Godrej River Crest, Manjari
by Godrej Properties · Manjari, Haveli, Pune district · 412307
- Possession
- Jun 2030
- completion filed with MahaRERA
- Booked
- 88 of 216
What stands out
As of 20 Nov 2026, from MahaRERA and the sources below.
- 41% of homes booked: MahaRERA shows 88 of 216 homes booked.
- Buildings in this registration: 2, up to 46 floors.
- 41% booked here; the middle of 15 Manjari projects registered within a year of it is 17%.
- Compared with other projects still being built in Manjari: Compared with other projects still being built in Manjari: its tallest building is higher than that of 11 of 11.
- Completion date filed with MahaRERA: 15 Jun 2030.
Updated 22 Nov 2026
Pictures
From the builder's website. Renders are the builder's artist's impressions and plans are indicative: check the sanctioned plans before you book.
Price
No price for Godrej River Crest is published yet.
What new homes in Manjari usually ask
- 2 BHK about ₹65 – 80 L (7 projects)
- 3 BHK about ₹90 L – ₹1.2 Cr (6 projects)
Our own guide: the middle half of the starting prices we have read for projects being sold in Manjari, rounded. Use it to judge an offer, not as a price.
Manjari average ₹9,668/sq ft across 3 projectsThe middle asking price per sq ft of other projects in Manjari.
Ask about this project
Outside our main East Pune areas: the Avasetu team finds out what it can.
Floor plans
Location
Position checkedThe project's pin on Google Maps, checked against its MahaRERA name and pincode. Open the map (opens in a new tab)
Godrej River Crest, year by year, up close
Sharp satellite pictures taken in Nov 2022, Jan 2024, Jan 2025 and Apr 2026, centred on the project's map pin, about 580 m across at about 0.5 m a pixel.
Nov 2022 Jan 2024 Jan 2025 Apr 2026 · latest
Each picture is dated by when it was taken; the ring is 100 m around the pin. Map image is the intellectual property of Esri and is used herein under license. Copyright © 2026 Esri and its licensors (imagery: Maxar, Vantor). All rights reserved. Compare every release ↗
Work hubs
- EON IT Park, Kharadi3.6 km
- World Trade Center, Kharadi3.6 km
- Magarpatta City5.9 km
- Pune Airport (Lohegaon)8.8 km
Nearby
- Railway stationManjari Budruk2.9 km
- SchoolThe Orbis School, Keshav Nagar, Pune (CBSE)3.1 km
- Industrial areaEon IT Park Pune3.3 km
- TempleRenuka Mata Mandir3.5 km
- Industrial areaInternational Tech Park Pune, Kharadi3.7 km
Straight-line distances; the drive is longer. Places: Google Maps.
MahaRERA record
From MahaRERA, read 20 Nov 2026Possession date
15 Jun 2030
Completion date filed with MahaRERA. At registration: 30 Jun 2029. Moved 7 months later, 4 of them by MahaRERA's August 2026 order for most projects.
Ask for the possession date in writing in your agreement for sale.
Beside other Manjari projects
Worked out by Avasetu- Homes booked
- 41%
- The middle of 13 Manjari projects registered within a year of it: 47%.
- Completion date
- Moved 7 months later
- 11 of 36 Manjari projects being built moved theirs 3 months or more.
From MahaRERA records read 20 Nov 2026. Homes booked are the builders' own quarterly counts. Dates net of MahaRERA's August 2026 order.
The record
- Homes booked
- 88 of 216
- Towers
- 2 in this registration
- The tallest has 46 floors.
- Units
- 216
- 208 homes, 8 shops or offices.
- Registered on
- 23 Jul 2024
- MahaRERA registration
- P52100077127
- Listed or updated on MahaRERA 14 Aug 2026.
- Promoter (builder)
- Manjari Housing Projects LLP
- Project type
- Others
- Pincode
- 412307
Check before you book
From MahaRERA- The builder has moved the completion date 7 months later since registration, from Jun 2029 to Jun 2030 (MahaRERA's 2026 blanket extension for all projects left out). Ask why, and which date goes in your agreement for sale.
- Towers go up to 46 floors. Ask how many lifts serve your tower and how many homes share them.
Tower by tower
2 buildings
Buildings
From MahaRERA| Building | Floors | Homes | Other |
|---|---|---|---|
| Tower 1 | 46 | 104 | 4 |
| Tower 2 | 46 | 104 | 4 |
As filed with MahaRERA (sanctioned floors).
Godrej Properties: track record
From MahaRERA recordsGodrej Properties has 39 projects in our MahaRERA register for Pune. 16 of 39 with both dates moved the completion date 3 months or more later, by 21 months on average.
