Pune MahaRERA tracker

New home projects registered with MahaRERA in the Pune areas we cover: how many there are, how many homes are booked and when they are due to complete.

As of . Source: MahaRERA public records.

MahaRERA-registered projects by Pune area, as of 29 November 2026
AreaProjectsHomes bookedDue 2026Due 2027
Kharadi289n/a1522
Upper Kharadi43n/a27
Wagholi343n/a1849
Lohegaon206n/a1626
Keshav Nagar8n/a00
Hinjawadi35n/a03
Wakad12n/a02
Baner19n/a42
All areas955n/a55111

“n/a”: MahaRERA did not give booked homes for every project in that area, so no total is shown rather than a partial one.

Possession dates that moved

As of 29 November 2026, the builders of 52 of 257 home projects still being built in these areas (20%) have moved their filed completion date 3 months or more later than at registration, not counting the 4 months MahaRERA added to most projects in August 2026 (Order 66/2026).

Home projects being built whose possession date moved, by Pune area, as of 29 November 2026
AreaBeing builtMoved by the builderUsual moveOnly MahaRERA's extension
Kharadi5311 (21%)12 months31
Upper Kharadi201 (5%)3 months18
Wagholi9826 (27%)29 months60
Lohegaon6711 (16%)24 months37
Keshav Nagar60 (0%)–6
Hinjawadi40 (0%)–3
Wakad51 (20%)12 months1
Baner42 (50%)12 months1
All areas25752 (20%)157

“Usual move” is the middle move among the projects whose date moved. Each project counts once, however many towers it registered.

The biggest moves

  • Pavilion 2 (Kharadi): filed for 31 March 2019 at registration, now 31 July 2028, 108 months later by the builderMahaRERA P52100003546
  • Pankaj Aasmaan Phase II (Lohegaon): filed for 31 December 2019 at registration, now 30 April 2028, 96 months later by the builderMahaRERA P52100005649
  • Nishigandh 1 (Kharadi): filed for 31 March 2019 at registration, now 30 April 2027, 93 months later by the builderMahaRERA P52100013723
  • Defence Colony Pune Phase4 (Wagholi): filed for 31 December 2018 at registration, now 30 November 2026, 91 months later by the builderMahaRERA P52100009756
  • Sai Sankul (Wagholi): filed for 15 April 2019 at registration, now 10 March 2027, 90 months later by the builderMahaRERA P52100011321
  • Nivaan Medows (Wagholi): filed for 31 October 2019 at registration, now 30 April 2027, 86 months later by the builderMahaRERA P52100020464
  • Dream Horizon (Lohegaon): filed for 28 November 2022 at registration, now 30 April 2028, 61 months later by the builderMahaRERA P52100020037
  • Chandan Heritage (Lohegaon): filed for 31 December 2021 at registration, now 30 January 2027, 57 months later by the builderMahaRERA P52100017547

How these numbers are made

  • Every project MahaRERA lists under each area's pincodes or name is read from its public project pages, and read again when MahaRERA marks it changed.
  • “Due” is the completion date the developer has currently filed with MahaRERA. Filed dates can move; each project's page shows both the first and the current date.
  • Nothing is estimated: a figure MahaRERA did not publish for every project is left out.

Use these figures

Journalists, bloggers and agents are welcome to quote this page. Please credit and link it:

Source: Avasetu Pune MahaRERA tracker (https://avasetu.in/pune-maharera-tracker), from MahaRERA public records, as of 29 November 2026.