MahaRERA registered P52100031556Verify on MahaRERA (opens in a new tab)Mid stage

VTP Verve, Baner

by VTP Realty · Baner, Mulshi, Pune district · 411045

Homes
3 BHK
Price
from ₹92 L
EMI about ₹63,872 a month
Possession
Apr 2030
completion filed with MahaRERA
Booked
643 of 701

Avasetu's read (from MahaRERA data, 13 Oct 2026)

With 644 of 701 homes booked (92%), sales are ahead of the 85% seen across 25 similar Baner projects. However, VTP Realty has moved completion dates by 3 months or more in 29 of 55 Pune projects with both dates on MahaRERA. Ask the builder about their timeline history against the completion date filed with MahaRERA of 30 Apr 2030.

What stands out

As of 27 Nov 2026, from MahaRERA and the sources below.

  • The developer originally filed for completion on 30 Jun 2026, but the current date on MahaRERA stands at 30 Apr 2030.
  • 92% of homes booked: Buyers have already taken 644 of the 701 homes. Similar projects are at about 85%.
  • With 701 homes in this registration, this development is larger than 177 of 181 ongoing projects in Baner.
  • Across Pune, 29 of 55 projects by VTP Realty moved their completion dates by 3 months or more.

Updated 12 Nov 2026

Pictures

VTP Verve, from the builder's website
VTP Verve, from the builder's website
VTP Verve, from the builder's website
VTP Verve, from the builder's website
VTP Verve, from the builder's website
VTP Verve, from the builder's website
VTP Verve, from the builder's website

From the builder's website. Renders are the builder's artist's impressions and plans are indicative: check the sanctioned plans before you book.

Price

  • 3 BHK

    ₹92 L – ₹1.17 Cr

    from 1,218 sq ft · ₹7,553/sq ft

    Last checked 4 Nov 2026

    All-in cost of the 3 BHK at ₹92 L: about ₹1.03 Cr
    Price (agreement value)₹92 L
    GST (5%)₹4.6 L
    Stamp duty (7%)₹6.44 L
    Registration (1%, at most ₹30,000)₹30,000
    Total before the builder's charges₹1.03 Cr

Starting prices; tower, floor, parking and floor-rise change the final price. Not included: parking, club house, maintenance deposit, legal and society charges. They differ by project: ask the builder for the full cost sheet. If a price already includes GST or stamp duty, do not add them twice.

EMI on the lowest price, as an example: about ₹63,872 a monthOn a ₹73.6 L loan (80% of ₹92 L) at 8.5% for 20 years. Ask your bank for its rate.

What new homes in Baner usually ask

  • 2 BHK about ₹90 L – ₹1.3 Cr (32 projects)
  • 3 BHK about ₹1.5 – 2.1 Cr (42 projects)
  • 4 BHK about ₹2.5 – 3.5 Cr (25 projects)
  • 4.5 BHK about ₹3 – 4.75 Cr (8 projects)

Our own guide: the middle half of the starting prices we have read for projects being sold in Baner, rounded. Use it to judge an offer, not as a price.

Baner average ₹14,212/sq ft across 23 projectsThe middle asking price per sq ft of other projects in Baner.

Ask about this project

Outside our main East Pune areas: the Avasetu team finds out what it can.

Send your question

Floor plans

We send them to you on WhatsApp

Location

A map search by name. Open the map (opens in a new tab)

Around VTP Verve

Measured from the Baner centre, each with its source and date.

ToBy road9 am6 pm, back
Baner-Balewadi offices (Balewadi High Street)0.7 km2-4 min5-12 min
Hinjawadi Phase 1 (Rajiv Gandhi Infotech Park)7.2 km20-36 min24-49 min
Hinjawadi Phase 2 (Rajiv Gandhi Infotech Park)11.5 km28-50 min29-58 min
Hinjawadi Phase 3 (Rajiv Gandhi Infotech Park)14.5 km32-57 min32-55 min
Pune Airport (Lohegaon)26.3 km59-102 min66-116 min

Driving from the Baner centre on a weekday, Google's typical traffic. Source: Google Maps (Routes API), typical weekday traffic · measured 28 Nov 2026

What's changing nearby

  • PMC bridges and flyovers due in 2027The Pune Municipal Corporation expects four to five bridges and flyovers to be finished by the end of December 2026 and opened in early 2027, among them the Sadhu Vaswani bridge (likely January 2027) and the Ghorpadi flyover, about 90% built. Another bridge is due in March 2027.Status of 19 Nov 2026
  • Metro Line 3 (Hinjawadi to Shivajinagar)Open: passenger trains run between Hinjawadi and District Court at 17 of the 23 stations, after the inauguration on 3 November. The other six, including Baner's and Shivajinagar, are to open in stages by January 2027.Status of 4 Nov 2026

Being built around it

228 projects with 31,252 homes being built within 2 km, due 2026 to 2033.

From MahaRERA's register. Source: MahaRERA project register (our copy, read daily) · measured 28 Nov 2026

9 schools within 3 km: 5 CBSE, 4 ICSE.

