VTP Leonara, Baner
Filed on MahaRERA as VTP Leonara H building
by VTP Realty · Baner, Mulshi, Pune district · 411045
- Possession
- from May 2025
- its parts filed May 2025 to Dec 2025
- Booked
- 264 of 264
- across 1 of its 3 MahaRERA registrations
As of 13 Oct 2026, VTP Leonara by VTP Realty in Baner, Pune district is registered with MahaRERA in 3 parts, the main one P52100009529. Its parts have filed completion dates from 15 May 2025 to 25 Dec 2025. For P52100009529: The completion date filed with MahaRERA is 15 May 2025, moved from 1 Dec 2022 at registration. MahaRERA shows 264 of 264 homes booked, across 1 of its 3 MahaRERA registrations. Of 50 VTP Realty projects in Pune with both dates on MahaRERA, 27 moved the completion date 3 months or more later. The filed completion date has passed: ask for the occupancy certificate (OC).
Updated 17 Oct 2026
Still being built in Baner
VTP Leonara is finished (completion filed for Dec 2025), so we do not take enquiries for it. These projects nearby still have homes to book, the soonest possession first.
- Mercurypossession Dec 2026
- Amar Infinitypossession Dec 2026
- One Hq Banerpossession Dec 2026
- Aneesha3, 3.5 BHK · from ₹2.03 Cr · possession Dec 2026
- Anand Viharpossession Dec 2026
- Estrella 45possession Dec 2026
- Godrej Hill Retreatpossession Dec 2026
- Godrej Meadowspossession Dec 2026
- Heramb Banerpossession Dec 2026
- Kalpataru Jade Skylinepossession Dec 2026
Location
A map search by name. Open the map (opens in a new tab)
Around VTP Leonara
Measured from the Baner centre, each with its source and date.
Commute
Commute from Baner| To | By road | 9 am | 6 pm, back |
|---|---|---|---|
| Baner-Balewadi offices (Balewadi High Street) | 0.7 km | 2-4 min | 5-12 min |
| Hinjawadi Phase 1 (Rajiv Gandhi Infotech Park) | 7.2 km | 20-36 min | 24-49 min |
| Hinjawadi Phase 2 (Rajiv Gandhi Infotech Park) | 11.5 km | 28-50 min | 29-58 min |
| Hinjawadi Phase 3 (Rajiv Gandhi Infotech Park) | 14.5 km | 32-57 min | 32-55 min |
| Pune Airport (Lohegaon) | 26.3 km | 59-102 min | 66-116 min |
Driving from the Baner centre on a weekday, Google's typical traffic. Source: Google Maps (Routes API), typical weekday traffic · measured 28 Nov 2026
What's changing nearby
- PMC bridges and flyovers due in 2027The Pune Municipal Corporation expects four to five bridges and flyovers to be finished by the end of December 2026 and opened in early 2027, among them the Sadhu Vaswani bridge (likely January 2027) and the Ghorpadi flyover, about 90% built. Another bridge is due in March 2027.Status of 19 Nov 2026
- Metro Line 3 (Hinjawadi to Shivajinagar)Open: passenger trains run between Hinjawadi and District Court at 17 of the 23 stations, after the inauguration on 3 November. The other six, including Baner's and Shivajinagar, are to open in stages by January 2027.Status of 4 Nov 2026
Being built around it
229 projects with 31,953 homes being built within 2 km, due 2026 to 2033.
- Earth 1 By VTP Luxe1,680 homes · due Aug 2029
- Nyati Emerald1,561 homes · due Dec 2028
- Godrej Meadows1,366 homes · due Dec 2026
From MahaRERA's register. Source: MahaRERA project register (our copy, read daily) · measured 28 Nov 2026
Schools
All schools in Baner6 schools within 3 km: 2 CBSE, 4 ICSE.
