Lodha Kharadi Pune P3, Upper Kharadi
Filed on MahaRERA as Kharadi Pune P3
by Lodha · Upper Kharadi, Pune · 412207
- Homes
- 3, 3.5, 4.5, 5 BHK
- Price
- from ₹2.34 Cr
- EMI about ₹1.62 L a month
- Possession
- Sep 2028
- completion filed with MahaRERA
- Booked
- 95 of 106
Avasetu's read (from MahaRERA data, 3 Nov 2026)
Sales are ahead of nearby projects, with 95 of 106 homes booked (90%) compared to about 80% across 9 similar Upper Kharadi projects. The developer has moved completion dates 3 months or more later in 4 of 33 Pune projects with both dates on MahaRERA. The completion date filed with MahaRERA is 30 Sep 2028.
What stands out
As of 3 Nov 2026, from MahaRERA and the sources below.
- 90% booked: Ninety percent of the 106 homes are booked, well above the area median of 83% for similar projects.
- The registration includes a single building that can reach up to 29 floors.
- 3 acres land: The site occupies three acres, providing ample space for amenities and open areas.
Updated 18 Nov 2026
Pictures
From the builder's website. Renders are the builder's artist's impressions and plans are indicative: check the sanctioned plans before you book.
Price
3 BHK
₹2.34 Cr – ₹2.5 Cr
from 1,270 sq ft · ₹18,425/sq ft
Last checked 18 Nov 2026
All-in cost of the 3 BHK at ₹2.34 Cr: about ₹2.62 Cr
Price (agreement value) ₹2.34 Cr GST (5%) ₹11.7 L Stamp duty (7%) ₹16.38 L Registration (1%, at most ₹30,000) ₹30,000 Total before the builder's charges ₹2.62 Cr 3.5 BHK
From ₹2.77 Cr
from 1,511 sq ft · ₹18,332/sq ft
Last checked 18 Nov 2026
All-in cost of the 3.5 BHK at ₹2.77 Cr: about ₹3.11 Cr
Price (agreement value) ₹2.77 Cr GST (5%) ₹13.85 L Stamp duty (7%) ₹19.39 L Registration (1%, at most ₹30,000) ₹30,000 Total before the builder's charges ₹3.11 Cr 4.5 BHK
From ₹4.05 Cr
from 2,244 sq ft · ₹18,048/sq ft
Last checked 18 Nov 2026
All-in cost of the 4.5 BHK at ₹4.05 Cr: about ₹4.54 Cr
Price (agreement value) ₹4.05 Cr GST (5%) ₹20.25 L Stamp duty (7%) ₹28.35 L Registration (1%, at most ₹30,000) ₹30,000 Total before the builder's charges ₹4.54 Cr 5 BHK
From ₹7.5 Cr
Last checked 18 Nov 2026
All-in cost of the 5 BHK at ₹7.5 Cr: about ₹8.4 Cr
Price (agreement value) ₹7.5 Cr GST (5%) ₹37.5 L Stamp duty (7%) ₹52.5 L Registration (1%, at most ₹30,000) ₹30,000 Total before the builder's charges ₹8.4 Cr
Starting prices; tower, floor, parking and floor-rise change the final price. Not included: parking, club house, maintenance deposit, legal and society charges. They differ by project: ask the builder for the full cost sheet. If a price already includes GST or stamp duty, do not add them twice.
EMI on the lowest price, as an example: about ₹1.62 L a monthOn a ₹1.87 Cr loan (80% of ₹2.34 Cr) at 8.5% for 20 years. Ask your bank for its rate.
What new homes in Upper Kharadi usually ask
- 2 BHK about ₹90 L – ₹1.2 Cr (10 projects)
- 2.5 BHK about ₹1.3 – 1.5 Cr (5 projects)
- 3 BHK about ₹1.3 – 1.6 Cr (10 projects)
- 3.5 BHK about ₹1.9 – 2.3 Cr (6 projects)
- 4 BHK about ₹2.3 – 3 Cr (10 projects)
Our own guide: the middle half of the starting prices we have read for projects being sold in Upper Kharadi, rounded. Use it to judge an offer, not as a price.
Upper Kharadi average ₹11,254/sq ft across 4 projectsThe middle asking price per sq ft of other projects in Upper Kharadi.
Get the exact price for your home
The Avasetu team gets you the current price sheet for the size you want, with parking and all other charges.
