Ready to move projects in Lohegaon, Pune

Updated 28 Nov 2026 · from MahaRERA's records

As of 29 Nov 2026, 8 projects in Lohegaon have passed the completion date filed with MahaRERA in the last three years and still have 10 or more homes not booked, the newest Shreeram Shivalay East (30 Oct 2026). Ask the builder for the occupancy certificate (OC) before you book.

8 projects

  1. Rank 1Due Oct 2026 · ask for OCThe project's position on the map
    Shreeram Shivalay East

    completion filed for 30 Oct 2026, now passed, 93 of 160 homes not booked

    Registered
    Dec 2022
    Possession filed
    Oct 2026moved from Jun 2025
    Homes
    160
    Booked
    67 (42%)

    MahaRERA P52100048271

  2. Rank 2Due Oct 2026 · ask for OCThe project's position on the map
    Swami Residency

    completion filed for 30 Oct 2026, now passed, 10 of 49 homes not booked

    Registered
    Feb 2021
    Possession filed
    Oct 2026moved from Dec 2024
    Homes
    49
    Booked
    39 (80%)

    MahaRERA P52100028342

  3. Rank 3Picture 1 / 3Due Jul 2026 · ask for OCAI illustration
    JD Gaatha by Shree Jagadguru Developers

    completion filed for 31 Jul 2026, now passed, 51 of 152 homes not booked

    Registered
    Feb 2021
    Possession filed
    Jul 2026moved from Jun 2024
    Homes
    152
    Booked
    101 (66%)

    MahaRERA P52100028163

  4. Rank 4Picture 1 / 5Due Jul 2026 · ask for OC
    Shreeram Shivalay West

    completion filed for 31 Jul 2026, now passed, 66 of 128 homes not booked

    Registered
    Aug 2019
    Possession filed
    Jul 2026moved from Jun 2023
    Homes
    128
    Booked
    62 (48%)

    MahaRERA P52100021971

  5. Rank 5Picture 1 / 5
    Nivasa Enchante by NIVASA ASSOCIATES

    completion filed for 31 Mar 2026, now passed, 21 of 284 homes not booked

    Registered
    Apr 2022
    Possession filed
    Mar 2026
    Homes
    640
    Booked
    362 (57%)

    MahaRERA P52100034898 · registered as NIVASA ENCHANTE - PHASE I

  6. Rank 6Due Mar 2026 · ask for OCThe project's position on the map
    Aaiji Pink City by AAIJI REALTY

    completion filed for 30 Mar 2026, now passed, 39 of 108 homes not booked

    Registered
    Jan 2020
    Possession filed
    Mar 2026
    Homes
    108
    Booked
    69 (64%)

    MahaRERA P52100023905

  7. Rank 7Due Jun 2025 · ask for OC
    Keshar Gold by KESHAR GROUP

    completion filed for 30 Jun 2025, now passed, 13 of 48 homes not booked

    Registered
    Oct 2020
    Possession filed
    Jun 2025moved from Dec 2024
    Homes
    48
    Booked
    35 (73%)

    MahaRERA P52100026834

  8. Rank 8Due Jun 2025 · ask for OC
    Vision Heights by SHREE MAHALAXMI DEVELOPERS

    completion filed for 30 Jun 2025, now passed, 37 of 70 homes not booked

    Registered
    Sep 2022
    Possession filed
    Jun 2025
    Homes
    70
    Booked
    33 (47%)

    MahaRERA P52100046992

What changed in the last month

Questions buyers ask

Which projects in Lohegaon, Pune are ready to move?
As of 29 Nov 2026, 8 projects in Lohegaon have passed the completion date filed with MahaRERA in the last three years and still have 10 or more homes not booked, the newest Shreeram Shivalay East (30 Oct 2026). Ask the builder for the occupancy certificate (OC) before you book. The newest: Shreeram Shivalay East, Swami Residency, JD Gaatha, Shreeram Shivalay West, Nivasa Enchante.
Does a passed completion date mean I can move in?
Not on its own. The completion date is what the builder filed with MahaRERA. The occupancy certificate (OC) from the local authority is what says the building can be lived in: ask for it.
Where do these numbers come from?
MahaRERA's public records, read by Avasetu; this list was worked out on 2026-11-29. Each project's page shows the date we read its record.

The same list near Lohegaon

How this list is made

Projects whose completion date filed with MahaRERA passed in the last three years and that still have 10 or more homes not booked, newest first. Offices and shops are left out. MahaRERA does not show the occupancy certificate, so ask the builder for it. Towers and phases of one project count once. From MahaRERA public records, worked out on 29 Nov 2026; each project's page shows the date we read its record. No builder pays to be on this list. This is general information, not investment or legal advice.