Ready to move projects in Kharadi, Pune
Updated 21 Nov 2026 · from MahaRERA's records
As of 29 Nov 2026, 7 projects in Kharadi have passed the completion date filed with MahaRERA in the last three years and still have 10 or more homes not booked, the newest Majestique Marbella (30 Sep 2025). Ask the builder for the occupancy certificate (OC) before you book.
7 projects
Rank 1Picture 1 / 5Majestique Marbella by Majestique Landmarkscompletion filed for 30 Oct 2026, now passed, 52 of 177 homes not booked
- Registered
- Jul 2020
- Possession filed
- Sep 2025
- Homes
- 453
- Booked
- 300 (66%)
MahaRERA P52100025697 · registered as MAJESTIQUE MARBELLA PHASE 1 · filed by Majestique Empire LLP
- Rank 2Due Mar 2026 · ask for OCThe project's position on the mapMithila Residency
completion filed for 31 Mar 2026, now passed, 11 of 12 homes not booked
- Registered
- May 2021
- Possession filed
- Mar 2026
- Homes
- 12
- Booked
- 1 (8%)
MahaRERA P52100029255
- Rank 3Due Dec 2025 · ask for OCThe project's position on the mapChandan Heights by OM DEVELOPERS
completion filed for 31 Dec 2025, now passed, 20 of 36 homes not booked
- Registered
- Mar 2022
- Possession filed
- Dec 2025
- Homes
- 36
- Booked
- 16 (44%)
MahaRERA P52100034307
- Rank 4Picture 1 / 3Due Dec 2025 · ask for OCAI illustrationShanti Anand by SANKALP PROMOTERS
completion filed for 31 Dec 2025, now passed, 17 of 40 homes not booked
- Registered
- Mar 2023
- Possession filed
- Dec 2025
- Homes
- 40
- Booked
- 23 (58%)
MahaRERA P52100049972
- Rank 5Due Dec 2025 · ask for OCThe project's position on the mapVenus Enclave
completion filed for 31 Dec 2025, now passed, 34 of 40 homes not booked
- Registered
- Dec 2023
- Possession filed
- Dec 2025
- Homes
- 40
- Booked
- 6 (15%)
MahaRERA P52100053855
- Rank 6Picture 1 / 3Due Dec 2025 · ask for OCAI illustrationGuruvista Phase II by GURUVISTA AOP
completion filed for 30 Dec 2025, now passed, 28 of 97 homes not booked
- Registered
- Mar 2019
- Possession filed
- Dec 2025
- Homes
- 97
- Booked
- 69 (71%)
MahaRERA P52100019971
- Rank 7Due Sep 2025 · ask for OCZen Estate by DESTINATION KHARADI DEVELOPERS LLP
completion filed for 30 Sep 2025, now passed, 68 of 541 homes not booked
- Registered
- Sep 2019
- Possession filed
- Sep 2025
- Homes
- 541
- Booked
- 473 (87%)
MahaRERA P52100022495
Questions buyers ask
- Which projects in Kharadi, Pune are ready to move?
- As of 29 Nov 2026, 7 projects in Kharadi have passed the completion date filed with MahaRERA in the last three years and still have 10 or more homes not booked, the newest Majestique Marbella (30 Sep 2025). Ask the builder for the occupancy certificate (OC) before you book. The newest: Majestique Marbella, Mithila Residency, Chandan Heights, Shanti Anand, Venus Enclave.
- Does a passed completion date mean I can move in?
- Not on its own. The completion date is what the builder filed with MahaRERA. The occupancy certificate (OC) from the local authority is what says the building can be lived in: ask for it.
- Where do these numbers come from?
- MahaRERA's public records, read by Avasetu; this list was worked out on 2026-11-29. Each project's page shows the date we read its record.
The same list near Kharadi
How this list is made
Projects whose completion date filed with MahaRERA passed in the last three years and that still have 10 or more homes not booked, newest first. Offices and shops are left out. MahaRERA does not show the occupancy certificate, so ask the builder for it. Towers and phases of one project count once. From MahaRERA public records, worked out on 29 Nov 2026; each project's page shows the date we read its record. No builder pays to be on this list. This is general information, not investment or legal advice.