Floor plans
Location
A map search by name. Open the map (opens in a new tab)
Project facts
- 2 acres of private open space for residents. (the builder's site)
- Three towers, each 27 storeys tall. (the builder's site)
- Landscape designed by Sitetectonix from Singapore. (the builder's site)
Amenities
- Includes tennis, squash, basketball, futsal courts, seating pavilions, infinity pool, pool deck, nature trails. (the builder's site)
- Clubhouse area is 12,000 square feet. (the builder's site)
- Units feature marble flooring, tall ceilings, full-height windows. (the builder's site)
Last checked 18 Nov 2026.
MahaRERA record
From MahaRERA, read 3 Nov 2026Possession date
30 Sep 2028
The completion date filed with MahaRERA is 30 Sep 2028; MahaRERA's August 2026 order added 4 months to it (the builder has not moved it). At registration: 31 May 2028.
Beside other Upper Kharadi projects
Worked out by Avasetu- Homes booked
- 90%
- The middle of 9 Upper Kharadi projects registered within a year of it: 87%.
- Completion date
- Not moved by the builder
- 2 of 21 Upper Kharadi projects being built moved theirs 3 months or more.
From MahaRERA records read 3 Nov 2026. Homes booked are the builders' own quarterly counts. Dates net of MahaRERA's August 2026 order.
The record
- Homes booked
- 95 of 106
- Towers
- 1 in this registration
- The tallest has 29 floors. 11 in the whole project.
- Registered on
- 25 Jan 2024
- MahaRERA registration
- P52100054436
- Listed or updated on MahaRERA 6 Jul 2026.
- Promoter (builder)
- Lodha Developers Limited
- Project type
- Residential / Group Housing
- Pincode
- 412207
Tower by tower
1 building
Buildings
From MahaRERA| Building | Floors | Homes | Other |
|---|---|---|---|
| P3 | 29 | 106 | 0 |
As filed with MahaRERA (sanctioned floors).
What the builder's and property sites say
Gathered and checkedLast checked 18 Nov 2026. MahaRERA counts where they differ.
Lodha: track record
From MahaRERA recordsLodha has 30 projects in our MahaRERA register for Pune. 5 of 30 with both dates moved the completion date 3 months or more later, by 7 months on average.
- LODHA BELMONDO ASHBRIDGE D, Ecompletion filed 31 Dec 2017
- LODHA BELMONDO AUGUSTA Ccompletion filed 31 Dec 2017
- LODHA BELMONDO SAWGRASS Bcompletion filed 30 Apr 2018
- Lodha Belmondo St. Andrews B,C,D Villa 1 to 28completion filed 31 Jul 2018
- LODHA BELMONDO - ESTANCIA Bcompletion filed 31 Aug 2018
- LODHA BELMONDO Pebble Beach E, Estancia Acompletion filed 30 Sep 2018
- Lodha Belmondo - Pebble Beach Dcompletion filed 31 Dec 2018
- LODHA BELMONDO ST. ANDREWS Ecompletion filed 31 Dec 2019
- Lodha Belmondo - Townhousescompletion filed 30 Jun 2022
- Lodha Belmondo - Tower 29completion filed 30 Sep 2024
- Lodha Belmondo Townhouse 3completion filed 31 Mar 2026
- Lodha Pune NIBM Projectcompletion filed 31 Jul 2026, moved 3 months later
- Lodha Belmondo Townhouse 2completion filed 30 Nov 2026, moved 4 months later
- Lodha Belmondo - Tower 30completion filed 31 Dec 2026, moved 11 months later
- Kharadi Pune Phase I - Tower 1 to 4completion filed 28 Feb 2027
- Lodha Bella Vita Signetcompletion filed 30 Apr 2027
- HINJEWADI PROJECTcompletion filed 30 Oct 2027
- Kharadi Pune P2completion filed 29 Feb 2028
- Bund Garden Projectcompletion filed 30 Aug 2028
- Kharadi Signetcompletion filed 31 Dec 2028
- Hinjewadi Premium-Tower 7completion filed 30 Apr 2029
- Kharadi Pune P1completion filed 30 Oct 2029
- Kothrud Pune -Tower Acompletion filed 30 Jan 2030
- Kharadi New Project - Tower 1completion filed 31 Jul 2030
- Belmondo Townhouse 4completion filed 31 Aug 2030
- KHARADI NEW PROJECT -TOWER 5completion filed 30 Jan 2031, moved 6 months later
- Lodha Hinjewadi Phase 3completion filed 30 Jun 2031
- Pune Wakad Projectcompletion filed 29 Oct 2031, moved 12 months later
- Wakad New Project- Tower 1completion filed 31 Dec 2032
Planning to buy here?
