Kohinoor Satori Mahalunge
by Kohinoor Group · Mahalunge, Mulshi, Pune district · 411045
- Homes
- 3, 4, 4.5 BHK
- Price
- from ₹1.6 Cr
- EMI about ₹1.11 L a month
- Possession
- Apr 2030
- completion filed with MahaRERA
- Booked
- 200 of 448
What stands out
As of 19 Nov 2026, from MahaRERA and the sources below.
- Buyers have reserved 200 of the 448 homes currently registered in the project.
- The completion date filed with MahaRERA is 30 Apr 2030, while the first date filed at registration was 31 Dec 2028.
- Out of 35 Kohinoor Group projects in Pune with both dates on MahaRERA, 10 moved the completion date 3 months or more later.
Updated 5 Nov 2026
Pictures
From the builder's website. Renders are the builder's artist's impressions and plans are indicative: check the sanctioned plans before you book.
Price
3 BHK
₹1.6 Cr – ₹1.9 Cr
from 1,121 sq ft · ₹14,273/sq ft
Last checked 5 Nov 2026
All-in cost of the 3 BHK at ₹1.6 Cr: about ₹1.79 Cr
Price (agreement value) ₹1.6 Cr GST (5%) ₹8 L Stamp duty (7%) ₹11.2 L Registration (1%, at most ₹30,000) ₹30,000 Total before the builder's charges ₹1.79 Cr 4 BHK
From ₹3.1 Cr
from 2,090 sq ft · ₹14,833/sq ft
Last checked 5 Nov 2026
All-in cost of the 4 BHK at ₹3.1 Cr: about ₹3.48 Cr
Price (agreement value) ₹3.1 Cr GST (5%) ₹15.5 L Stamp duty (7%) ₹21.7 L Registration (1%, at most ₹30,000) ₹30,000 Total before the builder's charges ₹3.48 Cr 4.5 BHK
From ₹3.4 Cr
from 2,326 sq ft · ₹14,617/sq ft
Last checked 5 Nov 2026
All-in cost of the 4.5 BHK at ₹3.4 Cr: about ₹3.81 Cr
Price (agreement value) ₹3.4 Cr GST (5%) ₹17 L Stamp duty (7%) ₹23.8 L Registration (1%, at most ₹30,000) ₹30,000 Total before the builder's charges ₹3.81 Cr
Starting prices; tower, floor, parking and floor-rise change the final price. Not included: parking, club house, maintenance deposit, legal and society charges. They differ by project: ask the builder for the full cost sheet. If a price already includes GST or stamp duty, do not add them twice.
EMI on the lowest price, as an example: about ₹1.11 L a monthOn a ₹1.28 Cr loan (80% of ₹1.6 Cr) at 8.5% for 20 years. Ask your bank for its rate.
Ask about this project
Outside our main East Pune areas: the Avasetu team finds out what it can.
Floor plans
Location
A map search by name. Open the map (opens in a new tab)
Project facts
- Comprises a total of 7 towers.
Amenities
- Provides ample car parking.
Last checked 5 Nov 2026.
MahaRERA record
From MahaRERA, read 19 Nov 2026Possession date
30 Apr 2030
Completion date filed with MahaRERA. At registration: 31 Dec 2028. Moved 12 months later, 4 of them by MahaRERA's August 2026 order for most projects.
Ask for the possession date in writing in your agreement for sale.
The record
- Homes booked
- 200 of 448
- Towers
- 6 in this registration
- The tallest has 23 floors. 7 in the whole project.
- Units
- 448
- 321 homes, 127 shops or offices.
- Registered on
- 11 Jun 2024
- MahaRERA registration
- P52100066472
- Listed or updated on MahaRERA 20 Aug 2026.
- Promoter (builder)
- Intofinity Promoters Private Limited
- Project type
- Others
- Pincode
- 411045
Check before you book
From MahaRERA- The builder has moved the completion date 12 months later since registration, from Dec 2028 to Apr 2030 (MahaRERA's 2026 blanket extension for all projects left out). Ask why, and which date goes in your agreement for sale.
- 127 shops or offices are part of the project. Ask where they open and whether their visitors use the residents' gate.
Tower by tower
6 buildings
Buildings
From MahaRERA| Building | Floors | Homes | Other |
|---|---|---|---|
| TOWER A1 | 12 | 26 | 21 |
| TOWER B1 | 23 | 70 | 24 |
| TOWER B2 | 23 | 74 | 21 |
| TOWER B3 | 23 | 74 | 21 |
| TOWER A2 | 23 | 77 | 24 |
| TOWER F | 19 | 0 | 16 |
As filed with MahaRERA (sanctioned floors).
What the builder's and property sites say
Gathered and checked- Land
- 6 acres
Last checked 5 Nov 2026. MahaRERA counts where they differ.
Kohinoor Group: track record
From MahaRERA recordsKohinoor Group has 36 projects in our MahaRERA register for Pune. 11 of 36 with both dates moved the completion date 3 months or more later, by 24 months on average.