Straight-line distance from the Baner centre. No fees or ratings: they are rarely published reliably. Sources: CBSE affiliated schools (SARAS), CISCE school locator, Google Maps (school positions) · measured 29 Nov 2026

Asked rent

Rent in Baner

Asked rent, from 125 listings, Nov 2026

SizeA monthMiddleListingsYield
1 BHK₹20,000 to ₹27,000₹24,00032
2 BHK₹32,500 to ₹40,000₹35,500463.7%
3 BHK₹48,000 to ₹75,000₹65,000474.2%

What owners ask on listings, not what tenants pay; the middle half of asks. Yield: a year's middle rent over the middle asking price for that size. Sources: MagicBricks rent listings, NoBroker rent listings, Square Yards rent listings, Asking prices of new projects (Avasetu project pages) · measured 28 Nov 2026

Amenities

Last checked 4 Nov 2026.

MahaRERA record

From MahaRERA, read 27 Nov 2026

Possession date

30 Apr 2030

Completion date filed with MahaRERA. At registration: 30 Jun 2026. Moved 42 months later, 4 of them by MahaRERA's August 2026 order for most projects.

Ask for the possession date in writing in your agreement for sale.

VTP Verve: what changed, as we read it

Homes booked went from 644 to 643 between 13 Oct 2026 and 12 Nov 2026 (MahaRERA shows cancellations this way), of 701 homes.

13 Oct 202612 Nov 2026
  • 12 Nov 2026: 643 booked
  • 13 Oct 2026: 644 booked

Read by Avasetu from MahaRERA on each date shown. MahaRERA shows only the latest figures, so earlier ones are our own readings.

Beside other Baner projects

Worked out by Avasetu
Homes booked
92%
The middle of 21 Baner projects registered within a year of it: 70%.
Completion date
Moved 42 months later
41 of 189 Baner projects being built moved theirs 3 months or more.

From MahaRERA records read 27 Nov 2026. Homes booked are the builders' own quarterly counts. Dates net of MahaRERA's August 2026 order.

The record

Homes booked
643 of 701
Towers
6 in this registration
The tallest has 35 floors.
Registered on
28 Oct 2021
MahaRERA registration
P52100031556
Listed or updated on MahaRERA 14 Nov 2026.
Promoter (builder)
Prasanna Developers
Project type
Residential / Group Housing
Pincode
411045

Open the MahaRERA record (opens in a new tab)

Check before you book

From MahaRERA
  • The builder has moved the completion date 42 months later since registration, from Jun 2026 to Apr 2030 (MahaRERA's 2026 blanket extension for all projects left out). Ask why, and which date goes in your agreement for sale.
  • Towers go up to 35 floors. Ask how many lifts serve your tower and how many homes share them.

Tower by tower

6 buildings

Buildings

From MahaRERA
BuildingFloorsHomesOther
Tower 1480
Tower 2351150
Tower 3351750
Tower 4351130
Tower 5351750
Tower 6351150

As filed with MahaRERA (sanctioned floors).

What the builder's and property sites say

Gathered and checked
Floors per tower (highest)
up to 30 floors
From the builder's site

Last checked 4 Nov 2026. MahaRERA counts where they differ.

VTP Realty: track record

From MahaRERA records

VTP Realty has 50 projects in our MahaRERA register for Pune. 27 of 50 with both dates moved the completion date 3 months or more later, by 20 months on average.

All 50 projects by VTP Realty in Pune

Planning to buy here?

Ask about prices, floor plans, offers or a site visit.

Other projects in Baner

More by Prasanna Developers

FAQ

What is the price of VTP Verve?

3 BHK: ₹92 L to ₹1.17 Cr, checked on 4 Nov 2026. Builders change prices often and add parking and other charges: ask for the current price sheet before you book.

What is the possession date of VTP Verve?

The completion date filed with MahaRERA is 30 Apr 2030. At registration it was 30 Jun 2026. MahaRERA added 4 months to most projects' dates in August 2026 (Order 66/2026). Ask the builder for the possession date in your agreement, in writing.

What is the MahaRERA number of VTP Verve?

VTP Verve is registered with MahaRERA as P52100031556.

How many towers and floors does VTP Verve have?

MahaRERA lists 6 buildings, the tallest with 35 floors.

How many flats are there in VTP Verve?

MahaRERA lists 701 units.

How many homes in VTP Verve are booked?

643 of 701 homes were booked as per MahaRERA on 27 Nov 2026.

Who is the builder of VTP Verve?

The promoter registered with MahaRERA is Prasanna Developers. Our register has 50 Pune projects by VTP Realty; 27 of 50 with both dates moved their completion date 3 months or more later.

Where is VTP Verve?

VTP Verve is in Mulshi, Pune district (pincode 411045).

Sources
  • Registration, promoter, pincodeFrom MahaRERA

    MahaRERA listing, updated 14 Nov 2026

  • Dates and homes bookedFrom MahaRERA

    Checked 5 Nov 2026

  • Buildings and wingsFrom MahaRERA

    Checked 5 Nov 2026

  • Location and nearbyNot checked yet

    Still checking

  • DescriptionGathered and checked

    Checked 5 Nov 2026

  • PricesGathered and checked

    The builder's site, or two property sites that agree (4 Nov 2026)

  • Project facts and amenitiesGathered and checked

    The builder's site and property sites, which can be wrong: where they differ from MahaRERA, MahaRERA counts (4 Nov 2026)

Get the price sheet and floor plans for VTP Verve

The Avasetu team calls or WhatsApps you back; we never share your number without your OK.

What would you like?

BHK

Add budget, move-in or a note (optional)

Skip anything you like. It only helps with better options.

Budget

Move in

Payment