- Bharati Vidyapeeth English Medium School,balewadiCBSEUp to Class 120.7 km
- Educon International SchoolICSEUp to Class 12 (ISC)1.1 km
- Vibgyor HighICSEUp to Class 12 (ISC)1.3 km
- St. Joseph High SchoolICSEUp to Class 102.6 km
- Lokseva EschoolCBSEUp to Class 122.7 km
- Vidya Valley SchoolICSEUp to Class 12 (ISC)3 km
Straight-line distance from the Baner centre. No fees or ratings: they are rarely published reliably. Sources: CBSE affiliated schools (SARAS), CISCE school locator, Google Maps (school positions) · measured 28 Nov 2026
Asked rent
Rent in BanerAsked rent, from 125 listings, Nov 2026
| Size | A month | Middle | Listings | Yield |
|---|---|---|---|---|
| 1 BHK | ₹20,000 to ₹27,000 | ₹24,000 | 32 | |
| 2 BHK | ₹32,500 to ₹40,000 | ₹35,500 | 46 | 3.7% |
| 3 BHK | ₹48,000 to ₹75,000 | ₹65,000 | 47 | 4.2% |
What owners ask on listings, not what tenants pay; the middle half of asks. Yield: a year's middle rent over the middle asking price for that size. Sources: MagicBricks rent listings, NoBroker rent listings, Square Yards rent listings, Asking prices of new projects (Avasetu project pages) · measured 28 Nov 2026
MahaRERA record
From MahaRERA, read 13 Oct 2026Possession date
15 May 2025 to 25 Dec 2025
The completion dates filed with MahaRERA for its 3 registrations; each is in the table of towers and phases below.
For P52100009529: 15 May 2025. Completion date filed with MahaRERA. At registration: 1 Dec 2022. Moved 29 months later.
The filed completion date has passed. Ask for the occupancy certificate (OC) before you book.
Ask for the possession date in writing in your agreement for sale.
The record
- Homes booked
- 264 of 264
- Across 1 of its 3 MahaRERA registrations.
- Registered on
- 22 Aug 2017
- Main MahaRERA registration
- P52100009529
- Listed or updated on MahaRERA 2 Jun 2025.
- Promoter (builder)
- Nnp Buildcon Pvt. Ltd
- Pincode
- 411045
Check before you book
From MahaRERA- The completion date filed with MahaRERA (May 2025) has passed. Ask for the occupancy certificate (OC) before you pay anything more.
- The builder has moved the completion date 29 months later since registration, from Dec 2022 to May 2025. Ask why, and which date goes in your agreement for sale.
Tower by tower
3 registrations
Towers and phases (3 registrations)
From MahaRERAMahaRERA holds VTP Leonara as 3 registrations. Together they list 264 homes.
| Registration | Completion filed | Booked |
|---|---|---|
| VTP Leonara H buildingP52100009529 (opens in a new tab) | 15 May 2025at registration 1 Dec 2022 | - |
| VTP Leonara Building BP52100011811 (opens in a new tab) | 14 Jun 2025 | - |
| VTP Leonara Building GP52100009845 (opens in a new tab) | 25 Dec 2025 | 264 of 264 |
Each row is its own MahaRERA registration, as filed.
VTP Realty: track record
From MahaRERA recordsVTP Realty has 50 projects in our MahaRERA register for Pune. 27 of 50 with both dates moved the completion date 3 months or more later, by 20 months on average.
