- Possession
- from Aug 2030
- its parts filed Aug 2030 to Apr 2031
- Booked
- 617 of 1,315
- 55 booked in the last 30 days
Avasetu's read (from MahaRERA data, 12 Oct 2026)
Out of 452 homes, 350 are booked, which is 77 percent compared to about 24 percent for 103 similar Tathawade projects. Of 59 Kolte Patil projects in Pune, 8 moved the completion date 3 months or more later, and the date filed with MahaRERA is 30 Aug 2030.
What stands out
As of 12 Nov 2026, from MahaRERA and the sources below.
- 77% of homes booked: MahaRERA shows 350 of 452 homes booked.
- 77% booked here; the middle of 103 Tathawade projects registered within a year of it is 24%.
- The same filing company has 4 other projects still being built in Tathawade.
- Towers: Towers: 2.
- Completion date filed with MahaRERA: 30 Aug 2030.
Updated 13 Nov 2026
Pictures
From the builder's website. Renders are the builder's artist's impressions and plans are indicative: check the sanctioned plans before you book.
Price
No price for Kolte Patil Qrious is published yet.
What new homes in Tathawade usually ask
- 2 BHK about ₹70 – 90 L (40 projects)
- 2.5 BHK about ₹90 L – ₹1.1 Cr (4 projects)
- 3 BHK about ₹90 L – ₹1.3 Cr (38 projects)
- 4 BHK about ₹1.3 – 2 Cr (7 projects)
Our own guide: the middle half of the starting prices we have read for projects being sold in Tathawade, rounded. Use it to judge an offer, not as a price.
Tathawade average ₹10,852/sq ft across 19 projectsThe middle asking price per sq ft of other projects in Tathawade.
Ask about this project
Outside our main East Pune areas: the Avasetu team finds out what it can.
Floor plans
Location
A map search by name. Open the map (opens in a new tab)
Project facts
- The project offers 2 and 3 BHK flats.
Last checked 13 Nov 2026.
MahaRERA record
From MahaRERA, read 12 Nov 2026Possession date
30 Aug 2030 to 30 Apr 2031
The completion dates filed with MahaRERA for its 2 registrations; each is in the table of towers and phases below.
For P52100079623: 30 Aug 2030. The completion date filed with MahaRERA is 30 Aug 2030; MahaRERA's August 2026 order added 4 months to it (the builder has not moved it). At registration: 30 Apr 2030.
The record
- Homes booked
- 617 of 1,315
- Across all 2 of its MahaRERA registrations. P52100079623 alone: 349 of 452.
- Towers
- 2 in this registration
- The tallest has 29 floors.
- Units
- 452
- 400 homes, 52 shops or offices.
- Registered on
- 17 Mar 2025
- Main MahaRERA registration
- P52100079623
- Listed or updated on MahaRERA 17 Mar 2025.
- Promoter (builder)
- Kolte-Patil Developers Limited
- Project type
- Residential / Group Housing
- Pincode
- 411033
Check before you book
From MahaRERA and checked sites- About 175 homes per acre (1,315 homes on 7.5 acres, from two property sites that agree). Towers stand close: ask how far your tower is from the next and which flats face another tower.
- 52 shops or offices are part of the project. Ask where they open and whether their visitors use the residents' gate.
Tower by tower
2 registrations, 2 buildings
Towers and phases (2 registrations)
From MahaRERAMahaRERA holds Kolte Patil Qrious as 2 registrations. Together they list 1,315 homes, 617 booked.
| Registration | Completion filed | Booked |
|---|---|---|
| LIFE REPUBLIC SECTOR R14/14TH AVENUE - QRIOUS/PHASE - IP52100079623 (opens in a new tab) | 30 Aug 2030at registration 30 Apr 2030 | 349 of 452 |
| LIFE REPUBLIC SECTOR R14/14TH AVENUE - QRIOUS/PHASE – IIPM1261012501226 (opens in a new tab) | 30 Apr 2031at registration 31 Dec 2030 | 268 of 863 |
Each row is its own MahaRERA registration, as filed.
Buildings
From MahaRERA| Building | Floors | Homes | Other |
|---|---|---|---|
| Building D | 29 | 204 | 0 |
| Building E and Shops | 28 | 196 | 52 |
As filed with MahaRERA (sanctioned floors).
What the builder's and property sites say
Gathered and checked- Land
- 7.5 acres
- Clubhouse
- 19,000 sq ft
Last checked 13 Nov 2026. MahaRERA counts where they differ.
Kolte Patil: track record
From MahaRERA recordsKolte Patil has 52 projects in our MahaRERA register for Pune. 8 of 52 with both dates moved the completion date 3 months or more later, by 16 months on average.
