Top projects in Pimple Saudagar, Pune
Updated 23 Nov 2026 · from MahaRERA's records
As of 28 Nov 2026, 18 projects in Pimple Saudagar still have 10 or more homes open on MahaRERA. Magnus sells fastest: 35 homes booked (20% of its 173 homes) between 2026-10-13 and 2026-11-12; 46 of 173 homes still open; completion date not moved by the builder. 14 more are sold out or nearly (fewer than 10 homes open).
Top 10 you can still buy
Most homes booked first (booked lately, where MahaRERA shows it), among projects with 10 or more homes open
Rank 1Under construction- Price
- 3 BHK ₹2.12 Cr
- Possession filed
- Jul 2029
- Registered
- Nov 2025
46 homes open · 127 of 173 booked (73%)
35 homes booked (20% of its 173 homes) between 2026-10-13 and 2026-11-12; completion date not moved by the builder.
MahaRERA PR1261012501489
- Rank 2Possession soonThe project's position on the map
- Price
- 3 BHK ₹2.55 Cr
- Possession filed
- Apr 2027
- Registered
- Oct 2022
44 homes open · 126 of 170 booked (74%)
12 homes booked (7% of its 170 homes) between 2026-10-13 and 2026-11-12; completion date not moved by the builder.
MahaRERA P52100047282
- Rank 3Possession soon
- Price
- Ask for price
- Possession filed
- Apr 2027
- Registered
- May 2024
18 homes open · 66 of 84 booked (79%)
5 homes booked (6% of its 84 homes) between 2026-10-14 and 2026-11-13; completion date not moved by the builder; the builder kept the date on 5 of 6 Pune projects.
MahaRERA P52100056332
- Rank 4Due Sep 2026 · ask for OC
- Price
- Ask for price
- Possession filed
- Sep 2026
- Registered
- Jul 2023
41 homes open · 163 of 204 booked (80%)
About 4 homes booked a month since registration (Jul 2023); completion date moved 2 months later.
MahaRERA P52100051930
- Rank 5Under construction
- Price
- Ask for price
- Possession filed
- Mar 2029
- Registered
- Nov 2022
16 homes open · 90 of 106 booked (85%)
About 2 homes booked a month since registration (Nov 2022); completion date not moved by the builder.
MahaRERA P52100047672
- Rank 6Under construction
- Price
- Ask for price
- Possession filed
- Jul 2028
- Registered
- Feb 2023
139 homes open · 52 of 191 booked (27%)
About 1 homes booked a month since registration (Feb 2023); completion date not moved by the builder.
MahaRERA P52100049203
- Rank 7Possession soon
- Price
- Ask for price
- Possession filed
- Apr 2027
- Registered
- Jan 2024
42 homes open · 39 of 81 booked (48%)
About 1 homes booked a month since registration (Jan 2024); completion date moved 6 months later.
MahaRERA P52100054268
- Rank 8
- Price
- Ask for price
- Possession filed
- Jan 2028 to Apr 2028
- Registered
- Jun 2020
194 homes open · 313 of 507 booked (62%)
About 1 homes booked a month since registration (Jun 2020); completion date moved 12 months later.
MahaRERA P52100025516
- Rank 9Due Oct 2026 · ask for OC
- Price
- Ask for price
- Possession filed
- Oct 2026
- Registered
- Jun 2022
16 homes open · 56 of 72 booked (78%)
About 1 homes booked a month since registration (Jun 2022); completion date moved 6 months later.
MahaRERA P52100046402
- Rank 10Due Dec 2025 · ask for OC
- Price
- Ask for price
- Possession filed
- Dec 2025
- Registered
- Aug 2021
103 homes open · 53 of 156 booked (34%)
About 1 homes booked a month since registration (Aug 2021); completion date not moved by the builder.
