Pune MahaRERA tracker
New home projects registered with MahaRERA in the Pune areas we cover: how many there are, how many homes are booked and when they are due to complete.
As of . Source: MahaRERA public records.
| Area | Projects | Homes booked | Due 2026 | Due 2027 |
|---|---|---|---|---|
| Kharadi | 289 | n/a | 15 | 22 |
| Upper Kharadi | 43 | n/a | 2 | 7 |
| Wagholi | 343 | n/a | 18 | 49 |
| Lohegaon | 206 | n/a | 16 | 26 |
| Keshav Nagar | 8 | n/a | 0 | 0 |
| Hinjawadi | 35 | n/a | 0 | 3 |
| Wakad | 12 | n/a | 0 | 2 |
| Baner | 19 | n/a | 4 | 2 |
| All areas | 955 | n/a | 55 | 111 |
“n/a”: MahaRERA did not give booked homes for every project in that area, so no total is shown rather than a partial one.
Possession dates that moved
As of 29 November 2026, the builders of 52 of 257 home projects still being built in these areas (20%) have moved their filed completion date 3 months or more later than at registration, not counting the 4 months MahaRERA added to most projects in August 2026 (Order 66/2026).
| Area | Being built | Moved by the builder | Usual move | Only MahaRERA's extension |
|---|---|---|---|---|
| Kharadi | 53 | 11 (21%) | 12 months | 31 |
| Upper Kharadi | 20 | 1 (5%) | 3 months | 18 |
| Wagholi | 98 | 26 (27%) | 29 months | 60 |
| Lohegaon | 67 | 11 (16%) | 24 months | 37 |
| Keshav Nagar | 6 | 0 (0%) | – | 6 |
| Hinjawadi | 4 | 0 (0%) | – | 3 |
| Wakad | 5 | 1 (20%) | 12 months | 1 |
| Baner | 4 | 2 (50%) | 12 months | 1 |
| All areas | 257 | 52 (20%) | 157 |
“Usual move” is the middle move among the projects whose date moved. Each project counts once, however many towers it registered.
The biggest moves
- Pavilion 2 (Kharadi): filed for 31 March 2019 at registration, now 31 July 2028, 108 months later by the builderMahaRERA P52100003546
- Pankaj Aasmaan Phase II (Lohegaon): filed for 31 December 2019 at registration, now 30 April 2028, 96 months later by the builderMahaRERA P52100005649
- Nishigandh 1 (Kharadi): filed for 31 March 2019 at registration, now 30 April 2027, 93 months later by the builderMahaRERA P52100013723
- Defence Colony Pune Phase4 (Wagholi): filed for 31 December 2018 at registration, now 30 November 2026, 91 months later by the builderMahaRERA P52100009756
- Sai Sankul (Wagholi): filed for 15 April 2019 at registration, now 10 March 2027, 90 months later by the builderMahaRERA P52100011321
- Nivaan Medows (Wagholi): filed for 31 October 2019 at registration, now 30 April 2027, 86 months later by the builderMahaRERA P52100020464
- Dream Horizon (Lohegaon): filed for 28 November 2022 at registration, now 30 April 2028, 61 months later by the builderMahaRERA P52100020037
- Chandan Heritage (Lohegaon): filed for 31 December 2021 at registration, now 30 January 2027, 57 months later by the builderMahaRERA P52100017547
How these numbers are made
- Every project MahaRERA lists under each area's pincodes or name is read from its public project pages, and read again when MahaRERA marks it changed.
- “Due” is the completion date the developer has currently filed with MahaRERA. Filed dates can move; each project's page shows both the first and the current date.
- Nothing is estimated: a figure MahaRERA did not publish for every project is left out.
Use these figures
Journalists, bloggers and agents are welcome to quote this page. Please credit and link it:
Source: Avasetu Pune MahaRERA tracker (https://avasetu.in/pune-maharera-tracker), from MahaRERA public records, as of 29 November 2026.
HTML for a website:
<a href="https://avasetu.in/pune-maharera-tracker">Avasetu Pune MahaRERA tracker</a>