Kohinoor Riverdale from space, 2023 to 2026

Ground clearing began in early 2023, followed by a building footprint in late 2023 ahead of the May 2024 MahaRERA registration. Construction footprints and shadows expanded continuously through 2026.

Today, from Google satellite, centred on the same map pin.

12 seasons, Jan 2023 to Oct 2026: every clear pass of the Sentinel-2 satellite over the project's map pin, October to May (the monsoon is under cloud). A new picture is added every season.

Season by season

  1. Oct–Dec 2026Little change inside the ring.
  2. Apr–May 2026Little change; blue sheets visible to the north and east.
  3. Jan–Mar 2026Building structure remains prominent with strong north-west shadow inside the ring.
  4. Oct–Dec 2025Building footprint with tall shadow expanding inside the ring.
  5. Jan–Mar 2025Distinct building footprint casting shadows; surrounding area shows cleared ground.
  6. Oct–Dec 2024Expanding building footprint casting a distinct shadow to the north-west.
  7. Jan–Mar 2024Building footprint defined with casting shadow inside the ring.
  8. Oct–Dec 2023Bright structure footprint appears in the ring before the May 2024 registration.
  9. Jan–Mar 2023Ground disturbed and cleared in the ring; surrounding vegetation decreased.

Kohinoor Riverdale: prices, MahaRERA facts and floor plansMore Pune projects from space

The yellow ring marks the project's map pin. Each picture is 600 m across at 10 m a pixel: it takes in neighbouring plots, and shows ground, not floors. Pictures are the middle of every clear pass, sharpened and colour-corrected by code; nothing is drawn in. The lines are written from the pictures and the MahaRERA filings, and say only what can be seen. Contains modified Copernicus Sentinel data 2023-2026.