Ask about prices, floor plans, offers or a site visit.
Other projects in Upper Kharadi
- Lodha Kharadi Pune P2from ₹2.54 Cr · possession Feb 2028Starts ₹20 L higher than Lodha Kharadi Pune P3
- iLIFE Business Zonefrom ₹73 L · possession Apr 2028Starts ₹1.61 Cr lower than Lodha Kharadi Pune P3
- 31 Palma Drive3 BHK · from ₹1.37 Cr · possession Oct 2029Starts ₹97 L lower than Lodha Kharadi Pune P3
- 343 Crestfrom ₹71 L · possession Dec 2027Starts ₹1.63 Cr lower than Lodha Kharadi Pune P3
- Lodha Kharadi Pune P13.5, 4 BHK · from ₹3.5 Cr · possession Oct 2029Starts ₹1.16 Cr higher than Lodha Kharadi Pune P3
- Lodha Kharadi Pune Phase Ifrom ₹1.6 Cr · possession Feb 2027Starts ₹74 L lower than Lodha Kharadi Pune P3
More by Lodha Developers Limited
- Lodha Belmondo Townhouse 4possession Aug 2030
- Lodha Bund Garden Projectpossession Aug 2028
- Lodha Hinjewadi Project2, 2.5, 3, 3.5, 4, 4.5, 5 BHK · from ₹1 Cr · possession Oct 2027
- Lodha Hinjewadi Premium3, 4 BHK · from ₹2.1 Cr · possession Apr 2029
- Lodha Camelot4 BHK · from ₹2.77 Cr · possession Jul 2030
- Lodha Camelot4 BHK · from ₹2.6 Cr · possession Jan 2031
- Lodha Kharadi Pune P13.5, 4 BHK · from ₹3.5 Cr · possession Oct 2029
- Lodha Kharadi Pune P2possession Feb 2028
FAQ
What is the price of Lodha Kharadi Pune P3?
3 BHK: ₹2.34 Cr to ₹2.5 Cr; 3.5 BHK: ₹2.77 Cr; 4.5 BHK: ₹4.05 Cr; 5 BHK: ₹7.5 Cr, checked on 18 Nov 2026. Builders change prices often and add parking and other charges: ask for the current price sheet before you book.
What is the possession date of Lodha Kharadi Pune P3?
The completion date filed with MahaRERA is 30 Sep 2028; MahaRERA's August 2026 order added 4 months to it (the builder has not moved it).
What is the MahaRERA number of Lodha Kharadi Pune P3?
Lodha Kharadi Pune P3 is registered with MahaRERA as P52100054436.
How many towers and floors does Lodha Kharadi Pune P3 have?
MahaRERA lists 1 building, the tallest with 29 floors.
How many flats are there in Lodha Kharadi Pune P3?
MahaRERA lists 106 units.
How many homes in Lodha Kharadi Pune P3 are booked?
95 of 106 homes were booked as per MahaRERA on 3 Nov 2026.
Who is the builder of Lodha Kharadi Pune P3?
The promoter registered with MahaRERA is Lodha Developers Limited. Our register has 30 Pune projects by Lodha; 5 of 30 with both dates moved their completion date 3 months or more later.
Where is Lodha Kharadi Pune P3?
Lodha Kharadi Pune P3 is in Upper Kharadi, Pune (pincode 412207).
Sources
- Registration, promoter, pincodeFrom MahaRERA
MahaRERA listing, updated 6 Jul 2026
- Dates and homes bookedFrom MahaRERA
Checked 18 Nov 2026
- Buildings and wingsFrom MahaRERA
Checked 3 Nov 2026
- Location and nearbyGathered and checked
Checked 18 Nov 2026
- DescriptionGathered and checked
Checked 18 Nov 2026
- PricesGathered and checked
The builder's site, or two property sites that agree (18 Nov 2026)
- Project facts and amenitiesGathered and checked
The builder's site and property sites, which can be wrong: where they differ from MahaRERA, MahaRERA counts (18 Nov 2026)