Misty Winds 2, Kamshet
by Planet I Developers · Kamshet, Mawal, Pune district · 410405
- Possession
- Sep 2023
- completion filed with MahaRERA
- Booked
- 71 of 128
As of 14 Oct 2026, Misty Winds 2 by Planet I Developers in Kamshet, Pune district is registered with MahaRERA as P52100018819. The completion date filed with MahaRERA is 30 Sep 2023, moved from 30 Sep 2022 at registration. MahaRERA shows 71 of 128 homes booked. The filed completion date has passed: ask for the occupancy certificate (OC).
Updated 14 Oct 2026
Still being built in Kamshet
Misty Winds 2 is finished (completion filed for Sep 2023), so we do not take enquiries for it. These projects nearby still have homes to book, the soonest possession first.
- Aranyapossession Apr 2027
- Forisaquapossession Apr 2027
- Stellar 8possession Apr 2027
- Gagan Nulifepossession Jun 2027
- Antaaya Villaspossession Apr 2028
- Palaash Valleypossession Apr 2028
- Divine Wonderspossession Apr 2029
- Pearl Realtypossession Apr 2029
- Bliss Estates Phase 2possession Dec 2029
- Monte Karlapossession Dec 2029
Location
A map search by name. Open the map (opens in a new tab)
MahaRERA record
From MahaRERA, read 14 Oct 2026Possession date
30 Sep 2023
Completion date filed with MahaRERA. At registration: 30 Sep 2022. Moved 12 months later.
The filed completion date has passed. Ask for the occupancy certificate (OC) before you book.
Ask for the possession date in writing in your agreement for sale.
Beside other Kamshet projects
Worked out by Avasetu- Completion date
- Moved 12 months later
- 4 of 16 Kamshet projects being built moved theirs 3 months or more.
From MahaRERA records read 14 Oct 2026. Dates net of MahaRERA's August 2026 order.
The record
- Homes booked
- 71 of 128
- Registered on
- 6 Dec 2018
- MahaRERA registration
- P52100018819
- Listed or updated on MahaRERA 19 Jan 2024.
- Promoter (builder)
- Planet I Developers
- Pincode
- 410405
Check before you book
From MahaRERA- The completion date filed with MahaRERA (Sep 2023) has passed. Ask for the occupancy certificate (OC) before you pay anything more.
- The builder has moved the completion date 12 months later since registration, from Sep 2022 to Sep 2023. Ask why, and which date goes in your agreement for sale.
Planet I Developers: track record
From MahaRERA recordsPlanet I Developers has 2 projects in our MahaRERA register for Pune.
- Misty Winds 1completion filed 30 Sep 2022
More by Planet I Developers
FAQ
What is the price of Misty Winds 2?
No price for Misty Winds 2 is published yet. Ask through the enquiry form on this page for the current price.
What is the possession date of Misty Winds 2?
The completion date filed with MahaRERA is 30 Sep 2023. At registration it was 30 Sep 2022. Ask the builder for the possession date in your agreement, in writing.
What is the MahaRERA number of Misty Winds 2?
Misty Winds 2 is registered with MahaRERA as P52100018819.
How many flats are there in Misty Winds 2?
MahaRERA lists 128 units.
How many homes in Misty Winds 2 are booked?
71 of 128 homes were booked as per MahaRERA on 14 Oct 2026.
Who is the builder of Misty Winds 2?
The promoter registered with MahaRERA is Planet I Developers. Our register has 2 Pune projects by Planet I Developers.
Where is Misty Winds 2?
Misty Winds 2 is in Mawal, Pune district (pincode 410405).
Has the completion date of Misty Winds 2 passed?
Yes. Ask the builder for the occupancy certificate (OC) before you book.
Sources
- Registration, promoter, pincodeFrom MahaRERA
MahaRERA listing, updated 19 Jan 2024
- Dates and homes bookedNot checked yet
Still checking
- Buildings and wingsNot checked yet
Still checking
- Location and nearbyNot checked yet
Still checking
- DescriptionNot checked yet
Still checking