- Godrej Infinitycompletion filed 30 Sep 2020
- Godrej Pranacompletion filed 30 Sep 2020
- Godrej 24completion filed 30 Sep 2022
- Godrej Elementscompletion filed 30 Dec 2022
- Godrej Wood Parkcompletion filed 30 Nov 2023
- Godrej Rejuvecompletion filed 30 Mar 2024
- Godrej Hillside 1completion filed 30 Oct 2024
- Godrej Hillside 2completion filed 30 Oct 2024
- GODREJ BOULEVARDcompletion filed 30 Sep 2025
- Godrej Parkridgecompletion filed 30 Sep 2025
- Godrej Eden Estate Phase 2completion filed 4 Feb 2026, moved 13 months later
- Godrej Green Vistascompletion filed 30 May 2026, moved 11 months later
- Godrej Greenscompletion filed 30 Sep 2026, moved 44 months later
- Godrej Green Covecompletion filed 30 Oct 2026, moved 15 months later
- Godrej Hill Retreatcompletion filed 31 Dec 2026, moved 8 months later
- Godrej Meadowscompletion filed 31 Dec 2026, moved 8 months later
- Godrej Sky Greens Phase 1completion filed 31 Dec 2026, moved 5 months later
- GODREJ CARNIVALcompletion filed 30 Jan 2027, moved 12 months later
- Godrej Nurturecompletion filed 30 Jan 2027, moved 24 months later
- MADHUBANcompletion filed 30 Jan 2027, moved 12 months later
- Godrej Hill Retreat 2completion filed 28 Mar 2027
- GODREJ WOODSVILLEcompletion filed 30 Mar 2027
- Mamurdi MHADA Northcompletion filed 30 Jul 2027, moved 36 months later
- Godrej Urban Retreatcompletion filed 11 Oct 2027
- GODREJ SERENEcompletion filed 30 Oct 2027
- FOREST GROVE AT GODREJ PARK GREENScompletion filed 30 Jan 2028, moved 30 months later
- SPARKLE AT GODREJ SERENEcompletion filed 30 Apr 2028
- Godrej Hillside 3completion filed 28 Jun 2028
- Godrej Park Greenscompletion filed 30 Jul 2028, moved 48 months later
- Godrej Emerald Waterscompletion filed 28 Jun 2029, moved 11 months later
Planning to buy here?
Ask about prices, floor plans, offers or a site visit.
Other projects in Manjari
More by Manjari Housing Projects LLP
FAQ
What is the price of Godrej River Crest?
No price for Godrej River Crest is published yet. Ask through the enquiry form on this page for the current price.
What is the possession date of Godrej River Crest?
The completion date filed with MahaRERA is 15 Jun 2030. At registration it was 30 Jun 2029. MahaRERA added 4 months to most projects' dates in August 2026 (Order 66/2026). Ask the builder for the possession date in your agreement, in writing.
What is the MahaRERA number of Godrej River Crest?
Godrej River Crest is registered with MahaRERA as P52100077127.
How many towers and floors does Godrej River Crest have?
MahaRERA lists 2 buildings, the tallest with 46 floors.
How many flats are there in Godrej River Crest?
MahaRERA lists 216 units (208 residential, 8 other).
How many homes in Godrej River Crest are booked?
88 of 216 homes were booked as per MahaRERA on 20 Nov 2026.
Who is the builder of Godrej River Crest?
The promoter registered with MahaRERA is Manjari Housing Projects LLP. Our register has 39 Pune projects by Godrej Properties; 16 of 39 with both dates moved their completion date 3 months or more later.
Where is Godrej River Crest?
Godrej River Crest is in Haveli, Pune district (pincode 412307).
Which school is nearest to Godrej River Crest?
The Orbis School, Keshav Nagar, Pune (CBSE), about 3.1 km away in a straight line from the map position; the drive is longer.
Which railway station is nearest to Godrej River Crest?
Manjari Budruk, about 2.9 km away in a straight line from the map position; the drive is longer.
How far is Godrej River Crest from Pune Airport?
About 8.8 km in a straight line from the map position; the drive is longer.
How far is Godrej River Crest from EON IT Park, Kharadi?
About 3.6 km in a straight line from the map position; the drive is longer. It is the nearest of Pune's main work hubs to Godrej River Crest.
Sources
- Registration, promoter, pincodeFrom MahaRERA
MahaRERA listing, updated 14 Aug 2026
- Dates and homes bookedFrom MahaRERA
Checked 9 Nov 2026
- Buildings and wingsFrom MahaRERA
Checked 9 Nov 2026
- Location and nearbyGathered and checked
Checked 9 Nov 2026
- DescriptionGathered and checked
Checked 9 Nov 2026