- Urban Risecompletion filed 30 Jun 2018, moved 6 months later
- URBAN BALANCEcompletion filed 31 Jul 2018, moved 1 month later
- Trade Park Phase1completion filed 29 Dec 2021, moved 24 months later
- Market Placecompletion filed 30 Dec 2021, moved 24 months later
- VTP ONEcompletion filed 28 Feb 2022, moved 14 months later
- Urban Nest Phase1completion filed 30 Mar 2022, moved 24 months later
- KPSQUAREcompletion filed 30 Jun 2022
- Urbanlife plottingcompletion filed 30 Jun 2022, moved 18 months later
- Purvanchal Phase1 ABcompletion filed 29 Dec 2022, moved 18 months later
- VTP Leonara E Buidlingcompletion filed 16 May 2023
- VTP Alpinecompletion filed 14 Jun 2023, moved 12 months later
- VTP SOLITAIRE PHASE 1 ABcompletion filed 31 Oct 2023, moved 34 months later
- Purvanchal Phase2 C D Ecompletion filed 31 Dec 2023, moved 6 months later
- Vtp Beaumonde- Nation R2 Tower5completion filed 15 Apr 2024, moved 20 months later
- VTP Beaumonde-Nation R2 T1completion filed 24 Oct 2024, moved 33 months later
- VTP Belair B And D Buildingcompletion filed 30 Dec 2024
- VTP Belair C buildingcompletion filed 30 Dec 2024
- VTP Leonara A and D Buildingcompletion filed 30 Dec 2024
- VTP Leonara building C and Fcompletion filed 30 Dec 2024
- VTP TOWNSQUAREcompletion filed 31 Mar 2025, moved 33 months later
- Purvanchal F Buildingcompletion filed 29 Jun 2025, moved 12 months later
- THE HUBcompletion filed 30 Jun 2025, moved 18 months later
- VTP Beaumonde Building T3completion filed 30 Jun 2025
- VTP Cygnus Building T11completion filed 30 Jun 2025
- VTP Cygnus BuildingT12 and Commercialcompletion filed 30 Jun 2025
- Vtp Cygnus- Nation R1-Tower 9completion filed 18 Jul 2025
- VTP Beaumonde Nation R2 Tower6completion filed 15 Aug 2025, moved 12 months later
- VTP AETHEREUS HIGH STREETcompletion filed 31 Mar 2026, moved 12 months later
- VTP ALTAIRcompletion filed 29 Jun 2026, moved 8 months later
More by Nnp Buildcon Pvt. Ltd
- VTP Alpinepossession Jun 2023
- VTP Belair B And D Buildingpossession Dec 2024
- VTP Belairpossession Dec 2024
- VTP Leonara A and D Buildingpossession Dec 2024
- VTP Leonara E Buidlingpossession May 2023
- Vtp Leonara Cpossession Dec 2024
- VTP Townsquarepossession Mar 2025
- VTPBelair E and F Buildingpossession Jun 2025
FAQ
What is the price of VTP Leonara?
No price for VTP Leonara is published yet. Ask through the enquiry form on this page for the current price.
What is the possession date of VTP Leonara?
The 3 MahaRERA registrations of VTP Leonara have filed completion dates from 15 May 2025 to 25 Dec 2025. For P52100009529: The completion date filed with MahaRERA is 15 May 2025. At registration it was 1 Dec 2022. Ask the builder for the possession date in your agreement, in writing.
What is the MahaRERA number of VTP Leonara?
VTP Leonara is registered with MahaRERA in 3 parts (towers or phases): P52100009529, P52100011811, P52100009845.
How many flats are there in VTP Leonara?
MahaRERA lists 264 units across 1 of its 3 MahaRERA registrations.
How many homes in VTP Leonara are booked?
264 of 264 homes were booked as per MahaRERA on 13 Oct 2026, across 1 of its 3 MahaRERA registrations.
Who is the builder of VTP Leonara?
The promoter registered with MahaRERA is Nnp Buildcon Pvt. Ltd. Our register has 50 Pune projects by VTP Realty; 27 of 50 with both dates moved their completion date 3 months or more later.
Where is VTP Leonara?
VTP Leonara is in Mulshi, Pune district (pincode 411045).
Has the completion date of VTP Leonara passed?
Yes. Ask the builder for the occupancy certificate (OC) before you book.
Sources
- Registration, promoter, pincodeFrom MahaRERA
MahaRERA listing, updated 2 Jun 2025
- Dates and homes bookedNot checked yet
Still checking
- Buildings and wingsNot checked yet
Still checking
- Location and nearbyNot checked yet
Still checking
- DescriptionNot checked yet
Still checking