MahaRERA registered P52100045236Verify on MahaRERA (opens in a new tab)Near completion

Godrej Madhuban, Ravet

Filed on MahaRERA as MADHUBAN

See the site from above today

by Godrej Properties · Ravet, Haveli, Pune district · 412101

Possession
Jan 2027
completion filed with MahaRERA
Booked
143 of 324

As of 20 Nov 2026, Godrej Madhuban by Godrej Properties in Ravet, Pune district is registered with MahaRERA as P52100045236. The completion date filed with MahaRERA is 30 Jan 2027, moved from 30 Sep 2025 at registration (MahaRERA's August 2026 order added 4 months to most projects). MahaRERA shows 143 of 324 homes booked. That is 44% booked, against 65% for the middle of 32 Ravet projects registered within a year of it. Of 39 Godrej Properties projects in Pune with both dates on MahaRERA, 16 moved the completion date 3 months or more later.

Updated 21 Nov 2026

Our team is still collecting details on Godrej Madhuban.

We do not have prices, the builder's pictures and floor plans yet. What you see here is what we have now: MahaRERA's record, read on the date shown. Ask us and we send you what we find first.

Ask for the detailsOther new projects we are reading

Price

No price for Godrej Madhuban is published yet.

What new homes in Ravet usually ask

  • 2 BHK about ₹60 – 85 L (47 projects)
  • 2.5 BHK about ₹90 L – ₹1.1 Cr (3 projects)
  • 3 BHK about ₹85 L – ₹1.2 Cr (51 projects)
  • 4 BHK about ₹1.6 – 2 Cr (8 projects)

Our own guide: the middle half of the starting prices we have read for projects being sold in Ravet, rounded. Use it to judge an offer, not as a price.

Ravet average ₹9,812/sq ft across 30 projectsThe middle asking price per sq ft of other projects in Ravet.

Ask about this project

Outside our main East Pune areas: the Avasetu team finds out what it can.

Send your question

Godrej Madhuban from above, today

Google satellite, centred on the project's map pin. Zoom in to see the site. Google does not date its picture, and it can be a year or more old: the latest reading below is from this season.

Godrej Madhuban, year by year, up close

Sharp satellite pictures taken in Nov 2022, Jan 2024, Feb 2025 and Apr 2026, centred on the project's map pin, about 580 m across at about 0.3 m a pixel.

  1. Godrej Madhuban from above, satellite picture of Nov 2022
    Nov 2022
  2. Godrej Madhuban from above, satellite picture of Jan 2024
    Jan 2024
  3. Godrej Madhuban from above, satellite picture of Feb 2025
    Feb 2025
  4. Godrej Madhuban from above, satellite picture of Apr 2026
    Apr 2026 · latest

Each picture is dated by when it was taken; the ring is 100 m around the pin. Map image is the intellectual property of Esri and is used herein under license. Copyright © 2026 Esri and its licensors (imagery: Maxar, Vantor). All rights reserved. Compare every release ↗

Latest reading from space, Oct–Dec 2026 (looked Nov 2026)

Ring area shows minor seasonal vegetation near boundaries.

Registered with MahaRERA May 2022 · possession filed for Jan 2027

Season by season, Jan 2021 to Oct 2026: 18 seasons, October to May (the monsoon is under cloud).

Satellite imagery for Madhuban shows ground clearing and seasonal vegetation changes within the ring following its May 2022 registration. No major structural shadow or distinct building footprints are visible through the timeline.

The seasons before

  1. Apr–May 2026Dry summer conditions show unchanged bare ground.
  2. Jan–Mar 2026Site remains cleared with sparse vegetation within the ring.
  3. Oct–Dec 2025Post monsoon patches of green appear outside the ring.
Construction proof from space: Jan 2021 to Oct 2026, Copernicus Sentinel-2 (14 earlier seasons)
  1. Apr–May 2025Dry earth dominates the ring area with no new structures.
  2. Jan–Mar 2025Ground appears stable with little change from previous quarters.
  3. Oct–Dec 2024Slight vegetation growth visible near the southern ring boundary.
  4. Apr–May 2024Dry conditions show bare soil across the central plot.
  5. Jan–Mar 2024Sparse vegetation and cleared ground persist inside the ring.
  6. Oct–Dec 2023Seasonal greenery returns to the edges of the ring.
  7. Apr–May 2023Dry earth and cleared patches remain visible in the ring.
  8. Jan–Mar 2023Ground clearing continues with reduced vegetation inside the ring.
  9. Oct–Dec 2022Work shows after the May 2022 registration with minor surface changes.
  10. Apr–May 2022Dry conditions prevail with bare ground visible in the ring.
  11. Jan–Mar 2022Ground is cleared with sparse vegetation remaining inside the ring.
  12. Oct–Dec 2021Post monsoon greenery appears around the ring area.
  13. Apr–May 2021Ground remains cleared with minimal vegetation in the dry summer.
  14. Jan–Mar 2021Ring shows bare ground and low plants. Little change.

The yellow ring marks the project's map pin. Each picture is 600 m across at 10 m a pixel: it takes in neighbouring plots, and shows ground, not floors. The satellite sees 10 m a pixel, so this shows that the ground changed, not the towers themselves. Pictures are the middle of every clear pass, sharpened and colour-corrected by code; nothing is drawn in. The timeline starts a year before the project registered. The lines are written from the pictures and the MahaRERA filings, and say only what can be seen. Contains modified Copernicus Sentinel data 2021-2026.

