether it has moved, and how many homes are booked, with the date we read the record.
Kamshet: the good and what to check
What's going for it
- Room to choose: 689 of 953 homes in projects being built are still open.
- 3 projects have possession filed within the next 12 months.
Check before you book
- 6 of 19 projects have moved their possession date by 3 months or more, usually by 73 months (not counting MahaRERA's 2026 extension for all projects). See the date history on a project's page before you book.
- 2 projects are past the completion date filed with MahaRERA: ask for the occupancy certificate (OC) before you pay.
Counted from MahaRERA records of the projects on this page.
Most active projects in Kamshet
- Monte Karla completion filed for 31 Dec 2029 (MahaRERA)
- Urban Nest completion filed for 31 Dec 2030 (MahaRERA)
- Mohar Srushti completion filed for 30 Apr 2031 (MahaRERA)
- Forisaqua completion filed for 30 Apr 2027 (MahaRERA)
- Antaaya Villas completion filed for 30 Apr 2028 (MahaRERA)
- Mount Kusur Phase 1 9 homes booked (50% of its 18 homes) between 2026-10-13 and 2026-11-13 (MahaRERA)
- Bliss Estates Phase 2 completion filed for 31 Dec 2029 (MahaRERA)
- Crystal Spring completion filed for 30 Apr 2030, moved 73 months later (MahaRERA)
Being built (18)
New launch (3)
- Bliss Estates Phase 2 Checked 2/4possession Dec 2029 · 0/4 booked
- Monte Karla Checked 3/4by Goodbrick Realty Private Limited · possession Dec 2029 · 0/144 booked
- Urban Nest Checked 3/4by GM Ventures · possession Dec 2030 · 0/50 booked
Early stage (3)
- Antaaya Villas MahaRERA onlyby Antaaya Builders LLP · possession Apr 2028 · 0/23 booked
- Mehul Bhupendra Shah and Sadhna Bhupendra Shah MahaRERA onlypossession Dec 2032 · 9/35 booked
- Mount Kusur Phase 1 MahaRERA onlyby Clarks Leisure Private Limited · possession Nov 2030 · 14/18 booked
Mid stage (5)
- Crystal Spring MahaRERA onlypossession Apr 2030 · 0/1 booked
- Divine Wonders MahaRERA onlyby M/S Zircon Properties · possession Apr 2029 · 0/35 booked
- Mohar Srushti MahaRERA onlyby Mohar Projects LLP · possession Apr 2031 · 5/54 booked
- Palaash Valley MahaRERA onlypossession Apr 2028 · 0/23 booked
- Vighnesh Vikas Checked 3/4possession Dec 2031 · 6/204 booked
Near completion (4)
- Aranya MahaRERA onlyby Karmaa Builders · possession Apr 2027 · 28/60 booked
- Forisaqua MahaRERA onlypossession Apr 2027 · 1/53 booked
- Pearl Realty MahaRERA onlypossession Apr 2029 · 3/10 booked
- Stellar 8 MahaRERA onlyby Iraah Lifespaces LLP · possession Apr 2027 · 5/8 booked
Completion date passed (2)
- Green Castle MahaRERA onlyby Apurva Developers · possession Jul 2026 · 41/50 booked
- Woodrock Estate MahaRERA onlypossession Jan 2026
Dates not read yet (1)
- Gagan Nulife Checkedpossession Mar 2018 · 100/129 booked
Stage by dates: how much of the time between MahaRERA registration and the completion date the builder filed has gone. Not a site check: MahaRERA’s construction progress reports are behind its login.
Sold out on MahaRERA (1)
- Peninsula Centre Commercial Building Shopping Complex MahaRERA onlyby Peninsula Land Limited · possession Jul 2026 · 52/52 booked
Finished more than a year ago (15)
- 7VILLA MahaRERA onlypossession Jul 2024
- Aquagem MahaRERA onlyby Namrata Realty · possession Jun 2025 · 78/266 booked
- Blue Bells Park MahaRERA onlypossession Dec 2024 · 5 homes
- Eka Vally MahaRERA onlypossession Dec 2024
- Goodwill Abode MahaRERA onlypossession Dec 2024
- Lonavalas Finest Phase 1 MahaRERA onlypossession Dec 2022 · 6/20 booked
- Misty Winds 1 MahaRERA onlyby Planet I Developers · possession Sep 2022 · 21/21 booked
- Misty Winds 2 MahaRERA onlyby Planet I Developers · possession Sep 2023 · 71/128 booked
- Mont Vert Cresta MahaRERA onlyby Mont Vert Constructions · possession Dec 2019
- Pristine Villa Phase III MahaRERA onlyby Atharv Developers · possession Dec 2021
- Pristine Villas MahaRERA onlyby Atharv Developers · possession Sep 2018
- Ramana Eka Valley MahaRERA onlypossession Dec 2024
- Regency Tower MahaRERA onlyby M/S. Riddhisiddhi Developers · possession Sep 2023
- Saisindhu Avenue MahaRERA onlypossession Dec 2018
- Weekender Country Songs MahaRERA onlyby Namrata Realty · possession Dec 2021 · 69 homes
Questions buyers ask about Kamshet
- How many new projects are there in Kamshet, Pune?
- 19 projects registered with MahaRERA are being built or recently finished in Kamshet as of 24 Nov 2026, out of 36 projects MahaRERA has listed there.
- Which projects in Kamshet have the earliest possession?
- By the completion date the builder filed with MahaRERA: Gagan Nulife (Mar 2018), Woodrock Estate (Jan 2026), Green Castle (Jul 2026). A filed date can move; each project's page shows whether it has.
- Do builders in Kamshet keep their possession dates?
- 6 of the 19 projects being built in Kamshet whose dates we have read have moved their MahaRERA possession date by 3 months or more, usually by 73 months, not counting MahaRERA's 2026 extension for all projects. Each project's page shows its own date history.
- Where do these Kamshet numbers come from?
- MahaRERA's public register, read by Avasetu; each project's page shows the date we read its record. No builder pays to be listed.
From MahaRERA's public records, read on the date shown on each project's page. A project is listed under the area of the pincode it is filed under. This is general information, not investment or legal advice.