- KOHINOOR BLISSPARKcompletion filed 31 Dec 2018, moved 6 months later
- Kohinoor Shangrila Phase Icompletion filed 31 Dec 2018, moved 12 months later
- KOHINOOR IRIS PARKcompletion filed 31 Dec 2019
- Jai Ganesh Vision Commercial Wing Acompletion filed 30 Jan 2021, moved 18 months later
- SUBHASHREE RESIDENTIAL PHASE IIIcompletion filed 30 Jan 2021, moved 18 months later
- KOHINOOR BEGONIA PHASE IIIcompletion filed 30 Dec 2021, moved 24 months later
- SHUBHAM GALLERIAcompletion filed 30 Oct 2022, moved 21 months later
- Kohinoorcompletion filed 30 Mar 2023
- OLIVE BLISScompletion filed 31 Dec 2023, moved 56 months later
- KOHINOOR GRANDEURcompletion filed 30 Mar 2024
- KOHINOOR JEEVAcompletion filed 30 Jun 2024
- KOHINOOR EMERALD 1completion filed 30 Sep 2024
- KOHINOOR CORALcompletion filed 30 Dec 2024
- KOHINOOR SAPPHIREcompletion filed 30 Dec 2024
- Kohinoor Heights IIcompletion filed 31 Dec 2025
- KOHINOOR WORLD TOWER PHASE 1completion filed 30 Jun 2026
- SHUBHAM GALLERIA PH-2completion filed 31 Jul 2026, moved 15 months later
- S3 LIFESTYLEcompletion filed 30 Nov 2026, moved 66 months later
- KOHINOOR VIVA PIXEL- PHASE Icompletion filed 30 Sep 2027, moved 11 months later
- Kohinoor City I and Kohinoor City IIcompletion filed 30 Apr 2028
- Kohinoor Kaleidocompletion filed 30 Apr 2028
- KOHINOOR RIVERDALEcompletion filed 31 Dec 2028
- Kohinoor Business Towercompletion filed 31 Dec 2028
- KOHINOOR FAMVILLEcompletion filed 30 Apr 2029
- Kohinoor Central Park - Phase 1completion filed 30 Apr 2029
- Kohinoor Westview Reservecompletion filed 30 Apr 2029
- Kohinoor Westview Reserve-IIcompletion filed 30 Apr 2029
- Kohinoor A/Ccompletion filed 28 Jun 2029
- Kohinoor Bcompletion filed 28 Jun 2029
- KOHINOOR WOODSHIREcompletion filed 31 Dec 2029
Planning to buy here?
Ask about prices, floor plans, offers or a site visit.
Other projects in Mahalunge
More by Intofinity Promoters Private Limited
- Kohinoor Riverdale2, 3 BHK · from ₹97.5 L · possession Dec 2028
- Kohinoor Woodshirepossession Dec 2029
- Kohinoor Avantarapossession Jul 2032
- Kohinoor Central Park2, 3 BHK · from ₹88 L · possession Apr 2029
- Kohinoor Kaleido2, 3 BHK · from ₹91.4 L · possession Apr 2028
- Kohinoor Royale Towerspossession Apr 2031
FAQ
What is the price of Kohinoor Satori Mahalunge?
3 BHK: ₹1.6 Cr to ₹1.9 Cr; 4 BHK: ₹3.1 Cr; 4.5 BHK: ₹3.4 Cr, checked on 5 Nov 2026. Builders change prices often and add parking and other charges: ask for the current price sheet before you book.
What is the possession date of Kohinoor Satori Mahalunge?
The completion date filed with MahaRERA is 30 Apr 2030. At registration it was 31 Dec 2028. MahaRERA added 4 months to most projects' dates in August 2026 (Order 66/2026). Ask the builder for the possession date in your agreement, in writing.
What is the MahaRERA number of Kohinoor Satori Mahalunge?
Kohinoor Satori Mahalunge is registered with MahaRERA as P52100066472.
How many towers and floors does Kohinoor Satori Mahalunge have?
MahaRERA lists 6 buildings, the tallest with 23 floors.
How many flats are there in Kohinoor Satori Mahalunge?
MahaRERA lists 448 units (321 residential, 127 other).
How many homes in Kohinoor Satori Mahalunge are booked?
200 of 448 homes were booked as per MahaRERA on 19 Nov 2026.
Who is the builder of Kohinoor Satori Mahalunge?
The promoter registered with MahaRERA is Intofinity Promoters Private Limited. Our register has 36 Pune projects by Kohinoor Group; 11 of 36 with both dates moved their completion date 3 months or more later.
Where is Kohinoor Satori Mahalunge?
Kohinoor Satori Mahalunge is in Mulshi, Pune district (pincode 411045).
Sources
- Registration, promoter, pincodeFrom MahaRERA
MahaRERA listing, updated 20 Aug 2026
- Dates and homes bookedFrom MahaRERA
Checked 5 Nov 2026
- Buildings and wingsFrom MahaRERA
Checked 5 Nov 2026
- Location and nearbyNot checked yet
Still checking
- DescriptionGathered and checked
Checked 5 Nov 2026
- PricesGathered and checked
The builder's site, or two property sites that agree (5 Nov 2026)
- Project facts and amenitiesGathered and checked
The builder's site and property sites, which can be wrong: where they differ from MahaRERA, MahaRERA counts (5 Nov 2026)
Get the price sheet and floor plans for Kohinoor Satori Mahalunge
The Avasetu team calls or WhatsApps you back; we never share your number without your OK.