- GLITTERATI IIcompletion filed 30 Apr 2018, moved 4 months later
- Cherylcompletion filed 31 Aug 2018
- Ivy Estate Umang Premiercompletion filed 30 Sep 2018
- STARGAZEcompletion filed 31 Dec 2018
- Xeniacompletion filed 31 Dec 2018
- CITY VISTAcompletion filed 31 Dec 2019
- Life Republic Sector R3 - 3rd Avenuecompletion filed 31 Dec 2019
- Life Republic Sector R2 - 2nd Avenuecompletion filed 30 Sep 2020, moved 18 months later
- 24K ATRIAcompletion filed 30 Dec 2021
- LITTLE EARTH MASULKAR CITY PHASE 2completion filed 30 Dec 2021, moved 24 months later
- Life Republic - Sector R 17 B - 17 B Avenue - Noracompletion filed 30 Mar 2022
- Life Republic Sector R16 - 16th Avenuecompletion filed 30 Dec 2022
- 24K Stargazecompletion filed 30 Mar 2023
- Life Republic Sector C1 - City Elanzacompletion filed 31 Jul 2023
- Ivy Estate - Ivy Apartments and Villas and Umang Premiere and Umang Primocompletion filed 29 Dec 2023, moved 12 months later
- Ivy Estate-Niacompletion filed 29 Dec 2023, moved 12 months later
- Western Avenuecompletion filed 29 Dec 2023, moved 12 months later
- Life Republic Sector R16 - 16th Avenue Arezocompletion filed 30 Dec 2023
- Giga Platinumcompletion filed 31 Dec 2023
- LIFE REPUBLIC SECTOR R9-ORO AVENUEcompletion filed 31 Jul 2024
- Life Republic Sector R7- 7th Avenue- i Towerscompletion filed 30 Dec 2024
- Life Republic/Sector R10/10th Avenue/Universe/Phase-Icompletion filed 30 Dec 2024
- Little Earth, Kiwale Building C16completion filed 30 Jun 2025
- 24K OPULAcompletion filed 31 Dec 2025, moved 36 months later
- Life Republic Sector R17A/17A Avenue-Sound of Soul/Phase-Icompletion filed 31 Dec 2025
- LITTLE EARTH, KIWALE BUILDING C10 AND C11completion filed 30 Apr 2027
- Life Republic Sector R13/13th Avenue/Aros/Phase Icompletion filed 30 Apr 2027
- Life Republic Sector R31/31st Avenue/24K-Espadacompletion filed 30 Apr 2027
- ALERIA - BLOCK Bcompletion filed 29 Jun 2027, moved 8 months later
- Life Republic Sector R22/22nd Avenue - Atmos/Phase - Icompletion filed 29 Feb 2028
Planning to buy here?
Ask about prices, floor plans, offers or a site visit.
Other projects in Tathawade
More by Kolte-Patil Developers Limited
- Kolte Patil 24k Alturapossession Jul 2028
- Kolte Patil 24K Manorpossession Oct 2028
- Kolte Patil 24K Opulapossession Dec 2025
- Kolte Patil 45 Westpossession Jul 2028
- Kolte Patil Aleria - Block Bpossession Jun 2027
- Kolte Patil Elixir - Phase Ipossession Oct 2030
- Kolte Patil Giga Platinumpossession Dec 2023
- Kolte Patil Life Republic Sector R17A/17A Avenue-Sound of Soul/Sound Squarepossession Mar 2028
FAQ
What is the price of Kolte Patil Qrious?
No price for Kolte Patil Qrious is published yet. Ask through the enquiry form on this page for the current price.
What is the possession date of Kolte Patil Qrious?
The 2 MahaRERA registrations of Kolte Patil Qrious have filed completion dates from 30 Aug 2030 to 30 Apr 2031. For P52100079623: The completion date filed with MahaRERA is 30 Aug 2030; MahaRERA's August 2026 order added 4 months to it (the builder has not moved it).
What is the MahaRERA number of Kolte Patil Qrious?
Kolte Patil Qrious is registered with MahaRERA in 2 parts (towers or phases): P52100079623, PM1261012501226.
How many towers and floors does Kolte Patil Qrious have?
MahaRERA lists 2 buildings in registration P52100079623, one of the project's 2, the tallest with 29 floors.
How many flats are there in Kolte Patil Qrious?
MahaRERA lists 1315 units across all 2 of its MahaRERA registrations; P52100079623 has 452.
How many homes in Kolte Patil Qrious are booked?
617 of 1315 homes were booked as per MahaRERA on 12 Nov 2026, across all 2 of its MahaRERA registrations.
Who is the builder of Kolte Patil Qrious?
The promoter registered with MahaRERA is Kolte-Patil Developers Limited. Our register has 52 Pune projects by Kolte Patil; 8 of 52 with both dates moved their completion date 3 months or more later.
Where is Kolte Patil Qrious?
Kolte Patil Qrious is in 411033, Mulshi, Pune district (pincode 411033).
Sources
- Registration, promoter, pincodeFrom MahaRERA
MahaRERA listing, updated 17 Mar 2025
- Dates and homes bookedFrom MahaRERA
Checked 13 Nov 2026
- Buildings and wingsFrom MahaRERA
Checked 5 Nov 2026
- Location and nearbyGathered and checked
Checked 13 Nov 2026
- DescriptionNot checked yet
Still checking
- Project facts and amenitiesGathered and checked
The builder's site and property sites, which can be wrong: where they differ from MahaRERA, MahaRERA counts (13 Nov 2026)
Get the price sheet and floor plans for LIFE REPUBLIC SECTOR R14/14TH AVENUE - QRIOUS/PHASE - I
The Avasetu team calls or WhatsApps you back; we never share your number without your OK.