Goel Ganga Pune Baner Project-Tower 4 and 5
Filed on MahaRERA as Pune Baner Project-Tower 4 and 5
by Goel Ganga · Baner, Pune · 411038
- Homes
- 4.5 BHK
- Price
- from ₹4.99 Cr
- EMI about ₹3.46 L a month
- Possession
- Oct 2030
- completion filed with MahaRERA
- Booked
- 246 of 270
What stands out
As of 11 Nov 2026, from MahaRERA and the sources below.
- 90% of homes already booked: Buyers have already committed to 244 out of the 270 homes available in this part of the project. This high booking rate exists even though the final completion date is several years away.
- Completion date set for 29 Jun 2030: The developer originally filed for a June 2029 completion but later updated the MahaRERA date to June 2030. This project features two buildings reaching up to 31 floors.
- The builder has a record where 9 out of 28 projects in Pune with registered dates moved their completion timelines by 3 months or more. This history provides a baseline for how the company manages its construction schedules.
Updated 11 Nov 2026
Price
4.5 BHK
From ₹4.99 Cr
Last checked 12 Nov 2026
All-in cost of the 4.5 BHK at ₹4.99 Cr: about ₹5.59 Cr
Price (agreement value) ₹4.99 Cr GST (5%) ₹24.95 L Stamp duty (7%) ₹34.93 L Registration (1%, at most ₹30,000) ₹30,000 Total before the builder's charges ₹5.59 Cr
Starting prices; tower, floor, parking and floor-rise change the final price. Not included: parking, club house, maintenance deposit, legal and society charges. They differ by project: ask the builder for the full cost sheet. If a price already includes GST or stamp duty, do not add them twice.
EMI on the lowest price, as an example: about ₹3.46 L a monthOn a ₹3.99 Cr loan (80% of ₹4.99 Cr) at 8.5% for 20 years. Ask your bank for its rate.
Rough price guide for Goel Ganga Pune Baner Project-Tower 4 and 5
- 3.5 BHK about ₹3.75 – 4.5 Cr
- 5 BHK about ₹8.5 – 15 Cr
Our own rounded guide, checked against the area on 12 Nov 2026. It is not a quote: the exact price is on the builder's price sheet.
What new homes in Kothrud usually ask
- 3 BHK about ₹2.1 – 2.5 Cr (4 projects)
- 4 BHK about ₹3.5 – 4 Cr (3 projects)
Our own guide: the middle half of the starting prices we have read for projects being sold in Kothrud, rounded. Use it to judge an offer, not as a price.
Ask about this project
Outside our main East Pune areas: the Avasetu team finds out what it can.
Floor plans
Location
A map search by name. Open the map (opens in a new tab)
MahaRERA record
From MahaRERA, read 11 Nov 2026Possession date
29 Oct 2030
Completion date filed with MahaRERA. At registration: 30 Jun 2029. Moved 12 months later, 4 of them by MahaRERA's August 2026 order for most projects.
Ask for the possession date in writing in your agreement for sale.
Goel Ganga Pune Baner Project-Tower 4 and 5: what changed, as we read it
Completion date filed with MahaRERA
- 29 Jun 2030 → 29 Oct 2030, by MahaRERA's August 2026 order for most projects (not the builder); we saw it on 11 Nov 2026
Read by Avasetu from MahaRERA on each date shown. MahaRERA shows only the latest figures, so earlier ones are our own readings.
Beside other Kothrud projects
Worked out by Avasetu- Homes booked
- 91%
- The middle of 101 Kothrud projects registered within a year of it: 11%.
- Completion date
- Moved 12 months later
- 36 of 208 Kothrud projects being built moved theirs 3 months or more.
From MahaRERA records read 11 Nov 2026. Homes booked are the builders' own quarterly counts. Dates net of MahaRERA's August 2026 order.
The record
- Homes booked
- 246 of 270
- Towers
- 2 in this registration
- The tallest has 37 floors.
- Registered on
- 3 Oct 2024
- MahaRERA registration
- PR1261012400049
- Listed or updated on MahaRERA 21 Aug 2026.
- Promoter (builder)
- Goel Ganga Ventures India Private Limited
- Project type
- Residential / Group Housing
- Pincode
- 411038
Check before you book
From MahaRERA- The builder has moved the completion date 12 months later since registration, from Jun 2029 to Oct 2030 (MahaRERA's 2026 blanket extension for all projects left out). Ask why, and which date goes in your agreement for sale.
- Towers go up to 37 floors. Ask how many lifts serve your tower and how many homes share them.
Tower by tower
2 buildings
Buildings
From MahaRERA| Building | Floors | Homes | Other |
|---|---|---|---|
| Tower-T4 | 37 | 135 | 0 |
| Tower-T5 | 37 | 135 | 0 |
As filed with MahaRERA (sanctioned floors).
Goel Ganga: track record
From MahaRERA recordsGoel Ganga has 28 projects in our MahaRERA register for Pune. 9 of 28 with both dates moved the completion date 3 months or more later, by 13 months on average.