Open the full timelineMore Pune projects from space

Floor plans

We send them to you on WhatsApp

Location

Position checked

The project's pin on Google Maps, checked against its MahaRERA name and pincode. Open the map (opens in a new tab)

Work hubs

  • Hinjawadi Phase 1 (Rajiv Gandhi Infotech Park)8.7 km
  • Baner-Balewadi High Street11.9 km
  • Pune Airport (Lohegaon)21.1 km
  • Pune Railway Station21.6 km

Nearby

  • Railway stationDehu Road1.3 km
  • SchoolS.B. Patil Public School (SBPPS) Ravet, Pune2.2 km
  • TempleISKCON (Shree Govinda Dham) Ravet2.9 km
  • CollegePimpri Chinchwad College Of Engineering (PCCOE)3.6 km
  • ShoppingD Mart Ravet3.6 km

Straight-line distances; the drive is longer. Places: Google Maps.

MahaRERA record

From MahaRERA, read 20 Nov 2026

Possession date

30 Jan 2027

Completion date filed with MahaRERA. At registration: 30 Sep 2025. Moved 12 months later, 4 of them by MahaRERA's August 2026 order for most projects.

Ask for the possession date in writing in your agreement for sale.

Beside other Ravet projects

Worked out by Avasetu
Homes booked
44%
The middle of 32 Ravet projects registered within a year of it: 65%.
Completion date
Moved 12 months later
55 of 205 Ravet projects being built moved theirs 3 months or more.

From MahaRERA records read 20 Nov 2026. Homes booked are the builders' own quarterly counts. Dates net of MahaRERA's August 2026 order.

The record

Homes booked
143 of 324
Towers
1 in this registration
The tallest has 22 floors.
Registered on
10 May 2022
MahaRERA registration
P52100045236
Listed or updated on MahaRERA 13 Aug 2026.
Promoter (builder)
Godrej Skyline Developers Limited
Project type
Residential / Group Housing
Pincode
412101

Open the MahaRERA record (opens in a new tab)

Check before you book

From MahaRERA
  • The builder has moved the completion date 12 months later since registration, from Sep 2025 to Jan 2027 (MahaRERA's 2026 blanket extension for all projects left out). Ask why, and which date goes in your agreement for sale.

Tower by tower

1 building

Buildings

From MahaRERA
BuildingFloorsHomesOther
EWS Tower223240

As filed with MahaRERA (sanctioned floors).

Godrej Properties: track record

From MahaRERA records

Godrej Properties has 39 projects in our MahaRERA register for Pune. 16 of 39 with both dates moved the completion date 3 months or more later, by 21 months on average.

All 39 projects by Godrej Properties in Pune

Planning to buy here?

Ask about prices, floor plans, offers or a site visit.

Other projects in Ravet

More by Godrej Skyline Developers Limited

FAQ

What is the price of Godrej Madhuban?

No price for Godrej Madhuban is published yet. Ask through the enquiry form on this page for the current price.

What is the possession date of Godrej Madhuban?

The completion date filed with MahaRERA is 30 Jan 2027. At registration it was 30 Sep 2025. MahaRERA added 4 months to most projects' dates in August 2026 (Order 66/2026). Ask the builder for the possession date in your agreement, in writing.

What is the MahaRERA number of Godrej Madhuban?

Godrej Madhuban is registered with MahaRERA as P52100045236.

How many towers and floors does Godrej Madhuban have?

MahaRERA lists 1 building, the tallest with 22 floors.

How many flats are there in Godrej Madhuban?

MahaRERA lists 324 units.

How many homes in Godrej Madhuban are booked?

143 of 324 homes were booked as per MahaRERA on 20 Nov 2026.

Who is the builder of Godrej Madhuban?

The promoter registered with MahaRERA is Godrej Skyline Developers Limited. Our register has 39 Pune projects by Godrej Properties; 16 of 39 with both dates moved their completion date 3 months or more later.

Where is Godrej Madhuban?

Godrej Madhuban is in Haveli, Pune district (pincode 412101).

Which school is nearest to Godrej Madhuban?

S.B. Patil Public School (SBPPS) Ravet, Pune, about 2.2 km away in a straight line from the map position; the drive is longer.

Which railway station is nearest to Godrej Madhuban?

Dehu Road, about 1.3 km away in a straight line from the map position; the drive is longer.

How far is Godrej Madhuban from Pune Airport?

About 21.1 km in a straight line from the map position; the drive is longer.

How far is Godrej Madhuban from Hinjawadi Phase 1 (Rajiv Gandhi Infotech Park)?

About 8.7 km in a straight line from the map position; the drive is longer. It is the nearest of Pune's main work hubs to Godrej Madhuban.

Sources
  • Registration, promoter, pincodeFrom MahaRERA

    MahaRERA listing, updated 13 Aug 2026

  • Dates and homes bookedFrom MahaRERA

    Checked 20 Nov 2026

  • Buildings and wingsFrom MahaRERA

    Checked 20 Nov 2026

  • Location and nearbyGathered and checked

    Checked 20 Nov 2026

  • DescriptionNot checked yet

    Still checking

Get the price sheet and floor plans for MADHUBAN

The Avasetu team calls or WhatsApps you back; we never share your number without your OK.

What would you like?

BHK

Add budget, move-in or a note (optional)

Skip anything you like. It only helps with better options.

Budget

Move in

Payment