MahaRERA P52100030372
Pick by what you need in Pimple Saudagar
From the list above: MahaRERA's records, and prices the builder's site states or two property sites agree on.
| If you want | Project | Why |
|---|---|---|
| Selling fastest | MagnusASWANI REALTY NEXUS LLP | 35 homes booked (20% of its 173 homes) between 2026-10-13 and 2026-11-12 |
| Lowest checked price | CullinanM/s Garve Corporation | 3 BHK from ₹2.02 crore |
| Earliest possession | Audumber ResidencyShama Construction Through Properiter Vikram Manohar Kamthe | possession filed for 31 Mar 2027 |
| Most homes to choose from | CullinanM/s Garve Corporation | 215 of 227 homes open |
| Builder that keeps its dates | 24 Sunshine VivaPARSHWA DEVELOPERS | date not moved; the builder kept the date on 5 of 6 Pune projects |
More projects with homes open (8)
- Rank 11Due Dec 2025 · ask for OCEpic Phase 2
about 1 homes booked a month since registration (Feb 2021); 21 of 77 homes still open; completion date not moved by the builder
- Registered
- Feb 2021
- Possession filed
- Dec 2025
- Homes
- 77
- Booked
- 56 (73%)
MahaRERA P52100028322
- Rank 12Due Oct 2026 · ask for OCAustin One by DIVYA ASSOCIATES
about 1 homes booked a month since registration (May 2021); 27 of 70 homes still open; completion date moved 6 months later; the builder kept the date on 3 of 5 Pune projects
- Registered
- May 2021
- Possession filed
- Oct 2026moved from Dec 2025
- Homes
- 70
- Booked
- 43 (61%)
MahaRERA P52100029297
- Rank 13Under constructionCullinan by M/s Garve Corporation
about 1 homes booked a month since registration (Jan 2025); 215 of 227 homes still open; completion date not moved by the builder
- Registered
- Jan 2025
- Possession filed
- Apr 2030moved from Dec 2029
- Homes
- 227
- Booked
- 12 (5%)
MahaRERA P52100078994
- Rank 14Due Oct 2026 · ask for OCOrchids by SAI BALAJI CONSTRUCTIONS
about 1 homes booked a month since registration (Sep 2021); 17 of 40 homes still open; completion date moved 24 months later
- Registered
- Sep 2021
- Possession filed
- Oct 2026moved from Jun 2024
- Homes
- 40
- Booked
- 23 (58%)
MahaRERA P52100030725
- Rank 15Possession soonAudumber Residency by Shama Construction Through Properiter Vikram Manohar Kamthe
about 1 homes booked a month since registration (Jun 2023); 41 of 54 homes still open; completion date moved 9 months later
- Registered
- Jun 2023
- Possession filed
- Mar 2027moved from Feb 2026
- Homes
- 54
- Booked
- 13 (24%)
MahaRERA P52100051532
- Rank 16Under constructionSahil Heights A1 by VAISHNAVI PROMOTERS AND DEVELOPERS
about 1 homes booked a month since registration (Feb 2024); 70 of 80 homes still open; completion date not moved by the builder; the builder kept the date on 5 of 9 Pune projects
- Registered
- Feb 2024
- Possession filed
- Apr 2028moved from Dec 2027
- Homes
- 80
- Booked
- 10 (13%)
MahaRERA P52100054948
- Rank 17Possession soonKingston Avenue Phase II by Supreme Developers
about 1 homes booked a month since registration (Nov 2022); 57 of 68 homes still open; completion date moved 24 months later
- Registered
- Nov 2022
- Possession filed
- Apr 2027moved from Dec 2024
- Homes
- 68
- Booked
- 11 (16%)
MahaRERA P52100047815
- Rank 18Possession soonVarad Classic by VINAY SUDAM KUNJIR, RAGINI RAJESH JAGATAP,VARSHA VIJAY SONAWANE, AND SRK REALITY THROUGH SUSHMA RAJENDRA TANPURE. KETAN ANIL MURKUTE
about 1 homes booked a month since registration (Apr 2022); 46 of 56 homes still open; completion date not moved by the builder
- Registered
- Apr 2022
- Possession filed
- Jul 2027moved from Mar 2027
- Homes
- 56
- Booked
- 10 (18%)
MahaRERA P52100034474
Sold out or nearly: 14 projects
Fewer than 10 homes left with the builder, as MahaRERA shows. A resale flat or a cancelled booking can still come up.