- KAMAL C1 C2completion filed 31 Dec 2019
- GANGA ARIA B1 B2completion filed 30 Dec 2020, moved 12 months later
- SHRINIWAS LIVIANO PHASE Icompletion filed 30 Mar 2021, moved 6 months later
- GANGA BHAGYODAY D BLDG.completion filed 30 Jun 2021
- GANGA GLITZ F. BLDGcompletion filed 30 Dec 2021
- GANGA LEGEND COMMERCIALcompletion filed 30 Jun 2023
- GANGA ARIA Acompletion filed 30 Dec 2023
- GANGA LEGEND A4 AND B1..completion filed 30 Dec 2023
- GANGA LEGEND A2 AND B4completion filed 31 Dec 2023
- WAGHOLI PLOTTED DEVELOPMENTcompletion filed 30 Jun 2024
- GANGA GLITZ G UNDRI PUNEcompletion filed 30 Dec 2024
- GANGA LEGEND A3 AND B3..completion filed 30 Dec 2024
- GANGA SERIO E F BUILDINGcompletion filed 30 Dec 2024
- GANGA AASHRAYcompletion filed 31 Dec 2024
- GANGA LEGEND B2completion filed 30 Apr 2025, moved 4 months later
- GANGA DHAM TOWER B..completion filed 30 Apr 2026
- GANGA LEGEND BUILDING B6completion filed 31 Dec 2026
- GANGA UTOPIA COMMERCIALcompletion filed 30 Apr 2027, moved 24 months later
- GANGA UTOPIA E BUILDINGcompletion filed 30 Apr 2027, moved 24 months later
- GG TOWN WAGHOLI PUNEcompletion filed 30 Jun 2027
- GANGA ARCADIA A BUILDINGcompletion filed 30 Jul 2027, moved 9 months later
- GANGA DHAM TOWER C BIBVEWADI PUNEcompletion filed 30 Oct 2027, moved 12 months later
- GANGA ALTUS WING Fcompletion filed 30 Jun 2028
- GG TOWN WAGHOLI PHASE B BUILDING 8 AND 9completion filed 30 Jun 2028
- GANGA ALTUS KHARADI PUNEcompletion filed 30 Dec 2028
- Ganga Altus Building Gcompletion filed 30 Dec 2028
- Pune Baner Project-Tower 3completion filed 29 Oct 2030, moved 12 months later
Planning to buy here?
Ask about prices, floor plans, offers or a site visit.
Other projects in Baner
More by Goel Ganga Ventures India Private Limited
FAQ
What is the price of Goel Ganga Pune Baner Project-Tower 4 and 5?
4.5 BHK: ₹4.99 Cr, checked on 12 Nov 2026. Builders change prices often and add parking and other charges: ask for the current price sheet before you book.
What is the possession date of Goel Ganga Pune Baner Project-Tower 4 and 5?
The completion date filed with MahaRERA is 29 Oct 2030. At registration it was 30 Jun 2029. MahaRERA added 4 months to most projects' dates in August 2026 (Order 66/2026). Ask the builder for the possession date in your agreement, in writing.
What is the MahaRERA number of Goel Ganga Pune Baner Project-Tower 4 and 5?
Goel Ganga Pune Baner Project-Tower 4 and 5 is registered with MahaRERA as PR1261012400049.
How many towers and floors does Goel Ganga Pune Baner Project-Tower 4 and 5 have?
MahaRERA lists 2 buildings, the tallest with 37 floors.
How many flats are there in Goel Ganga Pune Baner Project-Tower 4 and 5?
MahaRERA lists 270 units.
How many homes in Goel Ganga Pune Baner Project-Tower 4 and 5 are booked?
246 of 270 homes were booked as per MahaRERA on 11 Nov 2026.
Who is the builder of Goel Ganga Pune Baner Project-Tower 4 and 5?
The promoter registered with MahaRERA is Goel Ganga Ventures India Private Limited. Our register has 28 Pune projects by Goel Ganga; 9 of 28 with both dates moved their completion date 3 months or more later.
Where is Goel Ganga Pune Baner Project-Tower 4 and 5?
Goel Ganga Pune Baner Project-Tower 4 and 5 is in Baner, Pune (pincode 411038).
Sources
- Registration, promoter, pincodeFrom MahaRERA
MahaRERA listing, updated 21 Aug 2026
- Dates and homes bookedFrom MahaRERA
Checked 12 Nov 2026
- Buildings and wingsFrom MahaRERA
Checked 12 Nov 2026
- Location and nearbyGathered and checked
Checked 12 Nov 2026
- DescriptionGathered and checked
Checked 5 Nov 2026
- PricesGathered and checked
The builder's site, or two property sites that agree (12 Nov 2026)
- Rough price guideGathered and checked
An asking price seen on one site, rounded and checked against the area (12 Nov 2026)
Get the price sheet and floor plans for Pune Baner Project-Tower 4 and 5
The Avasetu team calls or WhatsApps you back; we never share your number without your OK.