The Grand, Katraj
by Venkateshwara Construction · Katraj, Haveli, Pune district · 411046
- Possession
- Apr 2028
- completion filed with MahaRERA
- Booked
- 52 of 132
What stands out
As of 14 Nov 2026, from MahaRERA and the sources below.
- MahaRERA order added 52 months: The completion date filed with MahaRERA is 30 Apr 2028, while the first date filed at registration was 30 Dec 2023.
- Check which part is bought: This registration is part of a bigger project, so which part is being bought.
Updated 23 Nov 2026
Our team is still collecting details on The Grand.
We do not have prices, the builder's pictures and floor plans yet. What you see here is what we have now: MahaRERA's record, read on the date shown. Ask us and we send you what we find first.
Price
No price for The Grand is published yet.
What new homes in Katraj usually ask
- 1 BHK about ₹35 – 50 L (4 projects)
Our own guide: the middle half of the starting prices we have read for projects being sold in Katraj, rounded. Use it to judge an offer, not as a price.
Ask about this project
Outside our main East Pune areas: the Avasetu team finds out what it can.
Floor plans
Location
Position checkedThe project's pin on Google Maps, checked against its MahaRERA name and pincode. Open the map (opens in a new tab)
The Grand, year by year, up close
Sharp satellite pictures taken in Nov 2022, Jan 2024, Feb 2025 and Feb 2026, centred on the project's map pin, about 580 m across at about 0.3 m a pixel.
Nov 2022 Jan 2024 Feb 2025 Feb 2026 · latest
Each picture is dated by when it was taken; the ring is 100 m around the pin. Map image is the intellectual property of Esri and is used herein under license. Copyright © 2026 Esri and its licensors (imagery: Maxar, Vantor). All rights reserved. Compare every release ↗
Work hubs
- Pune Railway Station9.6 km
- Magarpatta City11.8 km
- Baner-Balewadi High Street15.2 km
- World Trade Center, Kharadi16.1 km
Nearby
- TempleShri Mandhardevi Kalubai Mandir0.8 km
- TempleBAPS Shri Swaminarayan Temple0.9 km
- CollegeZeal College of Engineering and Research1.6 km
- Bus standKatraj1.9 km
- Industrial areaNavle IT Park2.3 km
Straight-line distances; the drive is longer. Places: Google Maps.
MahaRERA record
From MahaRERA, read 14 Nov 2026Possession date
30 Apr 2028
Completion date filed with MahaRERA. At registration: 30 Dec 2023. Moved 48 months later, 4 of them by MahaRERA's August 2026 order for most projects.
Ask for the possession date in writing in your agreement for sale.
Beside other Katraj projects
Worked out by Avasetu- Completion date
- Moved 48 months later
- 24 of 112 Katraj projects being built moved theirs 3 months or more.
From MahaRERA records read 14 Nov 2026. Dates net of MahaRERA's August 2026 order.
The record
- Homes booked
- 52 of 132
- 134 in the whole project.
- Towers
- 2 in this registration
- The tallest has 13 floors.
- Registered on
- 25 Sep 2018
- MahaRERA registration
- P52100017897
- Listed or updated on MahaRERA 28 Feb 2025.
- Promoter (builder)
- Venkateshwara Construction
- Project type
- Others
- Pincode
- 411046
Check before you book
From MahaRERA- The builder has moved the completion date 48 months later since registration, from Dec 2023 to Apr 2028 (MahaRERA's 2026 blanket extension for all projects left out). Ask why, and which date goes in your agreement for sale.
Tower by tower
2 buildings
Buildings
From MahaRERA| Building | Floors | Homes | Other |
|---|---|---|---|
| A WING | 13 | 132 | 0 |
| AMENITY BUILDING | 6 | 0 | 0 |
As filed with MahaRERA (sanctioned floors).
Venkateshwara Construction: track record
From MahaRERA recordsVenkateshwara Construction has 2 projects in our MahaRERA register for Pune.
- THE GRAND MAJESTIQUEcompletion filed 30 Dec 2024
Planning to buy here?
Ask about prices, floor plans, offers or a site visit.
Other projects in Katraj
More by Venkateshwara Construction
FAQ
What is the price of The Grand?
No price for The Grand is published yet. Ask through the enquiry form on this page for the current price.
What is the possession date of The Grand?
The completion date filed with MahaRERA is 30 Apr 2028. At registration it was 30 Dec 2023. MahaRERA added 4 months to most projects' dates in August 2026 (Order 66/2026). Ask the builder for the possession date in your agreement, in writing.
What is the MahaRERA number of The Grand?
The Grand is registered with MahaRERA as P52100017897.
How many towers and floors does The Grand have?
MahaRERA lists 2 buildings, the tallest with 13 floors.
How many flats are there in The Grand?
MahaRERA lists 132 units.
How many homes in The Grand are booked?
52 of 132 homes were booked as per MahaRERA on 14 Nov 2026.
Who is the builder of The Grand?
The promoter registered with MahaRERA is Venkateshwara Construction. Our register has 2 Pune projects by Venkateshwara Construction.
Where is The Grand?
The Grand is in Haveli, Pune district (pincode 411046).
How far is The Grand from Magarpatta City?
About 11.8 km in a straight line from the map position; the drive is longer. It is the nearest of Pune's main work hubs to The Grand.
Sources
- Registration, promoter, pincodeFrom MahaRERA
MahaRERA listing, updated 28 Feb 2025
- Dates and homes bookedFrom MahaRERA
Checked 22 Nov 2026
- Buildings and wingsFrom MahaRERA
Checked 22 Nov 2026
- Location and nearbyGathered and checked
Checked 22 Nov 2026
- DescriptionGathered and checked
Checked 22 Nov 2026
Get the price sheet and floor plans for THE GRAND
The Avasetu team calls or WhatsApps you back; we never share your number without your OK.