| Project | Builder | Booked | Possession filed | Ask |
|---|---|---|---|---|
| Kolte Patil 24K Opula | Kolte Patil | 280 of 280 | Dec 2025 | Ask about resale |
| Marigold Calendula | AUDUMBAR HOMES LLP | 77 of 77 | Jan 2027 | Ask about resale |
| Vantage Twenty One | VIVANTA REALTY | 376 of 379 | Oct 2027 | Ask about resale |
| Arc Finezza | ARC FINEZZA DEVELOPERS LLP | 139 of 141 | Mar 2026 | Ask about resale |
| Dwarka Heights | 99 of 102 | Dec 2025 | Ask about resale | |
| Kolte Patil 24K Manor | Kolte Patil | 250 of 351 | Oct 2028 | Ask about resale |
| Silver Orchid | 37 of 42 | Mar 2026 | Ask about resale | |
| Kohinoor S3 Lifestyle | Kohinoor Group | 55 of 63 | Nov 2026 | Ask about resale |
| Green Alley Phase - II | ARYAN DEVELOPERS | 13 of 15 | Apr 2027 | Ask about resale |
| Santiago Sunrise | Santiago Realtech Ventures | 40 of 48 | Apr 2028 | Ask about resale |
| Swapnashilp | Tirupati Developers | 14 of 20 | Apr 2027 | Ask about resale |
| Urban Edge | Gruham Constructions | 5 of 8 | Dec 2025 | Ask about resale |
| Soham Shree | SOHAM DEVELOPERS | 3 of 6 | Dec 2027 | Ask about resale |
| Dnyandeep Dream | Shambhuraj Developers | 2 of 11 | Oct 2028 | Ask about resale |
What changed in the last month
- 13 Nov 2026: 5 more homes booked at 24 Sunshine Viva (MahaRERA)
- 12 Nov 2026: 12 more homes booked at Presidential Tower (MahaRERA)
- 12 Nov 2026: 35 more homes booked at Magnus (MahaRERA)
Questions buyers ask
- Which are the top projects in Pimple Saudagar, Pune?
- As of 28 Nov 2026, 18 projects in Pimple Saudagar still have 10 or more homes open on MahaRERA. Magnus sells fastest: 35 homes booked (20% of its 173 homes) between 2026-10-13 and 2026-11-12; 46 of 173 homes still open; completion date not moved by the builder. 14 more are sold out or nearly (fewer than 10 homes open). In order: Magnus, Presidential Tower, 24 Sunshine Viva, Sai Aura, Hillcrest C Building.
- How is this list ranked?
- Only projects with 10 or more homes not booked and 40 or more homes in all are ranked, one row per project however many MahaRERA registrations it has: by homes booked in the last 90 days where two of our readings show it, else by homes booked a month since registration. MahaRERA's counts are the builders' own, filed each quarter. No builder pays to be on it or to move up.
- Why is a fully booked project in Pimple Saudagar not on this list?
- The builder has fewer than 10 homes left to sell, so it is listed apart below: 14 such projects. A resale flat or a cancelled booking can still come up there; ask us.
- Where do these numbers come from?
- MahaRERA's public records, read by Avasetu; this list was worked out on 2026-11-28. Each project's page shows the date we read its record.
The same list near Pimple Saudagar
How this list is made
Projects still being built or finished within a year that have 10 or more homes not booked and 40 or more homes in all, one row per project, ranked by homes booked in the last 90 days where two of our readings of MahaRERA show it, else by homes booked a month since registration (a project registered under six months counts as six months old). Each row says whether the builder moved the completion date and how many of the builder's Pune projects kept theirs. Booked counts are the builders' own, filed on MahaRERA each quarter. Projects with fewer homes open are listed apart, never ranked. Offices and shops are left out. Towers and phases of one project count once. From MahaRERA public records, worked out on 28 Nov 2026; each project's page shows the date we read its record. No builder pays to be on this list. This is general information, not investment or legal advice.