Vaishnavi Complex, Katraj
by Vaishnavi Constructions · Katraj, Haveli, Pune district · 411046
- Possession
- Jun 2025
- completion filed with MahaRERA
- Booked
- 38 of 40
As of 17 Oct 2026, Vaishnavi Complex by Vaishnavi Constructions in Katraj, Pune district is registered with MahaRERA as P52100011355. The completion date filed with MahaRERA is 30 Jun 2025, moved from 31 Jul 2019 at registration. MahaRERA shows 38 of 40 homes booked. The filed completion date has passed: ask for the occupancy certificate (OC).
Updated 17 Oct 2026
Still being built in Katraj
Vaishnavi Complex is finished (completion filed for Jun 2025), so we do not take enquiries for it. These projects nearby still have homes to book, the soonest possession first.
- Aishwarya Heightspossession Nov 2026
- Basil Shreeji Commercialpossession Nov 2026
- Basil Shreeji Residentialpossession Nov 2026
- Rajyog C Wingpossession Dec 2026
- Tcg Gardeniapossession Dec 2026
- Capellapossession Dec 2026
- Divya Elitepossession Dec 2026
- Green Hill Phase 2possession Dec 2026
- Shree Sadguru Kshitijpossession Dec 2026
- Saideep Dwarkapossession Dec 2026
Location
A map search by name. Open the map (opens in a new tab)
MahaRERA record
From MahaRERA, read 17 Oct 2026Possession date
30 Jun 2025
Completion date filed with MahaRERA. At registration: 31 Jul 2019. Moved 71 months later.
The filed completion date has passed. Ask for the occupancy certificate (OC) before you book.
Ask for the possession date in writing in your agreement for sale.
Beside other Katraj projects
Worked out by Avasetu- Completion date
- Moved 71 months later
- 25 of 113 Katraj projects being built moved theirs 3 months or more.
From MahaRERA records read 17 Oct 2026. Dates net of MahaRERA's August 2026 order.
The record
- Homes booked
- 38 of 40
- Registered on
- 31 Aug 2017
- MahaRERA registration
- P52100011355
- Listed or updated on MahaRERA 9 Sep 2021.
- Promoter (builder)
- Vaishnavi Constructions
- Pincode
- 411046
Check before you book
From MahaRERA- The completion date filed with MahaRERA (Jun 2025) has passed. Ask for the occupancy certificate (OC) before you pay anything more.
- The builder has moved the completion date 71 months later since registration, from Jul 2019 to Jun 2025. Ask why, and which date goes in your agreement for sale.
Vaishnavi Constructions: track record
From MahaRERA recordsVaishnavi Constructions has 2 projects in our MahaRERA register for Pune.
- VAISHNAVI VIHARcompletion filed 30 Dec 2022, moved 18 months later
More by Vaishnavi Constructions
FAQ
What is the price of Vaishnavi Complex?
No price for Vaishnavi Complex is published yet. Ask through the enquiry form on this page for the current price.
What is the possession date of Vaishnavi Complex?
The completion date filed with MahaRERA is 30 Jun 2025. At registration it was 31 Jul 2019. Ask the builder for the possession date in your agreement, in writing.
What is the MahaRERA number of Vaishnavi Complex?
Vaishnavi Complex is registered with MahaRERA as P52100011355.
How many flats are there in Vaishnavi Complex?
MahaRERA lists 40 units.
How many homes in Vaishnavi Complex are booked?
38 of 40 homes were booked as per MahaRERA on 17 Oct 2026.
Who is the builder of Vaishnavi Complex?
The promoter registered with MahaRERA is Vaishnavi Constructions. Our register has 2 Pune projects by Vaishnavi Constructions.
Where is Vaishnavi Complex?
Vaishnavi Complex is in Haveli, Pune district (pincode 411046).
Has the completion date of Vaishnavi Complex passed?
Yes. Ask the builder for the occupancy certificate (OC) before you book.
Sources
- Registration, promoter, pincodeFrom MahaRERA
MahaRERA listing, updated 9 Sep 2021
- Dates and homes bookedNot checked yet
Still checking
- Buildings and wingsNot checked yet
Still checking
- Location and nearbyNot checked yet
Still checking
- DescriptionNot checked yet
Still checking